Chapter 13. Reactor Design Studies g Utility criteria for choosing - - PowerPoint PPT Presentation

chapter 13 reactor design studies g
SMART_READER_LITE
LIVE PREVIEW

Chapter 13. Reactor Design Studies g Utility criteria for choosing - - PowerPoint PPT Presentation

Chapter 13. Reactor Design Studies g Utility criteria for choosing a power plant Reliability, availability, and maintainability Economics Economy of scale Fusion-fission hybrids y European power plant designs Japanese power plant designs


slide-1
SLIDE 1

Chapter 13. Reactor Design Studies g

Utility criteria for choosing a power plant Reliability, availability, and maintainability Economics Economy of scale Fusion-fission hybrids y European power plant designs Japanese power plant designs Japanese power plant designs Chinese power plant designs U it d St t l t d i

dolan swip 2009 1

United States power plant designs

slide-2
SLIDE 2

Criteria for Utility Decision to Build a Power Plant

dolan swip 2009 2

slide-3
SLIDE 3

Economics Criteria

Simplicity C it l t Capital cost Construction time Lifetime – 60 years? Fuel-cycle technology, costs, supply Reliability Availability – fraction of time operational y p Load following Maintainability

dolan swip 2009 3

Maintainability

slide-4
SLIDE 4

Economics Criteria

Ri k t t kh ld & fi i Risk to stockholders & financiers Staff – size, skills Market – nearby industry or city Transmission lines Grid stability Resources – Nb, He, … Natural hazards – earthquake, flood, fire, wind Waste Decommissioning Absence of fission products, reprocessing

dolan swip 2009 4

p p g

slide-5
SLIDE 5

Regulatory criteria

Regulations – promote or hinder? Law suits – intervenors? Safety – avoid engineered safety systems? y g y y Emissions – low? Existing regulations? Emergency planning – evacuation plant? Emergency planning evacuation plant? Worker exposure – doses? Li i b f itt d? Licensing – before money committed?

dolan swip 2009 5

slide-6
SLIDE 6

Public Acceptance

Public attitude – favorable or hostile? Environmental issues – Environmental issues restrict plant operations? water temperature rise ? water temperature rise ? protected species or archaeological sites? Emissions toxic metals and chemicals radioactivity? Emissions – toxic metals and chemicals, radioactivity? Radioactive waste – minimization, disposal? P bli h lth i t ? Public concerns – health impacts? Perception – public education

dolan swip 2009 6

terminology (“emergency core cooling”)

slide-7
SLIDE 7

Reliability Availability Maintainability Reliability, Availability, Maintainability

dolan swip 2009 7

slide-8
SLIDE 8

Reliability Reliability

Reliability = probability that a component will not fail during a certain time period during a certain time period Needed for economical operation Improves safety Related to component failure rates

dolan swip 2009 8

slide-9
SLIDE 9

Reliability

N = number of components t = time interval  component failure rate (Number of failures)/Nt  = component failure rate = (Number of failures)/Nt Reliability during time T = exp(- T) Example: 2 failures among 192 flashlamps

  • perating for 20,000 pulses. (Here “pulses” are used
  • perating for 20,000 pulses. (Here pulses are used

instead of time units T.) = 2 / (192x20,0000) = 5x10-7 per pulse During 50 000 pulses: During 50,000 pulses: Reliability = exp(-5.2x10-7 x 50,000) = 0.974 or 97.4%.

dolan swip 2009 9

slide-10
SLIDE 10

Availability

Availability A = (hours operating)/(total hours in a year) = uptime / (uptime + downtime) = MTBF / (MTBF + MTTR) / ( ) Mean time Mean time to repair between failures Fission reactors A = 75%  90% Capacity factor = (fractional power) x Availability

dolan swip 2009 10

slide-11
SLIDE 11

Availability

Example: Tokamak components operate 80% of the time, Example: Tokamak components operate 80% of the time, 8 hours/day, 5 days/week, 25 weeks/a. A = (0.8 x 8 x 5 x 25)/(24 x 365) = 0.09 = 9% ITER goal = 0.75 hr x (3000 pulses/a) / (24 x 365) = 26%.

dolan swip 2009 11

slide-12
SLIDE 12

Maintainability

Mean Time to Repair MTTR = Sum(repair times) / (number malfunctions) Example: Instrument repair times 4 0 5 9 2 25 man hours Example: Instrument repair times 4, 0.5, 9, 2.25 man-hours. MTTR = (4 + 0.5 + 9 + 32.25) / 5 = 3.5 hr/repair Mean Down Time MDT = (analyze +get parts +repair +install +test +startup)

dolan swip 2009 12

slide-13
SLIDE 13

Maintainability Maintainability

Preventive maintenance done during operations or normal shutdown time. (oil change on car) Predictive maintenance uses instruments to detect signs and predict failures before they occur. (meas re ibrations from bearings) (measure vibrations from bearings)

dolan swip 2009 13

slide-14
SLIDE 14

Maintainability

Traditional – technicians, electricians, welders, mechanics, carpenters, … “Balance of Plant’ = steam generators, turbines, generators, condenser, pipes, valves, instruments, controls, ... condenser, pipes, valves, instruments, controls, ... “Hands-on” maintenance dose rate < 10 Sv/hr Remote Maintenance – robotic, remote manipulators. heat, radiation, toxic atmosphere. ITER JET divertor modules: 112 hr/week x 15 weeks

dolan swip 2009 14

slide-15
SLIDE 15

Economics Economics

dolan swip 2009 15

slide-16
SLIDE 16

Cost of Electricity (COE)

h d l d years

  • perations

& maintenance

s c

scheduled component replacement Total capital cost Fuel years construction

h e

($ / kWh) f “fi d h t ”

