closedown event
play

Closedown Event Wednesday 28 February 2018 1 Introduction Paul - PowerPoint PPT Presentation

Closedown Event Wednesday 28 February 2018 1 Introduction Paul Marshall Innovation Project Manager 2 Housekeeping FIRE Main Q&A Fire alarms Mobile phones Breaks at end of day 3 Agenda Introduction Project overview Technology


  1. Closedown Event Wednesday 28 February 2018 1

  2. Introduction Paul Marshall Innovation Project Manager 2

  3. Housekeeping FIRE Main Q&A Fire alarms Mobile phones Breaks at end of day 3

  4. Agenda Introduction Project overview Technology Break 10.00 – 10:15am 10.15 – 10.45am 10.45 – 11.15am 11.15am – 11.45am Trials Customer engagement Summary & next steps Q&A 11.45am – 12.15pm 12.15pm – 12.45pm 12.45 – 12.50pm 12.50 – 1.00pm Lunch & close 4

  5. Our challenges Increasing Increasing customer customer expectations expectations Innovation Sustainability Affordability Changing energy usage Ageing assets 5

  6. Demand changes 2012 2025 Heat pump 14 14 Electric vehicle 12 12 TV Fridge 10 10 Demand (kW) Lights Washing machine 8 8 Dishwasher 6 6 4 4 2 2 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time of day 6

  7. Ageing assets Age profile of assets 450.0 400.0 350.0 Current replacement cost (£m) 300.0 250.0 200.0 150.0 100.0 50.0 - Estimated year of installation 7

  8. Opportunities New Smart meters New markets More open Storage technology regulation Access to more Demand side Provision of Automation data response Incentives response services Weezap 8

  9. Our strategy Offer new services and Maximise choice for the use of existing future assets Delivering Generate value to value for Innovative customers customers solutions ‘Fit and forget’ now to real problems Proven technology deployable today 9

  10. Innovation themes Safety & Network Capacity Efficiency Customer Commercial environment resilience service evolution Strive to Improve Maximise the Provide our Improve Change our continuously network use of existing existing customer role from improve safety performance assets to services at experience, network and reduce and reduce risk increase lower cost offer new operator to impact on the demand and services and system environment generation more choice operator capacity 10

  11. Project Overview Ben Ingham Innovation Engineer 11

  12. Background Historic networks LCTs create Customer Smart Street Conservation have no active network issues generation could stabilises voltage voltage reduction voltage regulation cause voltage to across the load Customer Stabilised voltage exceed statutory range and demand could can be lowered voltage limits optimises power cause voltage to making our flows dip below network and statutory limits customers’ appliances more efficient 12

  13. Project overview £11.5m, Started in Jan Trials period Extensive Quicker four-year 2014 and Jan 2016 – customer connection of innovation finishes in Apr Dec 2017 engagement LCTs project 2018 programme Lower energy throughout bills project Improved supply reliability 13

  14. Project review Four-month extension granted All Successful to project due to Will still be Delivery Reward equipment safety delivered within Criteria met modifications budget 14

  15. Outcomes A B C Monitored and Proven that Potential Associated actively techniques save deferment of carbon optimised energy reinforcement equivalent savings LV network First in the UK 15

  16. Project partners 16

  17. Technology Damien Coyle Innovation Technical Engineer 17

  18. Network overview Spectrum C C 2 C TC C W C 2 C CLASS L W W C L C 2 C C Capacity to Customers Capacitor WEEZAP LYNX On-load tap changer C 2 C C W L TC Builds on C 2 C and CLASS  Storage compatible  Transferable solutions 18

  19. System architecture 19

  20. Spectrum Power 5 Siemens network Optimisation Linked to CRMS via management module – DSSE/ ICCP link system VVC 20

  21. Learning points – system Integration with System Use of single line existing SCADA architecture diagram system 21

  22. Smart Street technology overview 50 end-point monitoring 498 Weezaps Three overhead devices 43 Lynx line HV capacitors Spectrum 5 (NMS) Five on-load tap 84 LV capacitors Three HV capacitors changing transformers 22

  23. Lynx and Weezap LV retrofit vacuum devices Telemetered back to central monitoring point Water Ingress issues with Lynx Comms issues 23

  24. Capacitors Used for voltage control only Issues with enclosure design System loadings not currently suitable for deployment 24

  25. On load tap changers (OLTCs) Nine tap positions with 2% per step Reset to nominal on comms blips Operated reliably throughout 25

  26. Learning points – general Cabinet design Communications Water ingress Enclosure size and location 26

  27. & QUESTIONS ANSWERS 27

  28. Break 28

  29. Trials Dr Geraldine Paterson Innovation Strategy & Transition Engineer 29

  30. Smart Street site selection Stage 1 Stage 2 Stage 3 Circuit simulation and refined Initial circuit screening Circuit classification circuit selection Use of existing Avoided areas Circuit types & Physical & HV network Identification of CLASS and C 2 C scheduled for customer types electrical modelling in IPSA / any thermal, assets asset replacement constraints DINIS voltage or fault Low carbon works level issues technology uptake LV inter- connection 30

  31. Smart Street site selection Stage 4 Stage 5 Network design methodology Final site selection Detailed combined Applied a range of Varied capacitor Modified the Final circuits Rules based design HV & LV network meshing scenarios sizes and locations demand profile selected methodology modelling applied Altered Developed rules transformer tap based settings methodology based on results 31

  32. Trial overview Six primary substations 67,000 customers Wigton & Egremont 11 HV circuits – five closable HV rings Three pole-mounted HV capacitors Three ground-mounted HV capacitors 38 distribution substations Five OLTC transformers Wigan & Leigh Manchester Five substation capacitors 79 LV circuit capacitors 32

  33. Trials overview Smart Street trial Test regime 1. On-load tap changing distribution transformer only 2. On-load tap changing distribution transformer and capacitor(s) on LV circuits LV voltage control 3. Capacitors at distribution substation only 4. Capacitors at distribution substation and on LV circuits 5. Capacitor(s) on LV circuits only 1. LV radial circuits LV network management & interconnection 2. LV interconnected circuits 1. Voltage controllers at primary substation only HV voltage control 2. Voltage controllers at primary substation and capacitor(s) on HV circuits 1. HV radial circuits HV network management & interconnection 2. HV interconnected circuits 1. Losses reduction Network configuration & voltage optimisation 2. Energy consumption reduction 33

  34. Initial trial design Two years Five trial techniques Two weeks on LV voltage control Two weeks off LV network management and One year’s worth of interconnection Smart Street data HV voltage control To be designed to HV network management and avoid placebo affect interconnection Five trial regimes to Network configuration and voltage test full effects optimisation 34

  35. Aims of trials Quantification of Validation of Identify potential benefits optimisation power quality and techniques customer side impacts 35

  36. Issues with initial trials Due to installation problems all Modified trial regime devices enabled when showed CVR working optimisation on ! Software issues led to a change in Further amendments to trial to get parameters best out of learning 36

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend