SLIDE 13 Details - Construction and Installation Work
13
Work Step Number Proposal Page # Work Step Descripon Duraon in Days Registered Engineer Days Design Engineer Days Roofing Supervisor Days Skilled Roofer Days Crane & Operator Days Extra Costs Total Cost Esmate $ by Design Engineer Total Cost Esmate $ by Other Body 1 Design Review and Changes 15 0.75 5 1,200 2 Create Safety Plan & gain Approval from Worksafe/CERA 10 5 3 Resource and Building Consents
(indicaons are that neither of these may be needed)
5 - 20 5
about $12,000 required if RC is needed
? 4 2 Cleanup, Frame Preparaon and Measurements
- remove rubble and containers
- remove two window covers
- measure frame dimensions
- measure distances to Cathedral
- remove three whalers
- place 4 concrete stability blocks
1.5 1.5 1.5 1.5 1.5 medium
Bobcat hire for 1/2 day to move rubble to another locaon
3,600 5 Adjust Drawings to suit dimensions gained 5 3 6 7 Build two Side Walls
- includes seng up of build procedure for all wall panels
- uses empty 20 litre paint containers (about 50 in total)
to locate panels above ground
- laser level used to create level surface
3 2 1 2 x 3.0 2,560 7 8 Build Porch Roof 2 2 1 2 x 2.0 1,920 8 9 Build West Wall 3 3 1 2 x 3.0 2,560 9 10 Build 4 Stays
(merge with other jobs)
1 1 X 1.0 320 10 3 Install Side Walls and Stays 2 2 2 2 x 2.0 2.0 medium 5,120 11 4 Install Porch Roof 2 2 2 2 x 2.0 2.0 medium 5,120 12 5 Weld 2 support stays to Frame for West Wall 0.25 0.25 2 x 0.25 0.25 medium 480 13 5 Install West Wall 2 2 2 2 x 2.0 2.0 large 2.0 medium 8,640 14 6 Close Roof and Side Returns and install spoung 1 1 1 2 x 1.0 1 large 3,040 15 Site Cleanup 0.5 0.5 2 x 0.5 320 total $ 34,880 Registered Engineer 200
(excludes possible regulatory costs)
Design Engineer (serviced provided free of charge) Roofing Supervisor 80 3.45 Roofer 40 2 roofers full me Large Crane and Operator 220 1 engineer full me Medium Crane and Operator 160 1 roofing supervisor about 2/3 the me Bobcat Hire 60 cranes about 1/2 the me
Work Steps and Costs
(excluding materials)
total weeks on site Esmated Charging Rates in $ / hour