“current dollar mode” E = 0 05 fcr = 0 15

fcr = “fixed charge rate” = cost of capital, depreciation, insurance, taxes. E = “escalation rate” = rate of inflation

current dollar mode E = 0.05, fcr = 0.15 “constant dollar mode” E = 0, fcr = 0.10

dolan swip 2009 16

slide-17
SLIDE 17

Interest and Escalation Factors

Cc = total capital cost ≈ 1.35 Cdc (FIDC+FEDC)

dolan swip 2009 17

slide-18
SLIDE 18

Physics-Engineering-Cost (PEC) Code

Purpose: Compare tokamaks, heliotrons, modular stellarators. Input - Rp/ap, , T

  • , Pe

 plasma parameters and power balance Adjusts Rp to match desired Pe Masses & unit costs ($/kg)  capital cost  COE COE variations with plasma and engineering parameters.

dolan swip 2009 18

slide-19
SLIDE 19

Heliotron Base Case Input Parameters

Rp/<ap> 5.7

p p

 2  3 % Pe 1.94 GWe Pe 1.94 GWe Bmax 13 T Jmax 30 MA/m2 40 %  40 % Mpol/Mhel 0.40 Msup/Mcoil 0.50

p

T

  • 20

keV favail 0.75

dolan swip 2009 19

slide-20
SLIDE 20

Direct Capital Cost

% direct M$ % direct

  • cap. cost
  • 20. Land & land rights

12.7 0.3 21 Structures & site facilities 450 3 11 1

  • 21. Structures & site facilities

450.3 11.1

  • 22. Reactor plant equipment

2798.2 68.7 22.1 fusion reactor equipment 2090.2 51.3 22 1 1 FW/bl k t/ fl t 259 4 6 4 22.1.1 FW/blanket/reflector 259.4 6.4 22.1.2 shield 254.3 6.2 22.1.3 magnets 956.7 23.5 22.2.4 current drive & heating 168.8 4.1 22.1.5 primary structure & support 169.3 4.2 22 1 6 vacuum systems 198 9 4 9 22.1.6 vacuum systems 198.9 4.9 22.1.7 power supply 67.6 1.7 22.1.8 impurity control & divertor 15.2 0.4 22 1 10 ECRH breakdown system 4 9 0 1

dolan swip 2009 20

22.1.10 ECRH breakdown system 4.9 0.1

slide-21
SLIDE 21

Direct Capital Cost, continued

M$ % 22.2 main heat transport systems 523 12.8 22.3 auxiliary cooling system 6.8 0.2 22.3 auxiliary cooling system 6.8 0.2 22.4 radioactive waste management 12.1 0.3 22.5 fuel handling and storage 108.2 2.7 22 6 other reactor plant eqt 11 0 3 22.6 other reactor plant eqt. 11 0.3 22.7 instrumentation and control 46.8 1.1 22BOP (sum of 22.2 to 22.7) 708 17.4

  • 23. Turbine plant equipment

509.6 12.5

  • 24. Electric plant equipment

199.6 4.9

  • 25. Misc. plant equipment

100.6 2.5

  • 25. Misc. plant equipment

100.6 2.5

  • 26. Special materials

103.4 2.5

  • 90. Total direct capital cost=20 to 26

4071 100

dolan swip 2009 21

slide-22
SLIDE 22

Direct Capital Cost Components

Magnet coil ~ 24% of the direct capital cost g p HTSC could reduce this cost. Other fusion reactor components 4 6% each: Other fusion reactor components 4-6% each: Blanket Shield Heating systems Structure Vacuum system y Balance of plant 17%

dolan swip 2009 22

slide-23
SLIDE 23

Base Case COE (mil/kWh) Base Case COE (mil/kWh)

COE capital cost 59.751 COE operations 7.875 COEfuel 0 019 COE fuel 0.019 COE replacement 3.387 COE Decon. & decom. 0.612 Total COE 71.6

dolan swip 2009 23

slide-24
SLIDE 24

Base Case Results

Rp 14.4 m  2 1 MW/m2 n 2.1 MW/m M(fusion island) 23 kt Total capital cost 7.9 G$ capital cost / Watt 4.1 $/W COE 72 mill/kWh COE 72 mill/kWh

dolan swip 2009 24

slide-25
SLIDE 25

COE vs. Peak Coolant Temperature

dolan swip 2009 25

slide-26
SLIDE 26

COE vs. Wall Life

dolan swip 2009 26

slide-27
SLIDE 27

Fusion could be competititve if

intense neutron sources for materials testing. carbon tax on fossil fuel use. If compact high power-density fusion reactors If compact high power density fusion reactors (such as spheromaks) successfully developed fusion fission hybrids built fusion-fission hybrids built large sizes (> 1 Gwe) to achieve economy of scale.

