City of Park Rapids 2016-2020 Capital Improvement Plan
Presented on 12/08/2015
**The Master Book can be viewed at City Hall in the Clerk’s Office**
City of Park Rapids 2016-2020 Capital Improvement Plan Presented - - PowerPoint PPT Presentation
City of Park Rapids 2016-2020 Capital Improvement Plan Presented on 12/08/2015 **The Master Book can be viewed at City Hall in the Clerks Office** What a CIP IS Tool for the scheduling, planning, and financing of large
Presented on 12/08/2015
**The Master Book can be viewed at City Hall in the Clerk’s Office**
For the City to use its authority to finance expenditures
DEPT 2016 2017 2018 2019 2020 TOTAL
Admin
Airport 58,100 $
60,000 $ 55,000 $ 173,100 $ Facility Maintenance 85,000 $
85,000 $ Fire
Liquor 68,000 $ 150,000 $ 150,000 $ 1,380,000 $
1,748,000 $ Library
Multiple
Parks 100,000 $ 75,000 $ 100,000 $
32,500 $ 307,500 $ Planning
25,000 $
50,000 $ 75,000 $ Police
Sewer
Storm Sewer
Streets 35,000 $ 75,320 $
110,320 $ W/S
Water
Grand Total 346,100 $ 300,320 $ 275,000 $ 1,440,000 $ 137,500 $ 2,498,920 $
DEPARTMENT 2016-2020 Percent
Administration $18,000 0.12% Airport $4,137,000 27.47% Facility Maintenance $130,000 0.86% Fire $900,000 5.98% Liquor $1,748,000 11.61% Library $0 0.00%
Construction Water/Sewer/Street
$7,150,000 47.47% Parks $465,000 3.09% Planning $75,000 0.50% Police $150,000 1.00% Sewer $127,500 0.85% Storm Sewer $50,000 0.33% Streets $110,320 0.73% W/S $0 0.00% Water $0 0.00% TOTAL $15,060,820
Admin Airport Facility Maint Fire Liquor Multiple Parks Planning Police Sewer Storm Sewer Streets
Year 1
PROJECT DEPARTMENT COST
Heartland Express Bus Fund Admin 16,000 $ Truck (mechanic) Streets 35,000 $ Remodel/Upgrade City Hall Facility Maint 25,000 $ Bldg Space Studies Facility Maint 50,000 $ Deane Park Improve Phase I - 2016 Parks 100,000 $ Apron/Taxiway Rehab/Pavement Removal Airport 1,162,000 $ GA Apron Overlay Lot (FFY 2016) Airport 425,000 $ Land Acquisition for Discovery Circle Storm Sewer 50,000 $ Video Replacement Liquor 18,000 $ Point of Sale Software Upgrade Liquor 20,000 $ Fire Hall Addition (incl property purch) Fire 900,000 $ Liquor Store Location/ Space Study Liquor 30,000 Install access controls-doors Facility Maint 40,000 $ Irrigator Motors Sewer 40,000 $ Irrigator #4 Rehab Sewer 65,000 $ Cold Storage Shelving Facility Maint 15,000 $ Bat wing Mower-Pull Behind Sewer 22,500 $ Squad Car (to be purchased in 2018) Police 15,000 $
* Bonded projects
Total $3,028,500
Admin Airport Facility Maint Fire Liquor Parks Police Sewer Storm Sewer Streets
2016
Year 2
PROJECT DEPARTMENT COST
Heartland Bus Admin 2,000 $ Crack Fill Machine Streets 45,320 $ Deane Park (from Rice Park) Parks 50,000 $ Pavement crack and joint repair Airport 50,000 $ Discovery Circle (from 2012) Multiple 2,000,000 $
*
Computers Multiple 30,000 $ Man Lift (used) Streets 30,000 $ Parks Utility Truck 1 ton dump box Parks 50,000 $ Squad Car (to be purchased in 2018) Police 30,000 $ Liquor Land (update) Liquor 150,000 $
Total 2,437,320 $ * Bonded Projects
Admin Airport Liquor Multiple Parks Police Streets
2017
Year 3
PROJECT DEPARTMENT COST
