City to City Collaboration between Kawasaki city and DKI-JKT (Green - - PowerPoint PPT Presentation

city to city collaboration
SMART_READER_LITE
LIVE PREVIEW

City to City Collaboration between Kawasaki city and DKI-JKT (Green - - PowerPoint PPT Presentation

City to City Collaboration between Kawasaki city and DKI-JKT (Green Building) Seminar on the Joint Crediting Mechanism (JCM) Implementation in Indonesia 24 July, 2018 (Tue) Nippon Koei Co., Ltd. 1. Overview (1/2) 1-1. Outline of City to City


slide-1
SLIDE 1

Nippon Koei Co., Ltd.

24 July, 2018 (Tue)

Seminar on the Joint Crediting Mechanism (JCM) Implementation in Indonesia

City to City Collaboration between Kawasaki city and DKI-JKT (Green Building)

slide-2
SLIDE 2

2 24th July 2018 Seminar on the Joint Crediting Mechanism Implementation in Indonesia

  • 1. Overview (1/2)

1-1. Outline of City to City Collaboration between Kawasaki city and DKI-JKT

GOAL Period

Realization of sustainable low carbon society in DKI-JKT

► Phase1 : September 2017 – March 2018 ► Phase2 : April 2018 – March 2019

Main Activity

► Identify potential JCM

model projects in DKI-JKT

► Apply to JCM model

project based on a result of the

feasibility study (1) Feasibility Study for JCM project (2) City to City collaboration

► Transfer experiences or

knowledge each other

► Discuss together how to solve

environmental issues of DKI-JKT

slide-3
SLIDE 3

3 24th July 2018 Seminar on the Joint Crediting Mechanism Implementation in Indonesia

  • 1. Overview (2/2)

1-2. Implementation Structure of the city to city collaboration

DKI-Jakarta

Governor

Kawasaki City

Mayor

BAPPEDA International Economic Affairs Office

Japanese private entities

City to City Collaboration

Indonesian private entities

Formulation of JCM model project

Support on JCM model project formulation Support on JCM model project formulation

Nippon Koei Co., Ltd.

▶ Support of city to city collaboration activities ▶ Implement feasibility study to formulate JCM model project with the cities and

private entities

slide-4
SLIDE 4

24th July 2018 Seminar on the Joint Crediting Mechanism Implementation in Indonesia 4

Green Building

Solid Waste Renewable Energy Urban Transportation Priority Sectors in DKI-JKT Formulation of JCM model project ▶Transferring knowledge/ experiences from Kawasaki city to DKI-JKT ▶ Collaboration to solve these environmental issues Main actions

2-1. Background to select Green Building sector as JCM model project 2-2. Business Matching in Jakarta in FY2017 Purpose

▶ To identify prospective JCM model projects ▶ To know each other to create future business opportunity

Presentation on Green Building regulation Business matching session Presentation by Kawasaki city

  • 2. Feasibility Study for JCM model project on Green Building (1/3)
slide-5
SLIDE 5

24th July 2018 Seminar on the Joint Crediting Mechanism Implementation in Indonesia 5

2-3. Outline of the JCM model project

▶ Installation of air conditioning energy-saving technologies into the office

buildings (Approx. 10 buildings) in central DKI-Jakarta.

▶ The technologies will be provided by PT. Azbil Berca Indonesia (local subsidiary of Azbil

Corporation), a leading company on building automation business.

Azbil Berca Indonesia

Ministry of the Environment, Japan

Reporting GHG emission reduction & monitoring, Application of subsidy

Subsidy Partner Participant

Buildings in DKI-JKT

(World Trade Center etc.)

International Consortium

▶ Order BEMS etc. ▶ Reporting on monitoring ▶ Lease Contract ▶ Management of the project and subsidy

Representative Participant

Tokyo Century Corporation

2-4. Prospective International Consortium

  • 2. Feasibility Study for JCM model project on Green Building (2/3)
slide-6
SLIDE 6

24th July 2018 Seminar on the Joint Crediting Mechanism Implementation in Indonesia 6

2-5. Expected Installed Technology

Office Building

A system realizing effective energy management and optimum facility control 2-6. Technology replication opportunities

Source: Azbil Berca Indonesia

There is a big potential of energy saving in buildings, but it has not been much invested into the buildings. BEMS (Building Energy Management System) Potential Very High in Indonesia

  • 2. Feasibility Study for JCM model project on Green Building (3/3)

PT Azbil Berca Indonesia has

► many experiences of BEMS in Japan

(over 200 buildings)

► many candidate buildings in DKI-

JKT for green building

slide-7
SLIDE 7

24th July 2018 Seminar on the Joint Crediting Mechanism Implementation in Indonesia 7

  • 3. Expected Schedule

Apri May Jun Jul Aug Sep Oct Nov Dec Jan Feb

1) Confirmation of existing condition 2) Creation of monitoring plan 3) Confirmation of environmental approval

etc.

4) Preparation of International Consortium 5) Confirmation of project cost, contract,

project schedule

6) Invitation DKI-JKT officers to Japan

7) Business matching between Kawasaki

companies and Indonesian companies

tentative

1) Workshop (tentative)

2) JCM Seminar in Japan organized by

MOEJ

3) Field Survey

★ ★ ★ ★

4) Final Report

★:Indonesia ☆:Japan

(2) Others Survey Item 2018 2019 (1): JCM model project formulation