dolan swip 2009 27

slide-28
SLIDE 28

Economy of Scale Economy of Scale

dolan swip 2009 28

slide-29
SLIDE 29

Strong Economy of Scale

14

NLHD-D1 Scaling

11 12 13 Wh =2% 3%

w = 1.5 MW/m2

8 9 10 11 E, Yen/kW 3% 4%

2 MW/m2 3 MW/m2

5 6 7 8 COE 5% 4 5 0.5 1 1.5 2 2.5 3 3.5

dolan swip 2009 29

Pe, GWe

slide-30
SLIDE 30

Factors providing economy of scale

Lower operating & maintenance costs per kW L i t t li Large equipment cost scaling Geometric effect Pe/(reactor mass) improves with size Lower recirculating power fraction R lt COE COE (P/P ) n 0 4 Result COE = COEo (P/Po)-n n  0.4

dolan swip 2009 30

slide-31
SLIDE 31

Economy of Scale Issues

Electricity at one site many plants > 4 GWe Heat rejection at one site many plants > 6 GWth j y p Public acceptance depends on undestanding Investment risk reluctance to invest Investment risk reluctance to invest Market penetration slow, depends on perceive demand Load following generate hydrogen with part of power Grid perturbation site several large plants together Small is beautiful but requires expensive storage Divertor heat load increases with size

dolan swip 2009 31

slide-32
SLIDE 32

Many Large Power Stations Exist

8 hydroelectric plants > 5 GWe 8 hydroelectric plants > 5 GWe Three Gorges Dam (China) = 18.2 GWe ( 2009) 9 nuclear power stations > 4 GWe. New European PWR = 1.6 GWe, single reactor (Limited by control and safety issues) Heliotron Base Case = 1.94 GWe But what about grid perturbation during outage?

dolan swip 2009 32

slide-33
SLIDE 33

Grid Perturbation Avoidance

5 large reactors at one site, each g , 60% hydrogen, 40% electricity to grid. Outage of one reactor: Outage of one reactor: 4 reactors, each 50% hydrogen, 50% electricity to grid. Same electrical power to grid.

Ref: J. Sheffield, FST 40 (2001) 1-26 Siting large fusion power plants

dolan swip 2009 33

Siting large fusion power plants.

slide-34
SLIDE 34

Fusion could be competititve if

developed for space propulsion intense neutron sources for materials testing. carbon tax on fossil fuel use carbon tax on fossil fuel use. compact high power-density fusion reactors (such as spheromaks) successfully developed (such as spheromaks) successfully developed fusion-fission hybrids built large sizes (> 1 Gwe) to achieve economy of scale.

dolan swip 2009 34

slide-35
SLIDE 35

Fusion-Fission Hybrids Fusion Fission Hybrids

dolan swip 2009 35

slide-36
SLIDE 36

Need for Breeding Fissile Fuel

Natural Uranium = 0.72% 235U the rest is 238U Present reactors use mostly 235U Breeding 239Pu: 238U + neutron 

239Np  239Pu

2.3 days Estimated World Resources

235U: 3.88*104 tonnes = 2.5x1021 J = 95 TW-a 238U: 5.43*106 tonnes = 3.5x1023 J = 1300 TW-a 232Th: (2.57*106 tonnes) = 1.7x1023 J = 6300 TW-a

dolan swip 2009 36

slide-37
SLIDE 37

Hybrids better than Liquid Metal Fast Breeder Reactors (LMFBRs) Breeder Reactors (LMFBRs)

No fissile fuel required for startup C iti l id d Critical mass avoided Fuel doubling times months, instead of many years One hybrid supplies many fission reactors Lower power density in uranium fuel Less afterheat  safer Accelerates development of pure fusion Accelerates development of pure fusion But Not et de eloped Not yet developed Require tritium-breeding Maintenance more complex

dolan swip 2009 37

slide-38
SLIDE 38

Main Parameters

Blanket energy gain M (energy/neutron) / 14-MeV Example: If n + 6Li  3 8 MeV Example: If n + Li  3.8 MeV then M = (14+3.8)/14 = 1.27 Tritium breeding ratio T tritons bred / incident neutron Fissile fuel breeding ratio F fissile atoms bred / incident neutron

dolan swip 2009 38

slide-39
SLIDE 39

Neutronics issues

Power density ~ 100 W/cm3 Blanket always subcritical Neutron multiplier Remove Np and Pu Remove Np and Pu Fuel management (fissile inventory, residence time) Afterheat Afterheat Radiation damage Coolant that does not slow down neutrons Low-pressure coolant  minimum structure

dolan swip 2009 39

slide-40
SLIDE 40

Breeding 232Th  233U

dolan swip 2009 40

slide-41
SLIDE 41

Estimates of T, F, M with U3Si Blanket

dolan swip 2009 41

slide-42
SLIDE 42

Ratio of fission to fusion power

 = capture to fission ratio  = capture-to-fission ratio C = fission reactor conversion ratio