Comprehensive Plan Update-2018 Planning 25,000 $ Deane Park Improve Phase 2 - 2018 Parks 200,000 $ 16 Unit T-Hangar 2017 West Apron Airport 700,000 $ 16 Unit T-Hangar 2017 (Prep) West Apron Airport 300,000 $ Private Hangar Taxilane Est/Site Prep Airport 350,000 $ Riverside II Multiple 1,750,000 $
*
Liquor Land (update) Liquor 150,000 $ Squad Car (to be purchased in 2018) Police 30,000 $
* Bonded Projects $3,505,000
Airport Liquor Multiple Parks Planning Police
2018
Year 4
PROJECT DEPARTMENT COST
Liquor Store Building Liquor 1,380,000 $ East Apron Expansion (FFY 2019) Airport 500,000 $ East 16 unit T Hangar demolition (FFY 2019) Airport 100,000 $ Squad Car (to be purchased in 2021) Police 30,000 $ 5th Street Street, Utilities, & Lighting Multiple 1,200,000 $
*
Franklin Avenue & 3rd Street Multiple 570,000 $
*
TOTAL 3,780,000 $ * Bonded Projects
Airport Liquor Multiple Police
Year 5
PROJECT DEPARTMENT COST
Construct South Connector Twy to Rwy 36
Airport
400,000 $ Install Taxiwa MITLS-Rwy 36 S Conn. Twy
Airport
150,000 $ Community Destination Signs 2017
Planning
50,000 $ Squad Car (to be purchased in 2021) Police 30,000 $ Red Bridge Park Impr Bldg
Parks
65,000 $ Fair Avenue Multiple 1,600,000 $
*
$2,295,000 * Bonded projects
Airport Multiple Parks Planning Police
Years 6+
PROJECT DEPARTMENT COST
Salt/Sand Shed w/ Pavement Streets 221,222 $ Squad Car (to be purchased in 2021) Police 30,000 $ PW Utilities - Pick up W/S 35,000 $ Wood Chipper 2014 (move to other yrs) Streets 20,000 $ Gravel Conveyor Streets 10,000 $ Runway 15-33 Pavement Reconstruction Airport 1,200,000 $ Western Avenue South Only Streets 70,000 $ North Shore / East River Drive Multiple 590,000 $
*
Gilbert Avenue Multiple 165,000 $
*
Grove / 2nd Avenue / Alleys Multiple 1,000,000 $
*
South Main Avenue / 11th Street Multiple 900,000 $
*
Stevens/Front/2nd, 3rd, 4th Street/Alleys Multiple 2,400,000 $
*
Western Avenue (North) Multiple 660,000 $
*
Industrial Park Multiple 2,300,000 $
*
Administration/Library Building Admin 1,900,000 $
*
Garage Bay Additions-PW/Safety Bldg Police 273,000 $ Terminal Bldg Remodel (Arrival/Departure) Airport 750,000 $ Pavement crack and joint repair Airport 50,000 Fuel System Upgrade Airport 100,000 $ Master Plan / ALP update Airport 500,000 $ Runway 18-36 Pavement Rehabilitation Airport 500,000 $
* Bonded projects
$13,674,222
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Round 2 of 2016 CIP Planning $690,137 $595,791 $626,686 $716,831 $722,622 $803,662 $859,348 $886,283 $832,133 $853,233 $818,583 Round 1 of 2016 CIP Planning $689,137 $675,791 $900,686 $1,015,831 $1,126,622 $1,165,662 $1,199,348 $1,236,283 $1,191,133 $1,220,233 $1,194,583 $- $200,000 $400,000 $600,000 $800,000 $1,000,000 $1,200,000 $1,400,000
BREAKDOWN OF DEPARTMENTS
DEPT TOTAL AMT %
Airport $ 681,861 26%
$ 5,000 0% Fire $ 104,759 4% General $ 447,872 17% Parks $ 444,266 17% Planning $ 63,640 2% Police $ 85,786 3% Public Works $ 626,142 24% PW/W/S $ 84,854 3% Water/Sewer $ 40,830 2%
$ 2,585,010
Liquor Transfers from 2003 - 2014
