SLIDE 1
CCA Draft Final Report
72-Hour Well 6 Water Test Conducted July 13-16, 2020 September 3, 2020
1
CCA Draft Final Report 72-Hour Well 6 Water Test Conducted July - - PowerPoint PPT Presentation
CCA Draft Final Report 72-Hour Well 6 Water Test Conducted July 13-16, 2020 September 3, 2020 1 Histor orical B Backgrou ound: CCA Has Been Pursuing An Increase In Water Capacity For 5+ Years: In 2016 CCA BOD approved an Engineers
1
1
2
the build out cost reasonable if the pump plant was to become permanent.
acceptability.
3
4
5
6
with thick plastic sheeting to direct flow into Blue Lake and minimize its erosive potential.
certified labs
Test.
7
7
9
Well 5 & 6
NWWS draft response to DOH next week.
Wells 1 & 2
Well 2 repairs completed in 2020 – higher reliability
existing NWWS contract
9