233U C = 0.85,  = 0.1 

Pfis/Pfus = 69

239Pu C = 0.6,  = 0.3 

Pfis/Pfus = 23

dolan swip 2009 42

slide-43
SLIDE 43

Tokamak Hybrid Blanket

Radiation shield Radiation shield Cooled by Low-pressure water LiFBeF2 + SS + He

dolan swip 2009 43

LiFBeF2 SS He

slide-44
SLIDE 44

Catalyzed DD Hybrids

dolan swip 2009 44

slide-45
SLIDE 45

Advantages of Catalyzed DD Hybrid

Tritium breeding not needed more neutrons for fissile fuel breeding can allow more structure structure between first wall, breeder  maintenance easier maintenance easier Molten salt

  • n-line reprocessing

l i t i f fi il f l d di ti it lower inventories of fissile fuel and radioactivity less afterheat lower reprocessing costs Disadvantages: corrosion, low fusion power density

dolan swip 2009 45

slide-46
SLIDE 46

European Power Plant Designs European Power Plant Designs

dolan swip 2009 46

slide-47
SLIDE 47

Power Plant Conceptual Study (PPCS).

Safety / Environment no need for emergency evacuation, no active systems for safe shut-down, no active systems for safe shut down, no structure melting following LOCA minimum waste and transport Operation steady state, ~ 1 GWe, base load; availability > 75 % Economics public acceptance Licensing easier than for fission construction time  5 years

dolan swip 2009 47

construction time  5 years

slide-48
SLIDE 48

Four Models

(A & B) similar to ITER H<1.2, n/nGR<1.2, βN<3.5 first stability region

6 8

A B

first stability region. (C & D) high β and H

2 4 6

Z(m)

B C D ITER

strong plasma shaping, high bootstrap current fraction

  • 2

2 5 10 15

R(m)

fraction divertor protection.

  • 6
  • 4
  • 2
  • 8
  • 6

(f I C k UKAEA)

dolan swip 2009 48

(from Ian Cook, UKAEA)

slide-49
SLIDE 49

Four Models

Parameter Model A Model B Model C Model D Unit Size (GWe) 1.5 1.3 1.4 1.5 Fusion Power (GW) 5.0 3.6 3.4 2.5 Net efficiency 0.31/0.33 0.36 0.41 0.60 Major Radius (m) 9.55 8.6 7.5 6.1 Plasma Current (MA) 30.5 28.0 20.1 14.1 Bootstrap Fraction 0 45 0 43 0 63 0 76 Bootstrap Fraction 0.45 0.43 0.63 0.76 Padd (MW) 246 270 112 71 Recirculating power fraction 0.28 0.27 0.13 0.11 g p Divertor Peak load (MW/m-2) 15 10 10 5

  • Av. neutron wall load

2.2 2.0 2.2 2.4

dolan swip 2009 49

(from Ian Cook, UKAEA)

slide-50
SLIDE 50

Materials of Four Models

Mode l Divertor structure Blanket structure Breeder/coolant A Cu/water or RAFM PbLi + water A Cu/water or RAFM/water RAFM PbLi water B W + RAFM/He RAFM Li4SiO4 + Be + He C W + RAFM/He RAFM (ODS) PbLI + SiC + He D SiC + PbLi SiCi PbLi

All use tungsten alloy divertor armor.

dolan swip 2009 50

From D. Maisonnier 2004

slide-51
SLIDE 51

Other key parameters Other key parameters

Parameter Model A Model B Model C Model D

F i Fusion power (GW)

5.0 3.6 3.4 2.5

Q

20 13 5 30 35

Q

20 13.5 30 35

Recirculating power

0.28 0.27 0.13 0.11

p fraction Wall load (MW/m2)

2.2 2.0 2.2 2.4

( Divertor peak load (MW/m2)

15 10 10 5

dolan swip 2009 51

( ) (from Ian Cook, UKAEA)

slide-52
SLIDE 52

Divertor Lifetime is Important

dolan swip 2009 52

(from Ian Cook, UKAEA)

slide-53
SLIDE 53

Costs: internal and external Costs: internal and external Costs: internal and external Costs: internal and external

  • Contributions to the cost of electricity:

Contributions to the cost of electricity:

  • Internal costs: constructing fuelling
  • Internal costs: constructing, fuelling,
  • perating, maintaining, and disposing
  • f power plants
  • f, power plants.
  • External costs: environmental damage,

adverse health impacts.

dolan swip 2009 53

(from Ian Cook, UKAEA)

slide-54
SLIDE 54

Internal costs: scaling Internal costs: scaling

  • Cost of electricity is

well represented by the scaling it

1.5

  • pposite.
  • The figure shows

systems code

1 PPCS)

systems code calculations for Models A to D, against the scaling

0.5 coe (P

against the scaling.