Parks 2014 Heartland Trail Project $113,161 Police 2013 Police Investigator car $17,186 Police 2012 Police Radio upgrade $44,610 Public Works 2011 Cat Loader $104,377 Public Works 2011 Plastic Cutting Edges-Main Ave $3,860 Public Works 2011 Snow Bucket - rubberized $5,846 Public Works 2011 Elgin Sweeper $174,374 Police 2011 Squad Car $23,990 Parks 2011 Portion of Red Bridge Parking Lot $14,500 Public Works 2010 Plow Truck (portion) $132,252 Parks 2010 Mower and Trailer $10,618 Fire 2010 Relief Association-Fire Dept $27,311
2010 Addt'l amt to HCREDC $5,000 Parks 2009 Kaywood Trail $47,651 Planning 2008 Downtown Revitalization Plan-Bal $8,269 Planning 2008 Community Center $18,000 Parks 2008 Kaywood Trail $35,980 General 2008 Balance General Fund $72,361 PW/W/S 2007 Cold Storage Building $84,854 Public Works 2007 Sterling Plow Truck-2007 $136,038 Planning 2007 Downtown Revitalization Plan $37,371 Parks 2007 Depot Park Playground Equip $139,170 Parks 2007 Depot Park Paving/Sidewalks $83,186 Water/Sewer 2006 2006 Chevy 3500 Truck w/ hoist $40,830 Public Works 2006 2006 Ford F350 w/ flatbed $42,812 Public Works 2006 Generator $26,583 Fire 2006 2007 Flatbed w/ Compart &Pump $77,448 General 2004 Balance General Fund $202,064 General 2003 Balance General Fund $173,447 $1,903,149
Airport Transfers Year Amount 2014 $48,219 2013 $68,046 2012 $89,392 2011 $65,351 2010 $109,255 2009 $10,615 2008 $96,406 2007 $49,255 2006 $40,054 2005 $18,224 2004 $44,692 2003 $42,351 $681,861
2001 $ 2,530,000 GO Bonds (refinanced in 2009) 2003 $ 925,000 GO Bonds (refinanced in 2009) CSAH 15 w/s Baywoods Addition Malm Easement McGrane's 2nd Addition Gilbert Timbers Phase 1 6th Street Malm's Addition 2004 $ 2,245,000 GO Bonds (refinanced in 2010) Sanquist Addition FishHook Lake/Deane Point 7th Street SE Timbers Phase 2 8th Street SE FishHook Avenue Alleys 8th Street W 2007 $ 3,945,000 GO Bond (refinanced in 2012) City Shop Utilities Hwy 34E Hydrants & Gate Valves State/DNR CSAH 15 Storm Sewer (City Share) Hwy 34W Barscreen Central/South Downtown Alleys 7 Block Sewer Sidewalk Reconstruction Pleasant 2008 $ 1,215,000 GO Bonds (refinanced 2015) 2009 $ 535,000 GO Refunding Bond Edmond Drive PW/Safety Bldg Hollinger Street/Eastern Avenue Bear Path Drive 2010 $ 1,440,000 GO bond (a) Eagle Drive Southwest 2nd Street West 4th Street $ 20,967,400 Total 2010 $ 4,740,000 GO Bond (b) $ 6,448,520 Interest Main Avenue $ 27,415,920 Grand Total (when completely paid) 2015 $ 3,392,400 GO Bond Riverside $ 1,126,526 Savings due to refinancing North Main
Bonded Projects Completed Since 2001
SUMMARY
All Funds $ Total
Airport
$ 7,586,668 41.10%
Administration
$ 9,634 0.05%
Fire
$ 1,321,091 7.16%
$ 12,450 0.07%
Hwys, Streets
$ 1,091,800 5.91%
Internal Service Fund
$ 28,595 0.15%
Library
$ 38,169 0.21%
Liquor
$ 506,128 2.74%
Parks
$ 947,408 5.13%
Police
$ 260,240 1.41%
Sewer
$ 4,305,535 23.33%
Storm Sewer
$ 201,142 1.09%
Street Lighting
$ 63,800 0.35%
Water
$ 2,085,651 11.30% $ 18,458,311 Excluding Airport & Enterprise $ Total
Administration
$ 9,634 0.26%
Fire
$ 1,321,091 35.01%
$ 12,450 0.33%
Hwys, Streets
$ 1,091,800 28.94%
Internal Service Fund
$ 28,595 0.76%
Library
$ 38,169 1.01%
Parks
$ 947,408 25.11%
Police
$ 260,240 6.90%
Street Lighting
$ 63,800 1.69% $ 3,773,186
Assets 2001-2014 Excluding Projects Included in Bonding (Payment for Assets Vary, Including Grants)