Colchester Interceptor System Im provem ents Project Community - - PowerPoint PPT Presentation

colchester interceptor system im provem ents project
SMART_READER_LITE
LIVE PREVIEW

Colchester Interceptor System Im provem ents Project Community - - PowerPoint PPT Presentation

Colchester Interceptor System Im provem ents Project Community Meeting #2 July 24, 2017 SA Project Manager: Debbie J. Maxwell, P.E., CCM Design Engineer: Michael Baker International, Inc. Construction Management: Arcadis U.S., Inc.


slide-1
SLIDE 1

Colchester Interceptor System Im provem ents Project

Community Meeting #2 July 24, 2017

SA Project Manager:

Debbie J. Maxwell, P.E., CCM

Design Engineer:

Michael Baker International, Inc.

Construction Management:

Arcadis U.S., Inc.

Construction Contractor:

Garney Companies, Inc.

slide-2
SLIDE 2

Agenda

Purpose of the Project

Overview of the Limits of Service Definitions Purpose and Benefits of the Project

Existing System Conditions Proposed System Improvements

Project Details

Site Activities & Notes of Interest Anticipated Construction Schedule Contacts Q&A

slide-3
SLIDE 3

Purpose of the Project

Limits of Service

7 Service Areas Numerous Lift Stations Miles of Gravity Sewers Miles of Force Mains

Featherstone Lift Station H.L. Mooney Water Reclamation Facility Project Limits Belmont Lift Station

slide-4
SLIDE 4

Purpose of the Project

Definitions

Gravity Sewer Lines

Sewer lines constructed to allow the wastewater to flow based

  • n a downward slope

Interceptor Sewers

Gravity Sewer mains which receive the flow from collector sewers and conveys the wastewater to treatment facilities

Lift Station

A gravity sewer sump with a pump to lift accumulated sewage to a higher elevation

Force Mains

A pressurized sewer line to convey wastewater from a lift station to another service level and gravity sewer

slide-5
SLIDE 5

Purpose of the Project

Purpose of the Project

Replace an existing and aged Interceptor Sewer System Increase system capacity Reduce or eliminate stormwater and groundwater from entering the system

Benefits of the Project

Provide environmental benefits by relief of potential surcharge conditions Maintain service reliability

slide-6
SLIDE 6

Existing System Conditions

Featherstone Lift Station Belmont Lift Station Colchester Road Gravity Sew er Discharge Belmont Force Main 48” Interceptor Sew er

slide-7
SLIDE 7

Existing System Conditions

Approximately 7,600 linear feet of 36” - 48” gravity interceptor sewer Approximately 1,500 linear feet of 8” and 12” gravity sewer

slide-8
SLIDE 8

Proposed System Im provem ents

Install approximately 5,411 linear feet of 30” and 36” force main Replace approximately 2,132 linear feet of 48” gravity sewer with 54” gravity sewer Install approximately 1,530 linear feet of 8” and 12” gravity sewer Construct a new lift station

slide-9
SLIDE 9

Proposed System Im provem ents

Featherstone Lift Station Belmont Lift Station Colchester Road Gravity Sew er Discharge Belmont Force Main 54” Interceptor Sew er Marumsco Acres Lake Lift Station

slide-10
SLIDE 10

Proposed System Im provem ents

slide-11
SLIDE 11

Proposed System Im provem ents Marum sco Acres Lake Lift Station

slide-12
SLIDE 12

Proposed System Im provem ents Marum sco Acres Lake Lift Station

Lift Station Details

The building is 14’ x 14’ Brick siding Shingled roof The Station capacity is 350 gpm

Emergency diesel engine generator as back-up power Odor Control Carbon Filters Bioxide (calcium nitrate)

slide-13
SLIDE 13

Proposed System Im provem ents Marum sco Acres Lake Lift Station

slide-14
SLIDE 14

Site Activities

Activities

The Contractor will determine the final sequence of construction The Lift Station is limited to a 10 month construction period Open cutting of trenches

Force Mains and some gravity

Trenchless installation

Boring under Featherstone Road to avoid road closures

Microtunnelling for a portion of the 54” gravity main Installation of new manholes Tie-in of existing systems

slide-15
SLIDE 15

Notes of Interest

Construction Notes of Interest

Notifications will be provided by the Service Authority and the Contractor for any anticipated interruptions Access will not be interrupted

Emergency Services, school buses, trash, mail and other services will not be disrupted

Temporary parking areas will be coordinated with land

  • wners, the Department of Parks and Recreation, and

HOAs if needed by the Contractor prior to construction Daily clean-up by the Contractor is required A Service Authority Inspector will cover this project and

  • thers close by and will be on site on a daily basis

A Construction Manager / SA Project Representative will be onsite fulltime for the duration of the project

slide-16
SLIDE 16

Final Layout

Featherstone Lift Station Belmont Lift Station Colchester Road Gravity Sew er Discharge Belmont Force Main 54” Interceptor Sew er Marumsco Acres Lake Lift Station

Summary

Redirect flows to Belmont Lift Station Construct a new Lift Station Extend the force main Enlarge the gravity sewer size

Benefits

Increase system capacity Environmental benefits

Relief of potential surcharge conditions

Reduce or eliminate Inflow Improve system reliability

slide-17
SLIDE 17

Anticipated Construction Schedule

Project Duration

660 days / 21 months

Anticipated Start Date:

Award Contract in July 2017 Notice to Proceed in September 2017 On-site Construction start anticipated for October 2017

Anticipated End Date:

July 2019

Weekday Hours of Operations

7:00 a.m. to 5:00 p.m. Previously negotiated and approved night time hours

Certain business parcels

slide-18
SLIDE 18

Contacts

Community Relations & Outreach Liaison

Marlo Thomas Watson 571.285.8127 Email: colchester@pwcsa.org Project Specific Website: http://www.pwcsa.org/colchester-project

slide-19
SLIDE 19

Q & A

Any Questions?

slide-20
SLIDE 20

Proposed Layout