  • Shows that PPCS

Models are good

0.5 1 1.5 coe(scaling)

Models are good representatives of a much wider class of possible designs

coe(scaling)

0.3 0.4 0.4 0.5 0.6

N β P 1 η 1 A 1 coe       

dolan swip 2009 54

possible designs.

N e th

N β P η A  

(from Ian Cook, UKAEA)

slide-55
SLIDE 55

Conventional cost items make the l t t ib ti t th t liti largest contribution to the externalities

8 00E 02 1.00E-01 1.20E-01 1.40E-01 1.60E-01 1.80E-01

  • /kW h

Model 4 Model 5 0.00E+00 2.00E-02 4.00E-02 6.00E-02 8.00E-02 g f al t

  • al

al m Euro Model 6 M anufacturing

  • f m aterials

Transport o m aterials O ccupationa building accidents Local effec

  • f routine

releases G lobal dispersion C 14 and H-3 O ccupationa exposure O ccupationa accidents M

(f I C k UKAEA)

dolan swip 2009 55

(from Ian Cook, UKAEA)

slide-56
SLIDE 56

Achievements of PPCS

f f Economic viability of fusion power with plasma confinement only slightly better than the ITER physics basis. A maintenance concept that could facilititate 75% availability A divertor concept capable of handling 10 MW/m2 A divertor concept capable of handling 10 MW/m Passively safe, so no offsite evacuation plan would be needed Possibility of recycling practically all the materials, with no wastes requiring permanent disposal. q g p p Work needed on divertors and maintenance procedures

dolan swip 2009 56

Work needed on divertors and maintenance procedures.

slide-57
SLIDE 57

UKAEA Conclusions UKAEA Conclusions UKAEA Conclusions UKAEA Conclusions

  • Economically acceptable fusion power

y plants, with major safety and environmental advantages, are accessible by a “fast-track” development of fusion, through ITER without major materials advances.

  • There is potential for a more advanced
  • There is potential for a more advanced

second generation of power plants.

(f I C k UKAEA)

dolan swip 2009 57

(from Ian Cook, UKAEA)

slide-58
SLIDE 58

Japanese Power Plant Designs Japanese Power Plant Designs

dolan swip 2009 58

slide-59
SLIDE 59

Heliotron Coils l = 2, m = 10 lik LHD E i t like LHD Experiment

dolan swip 2009 59

slide-60
SLIDE 60

Confinement Scaling Laws Confinement Scaling Laws

HELICAL TOKAMAK

1 10 ASDEX AUG CMOD COMPASS TOK

1 10 ATF CHS FFHR HELE STELL

EXP E

EXP E

0.01 0.1 D3D JET JFT2M JT60U PBXM PDX TCV

0.01 0.1 tau_exp HSR LHD MHR SPPS W7-A W7-AS

E

0.001 .001 .01 .1 1 10 TCV

0.001 .001 .01 .1 1 10

10 . 50 . 83 .

* *

  

      ELMY

04 . 16 . 71 . 95

* *

  

ISS

40 . 3 / 2 80 . 51 . 59 . 65 . 21 . 2 95

08 .   B n P R a

e ISS E 

97 . 23 . 08 . 41 . 63 . 93 . 1

0365 . I B n P R

e ELMY E

 

     

B E 04 . 16 . 71 . 95

* *      

B ISS E

dolan swip 2009 60

slide-61
SLIDE 61

First Wall Bl k t

h

First Wall Bl k t

h

SC Coil Blanket Shield

Plasma

w

SC Coil Blanket Shield

Plasma

w

Bmax B R Rm Bmax B R Rm Ro Bt Rp B0 Ro Bt Rp B0

dolan swip 2009 61

slide-62
SLIDE 62

FFHR2m2

Varies the pitch of helical coil to reduce Varies the pitch of helical coil to reduce the hoop force on helical coil support structure. Carbon armor tiles containing beryllium soften the neutron energy spectrum, facilitating a local breeding ratio of 1.2.

dolan swip 2009 62

slide-63
SLIDE 63

FFHR2m2 Parameters

R 16.0 m a 2.80 m Blanket thickness 1.1 m Ferritic steel and FLIBE Bo in plasma 4.43 T Bcoil 13.0 T Pfus 3.0 GWth Neutron wall load 1.3 MW/m2 Heating power 100 MW ne 1.9x1020 m-3 n/nsugo 1.5 Zeff 1.35 HISS95 1.76 Ti 16.1 keV  4.1 %

dolan swip 2009 63

slide-64
SLIDE 64

FFHR2m2 Blanket

dolan swip 2009 64

slide-65
SLIDE 65

FLIBE Blanket

q” ~ 0.1 MW/m2  T(surface) ~ 1600 K  little tritium retention Be2C pebble bed 1 MW/m2  flowing FLIBE coolant Swelling limits C tile lifetime. Manipulator on helical tracks replaces armor tiles remotely Radiation damage limits tile lifetime Rest of RAF blanket lasts 40 years. y

dolan swip 2009 65

slide-66
SLIDE 66

Long blanket lifetime is valuable

dolan swip 2009 66

slide-67
SLIDE 67

Heliotron Reactor Model Heliotron Reactor Model

h

First Wall Blanket Shield

h

First Wall Blanket Shield

h

SC Coil

Plasma

w

SC Coil

Plasma

w

B Rm B Rm R Bmax Bt Rp

m

R Bmax Bt Rp

m

dolan swip 2009 67

Ro B0 Ro B0

slide-68
SLIDE 68

Small Plasma-Coil Distance is Needed

9.5 8 5 9 9.5 /kWh 8 8.5 E, Yen

Base Case RAF-Flibe line

7 7.5 CO

Base Case

0.8 1 1.2 1.4 1.6 1.8 Plasma-coil distance 

dolan swip 2009 68

Plasma coil distance 

slide-69
SLIDE 69

High beta is desirable

20 16 18 Rp, m 12 14 6 8 10 COE, Yen/kWh 6 1 2 3 4 5 6 beta %

dolan swip 2009 69

beta, %

slide-70
SLIDE 70

High Neutron Wall Load is Desirable g

18 20 14 16 18 kWh

beta = 1%

10 12 14 OE, Yen/k

beta = 2%

6 8 10 CO

beta=3-7%

4 2 4 6

dolan swip 2009 70

Neutron wall load, MW/m2

slide-71
SLIDE 71

High Bmax is good

20 16 18 Rp, m 12 14 8 10 COE, Yen/kWh 6 6 8 10 12 14 16 18

dolan swip 2009 71

Bmax, T

slide-72
SLIDE 72

COE vs. Blanket Lifetime

10 11 9 10 en/kWh 8 COE, Ye 6 7 C

5 10 15 20 25 30 35 40

Blanket Lifetime, years

dolan swip 2009 72

y

  • A. Sagara
slide-73
SLIDE 73

Comparison with ITER

Original ITER Reduced ITER Heliotron ITER ITER Total coil mass, kt 20 12 13 C i l 10 8 Capital cost, G$ 10 5 8 Fusion 0 5 0 5 5 Fusion power, GW 0.5 0.5 5

dolan swip 2009 73

slide-74
SLIDE 74

COE in Japan p

Fission 50 mill/kWh Fission 50 mill/kWh Coal 54 Natural gas 58 Natural gas 58 Oil 101 Pumped hydro storage 112 Heliotron base case 72 beta 5%, NLHD, 3GWe 49

dolan swip 2009 74

slide-75
SLIDE 75

Conclusions of NIFS Study

Neutron wall load ~ 4 MW/m2 desirable. S f l Hi h P  i i COE Strong economy of scale: High Pe  competitive COE Higher   smaller a  lower   ignition difficult Higher   smaller ap  lower E  ignition difficult Engineering uncertainties Engineering uncertainties coil reliability divertor divertor maintenance

dolan swip 2009 75

slide-76
SLIDE 76

United States Power Plant Designs United States Power Plant Designs

dolan swip 2009 76

slide-77
SLIDE 77

1990 ARIES I First stability 6 75m/1 5m 10MA  = 8 1 Uses achieved physics

Advanced Reactor Innovative Engineering Study (ARIES)

1990 ARIES-I First-stability regime 6.75m/1.5m, 10MA,  = 1.9%, Bcoil=21 T, SiC+Li2ZrO3+He, 650 C, 49%, n=2.5MW/m2 8.1 Uses achieved physics. Precirc =20% 1991 ARIES- III D-3He fueled tokamak 7.5m/2.5m, 30Ma,  = 24%, Bcoil=14 T, n=0.08MW/m2 8.6 2nd stability regime. Ti=55 keV Precirc =24% 1992 ARIES- 2nd stability 1992 ARIES- II, IV 2 stability 1993 PULSAR Pulsed tokamak 1994 SPPS Stellarator 14m/1 6m  = 5 % 7 5 P

i

=5% 1994 SPPS Stellarator 14m/1.6m,  = 5 %, Bcoil=15T, 4 field periods, 32 modular coils, V+Li, 46% 7.5 Precirc 5%, 1996 ARIES- Reversed- 5 5m/1 4m 11MA  = 7 6 P

i

=17% 1996 ARIES RS Reversed shear tokamak 5.5m/1.4m, 11MA,  15% Bcoil=16 T, V+Li, 610 C, n=5MW/m2 7.6 Precirc 17%

dolan swip 2009 77

slide-78
SLIDE 78

Advanced Reactor Innovative Engineering Study (ARIES)

Year Name Type Parameters ¢/kWh Remarks 1999 ARIES- ST Spherical torus 3.2m/1.6m, 28MA,  = 50%, P(Cu coil)=329MW, Bcoil=7.4 T, ferritic+PbLi, 7.9 Precirc =34% 700 C, 45% 2000 ARIES- AT Advanced technology tokamak 5.2m/1.3m, 13MA,  = 9%, Bcoil= 11.5, SiC+PbLi, 1100 C, 59%, 4.7 YBCO high- temperature superconductor, ITER89-Pconfinement multiplier =2.0, Precirc =14% 2008 ARIES- CS Compact t ll t 7.75m/1.7m, 4MA,  = % 7.8 High-n, low-T, ISS95 f CS stellarator 6.4%, T=6.6keV, Bcoil= 15T, n=2.6 (max.5.4)MW/m2 , ferritic +PbLi +He, Brayton 43%, H i P 183MW confinement multiplier =2.0, Precirc ~ 18% He pumping P=183MW.

dolan swip 2009 78

slide-79
SLIDE 79

ARIES-AT

dolan swip 2009 79

slide-80
SLIDE 80

Removable Sector

dolan swip 2009 80

slide-81
SLIDE 81

Advanced Tokamak Features

YBCO high-temperature superconductor Internal Transport Barrier SiC t t SiC structure High-temperature PbLi blanket  efficiency = 59% g p y low COE  4.7 ¢/kWh competitive with other energy sources competitive with other energy sources.

dolan swip 2009 81

slide-82
SLIDE 82

ARIES-AT Development Needs

  • 1. Plasma profile control

J(r), n(r) Reversed shear  internal transport barrier  long E, high beta, and high bootstrap current fraction.

  • 2. Power flow control q“ to wall and divertor < safe limit
  • 3. Disruption avoidance < one per year
  • 4. SiC composites large sizes radiation damage resistance
  • 4. SiC composites large sizes, radiation damage resistance
  • 5. Compatibility SiC + flowing Pb-17Li at 1000 C

6 Heat exchangers between Pb 17Li and He at 1100 C

  • 6. Heat exchangers between Pb-17Li and He at 1100 C

(Brayton cycle for high efficiency)

dolan swip 2009 82

  • 7. High-heat-flux materials for divertor (probably W)
slide-83
SLIDE 83

Summary – Power Plant Designs

F i ill b i ll i bl if Fusion will be economically viable if: neutron source needed for materials testing carbon tax on fossil fuel use compact high power-density fusion reactors (such as spheromaks) successfully developed fusion-fission hybrids built large sizes  economy of scale.

dolan swip 2009 83

slide-84
SLIDE 84

Extra Slides

dolan swip 2009 84

slide-85
SLIDE 85

Helical Reactors

LHD experiment Heliotron reactor Compact Modular Heliotron

dolan swip 2009 85

Compact Stellarator

slide-86
SLIDE 86

Algorithms for Bo, nav, and COE

B /B 0 476 (80S /R )0 4 ( /10)0 82 (1 2/ )0 05 Bo/Bmax = 0.476 (80Scoil/Ro)0.4 (m/10)0.82 (1.2/c)0.05 nav =  Bt

2/(4okTav) av

t ( o av)

iss = 0.26 P-0.59 ne

0.51 B0.83 R0.65 a2.21 2/3 0.4

Hiss = E/iss Hiss > 1.5 achieved in LHD COE = [CAC + (CO&M + CSCR + CF)(1+y)Y]/(8760Pe favail) + CD&D

dolan swip 2009 86

slide-87
SLIDE 87

COE vs. Central Temperature

18 14 16 Rp, m 10 12 14 8 10 COE, Yen/kWh 6 10 20 30 40 Central Temperature T keV

dolan swip 2009 87

Central Temperature To, keV

slide-88
SLIDE 88

Comparison of Plasma Aspect Ratios Comparison of Plasma Aspect Ratios

8.5 7 5 8 /kWh

Rp/ap = 8.1 Base Case

7 7.5 OE, Yen/

R /a = 5 7 Base Case

6 6.5 CO

Rp/ap = 5.7

6 1 1.5 2 2.5 3 Pe, GWe

dolan swip 2009 88

Pe, GWe

slide-89
SLIDE 89

COE vs. Coil width/depth

8.4 7 8 8 8.2 n/kWh 7.4 7.6 7.8 COE, Yen 7 7.2 1 2 3 4 1 2 3 4 w/h

dolan swip 2009 89

slide-90
SLIDE 90

COE vs. Profile Parameters

n(x)/ no = (1-yed)(1 – xp)q [d + (1-d)x2] + yed T(x)/ T

  • = (1-ted)(1 – xr)s + ted

x = r/rp

8.5 7.5 8 en/kWh

q=0.25 q=1 q 2

flat

6 5 7 COE, Ye

q=2 q=4

peaked

6 6.5 2 4 6 8

dolan swip 2009 90

2 4 6 8 s

flat peaked

slide-91
SLIDE 91

Effect of Hollow Density Profiles

n(x)/ n = (1 y )(1 xp)q [d + (1 d)x2] + y

8 5

1 2

n(x)/ no = (1-yed)(1 – xp)q [d + (1-d)x2] + yed T(x)/ T

  • = (1-ted)(1 – xr)s + ted

8.4 8.5 h

0 4 0.6 0.8 1.0 1.2 y

d = 1 0.8 0.6 0 4

8 2 8.3 , Yen/kWh q=0.5

0.0 0.2 0.4 0.2 0.4 0.6 0.8 1 x

0.4

8.1 8.2 COE, q=1

x

8 0.4 0.5 0.6 0.7 0.8 0.9 1

Ref: J. F. Lyon, hollow

dolan swip 2009 91

d

ARIES study hollow flat

slide-92
SLIDE 92

Required Hiss for Ignition Required Hiss for Ignition

3 5 2 5 3 3.5 Hiss

=6%

Rp/<ap>=5.7 c = 1.25  = 1 15 m

1.5 2 2.5

4% 2% 1%

 1.15 m

0.5 1

1% "base case"

1 2 3 4 Pe, GWe

dolan swip 2009 92

slide-93
SLIDE 93

dolan swip 2009 93

slide-94
SLIDE 94

Blanket-Shield Comparison

Units RAF-Flibe V-Li (SPPS) SiC-PbLi (AT) Inboard FW/BL/SH/VS m 0.95 1.29 1.02 Inboard FW/BL/SH/VS thickness m 0.95 1.29 1.02 Inboard blanket+shield cost M$/m2 0.27 0.37 0.25 Outboard M$/m2 0 27 0 37 0 34 Outboard blanket+shield costs M$/m 0.27 0.37 0.34 Coolant outlet Temperature C 560 610 1100 Energy conversion Efficiency % 40 46 59 Thinnest; But lowest Thickest & most expensive; Highest efficiency; But lowest efficiency expensive; but might be made thinner. efficiency; but expensive materials

dolan swip 2009 94

slide-95
SLIDE 95

Fusion Power Island Mass vs. Pe

50 35 40 45 kt

beta=2%

20 25 30 35

3% 4%

10 15 20

5% 6%

5 1 2 3 4

dolan swip 2009 95

1 2 3 4 Pe, GWe

slide-96
SLIDE 96

Strong Economy of Scale Available

12 13 COE, Yen/kWh

beta = 2%

10 11 12

Hiss = 2 1 7

7 8 9

3% 4%

1.7 1.5

5 6 7

4% 5%

4 5 0.5 1 1.5 2 2.5 3 3.5 P GW

dolan swip 2009 96

Pe, GWe

slide-97
SLIDE 97

ISS-95 and NLHD-D1 scalings

iss = 0.26 P-0.59 ne

0.51 B0.83 R0.65 a2.21 2/3 0.4

NLHD = 0.269 P-0.59 ne

0.52 B1.06 R0.64 a2.58

Hiss = E/iss

dolan swip 2009 97

slide-98
SLIDE 98

Required Hiss for Ignition Required Hiss for Ignition

3 5 2 5 3 3.5 Hiss

=6%

Rp/<ap>=5.7 c = 1.25  = 1 15 m

1.5 2 2.5

4% 2% 1%

 1.15 m

0.5 1

1% "base case"

1 2 3 4 Pe, GWe

dolan swip 2009 98

slide-99
SLIDE 99

Heliotrons & Modular Coil Stellarators Heliotrons & Modular Coil Stellarators

Heliotrons Modular coil stellarators Th ti l b t 5% P t ti l b t 5% d Theoretical beta < 5%, 4% achieved Potential beta > 5%, needs experimental verification. Alpha confinement uncertain Potentially good alpha p y g p confinement Plasma aspect ratio restricted by c to approximate range 5 5 -- Aspect ratio can vary over wide

  • range. Low ratios may yield

by c to approximate range 5.5 8.5.

  • range. Low ratios may yield

lower COE. Natural helical divertor Local divertors, space problem NLHD D1 scaling favorable NLHD-D1 scaling favorable

dolan swip 2009 99

slide-100
SLIDE 100

Heliotrons & Modular Coil Stellarators

Heliotrons Modular coil stellarators Coil winding accuracy uncertain. Coil winding & alignment to be demonstrated by W-7X. Coil failure probably unfeasible to repair. Failed coil or module could be replaced. Alignment should last for the lifetime of the plant Coils must be re-aligned after removal of a module Lifetime blanket might be Periodic replacement of blanket feasible. modules envisioned. Large ports available for first wall replacement. Port size generally smaller, depends on specific design. Elli i l h i Odd h d i Elliptical shape cross section permits close proximity of blanket and shield. Odd shaped cross sections, more complex.

dolan swip 2009 100

slide-101
SLIDE 101

CHS Modular Coil System CHS Modular Coil System

0 degree 45 degree 90 degree plasma shield blanket coil shield QAR (N=2)

dolan swip 2009 101

slide-102
SLIDE 102

Waste and Recycling

dolan swip 2009 102

(from D. Maisonnier, 2004

slide-103
SLIDE 103

dolan swip 2009 103