Briefing on grid management charge cost of service study results - - PowerPoint PPT Presentation

briefing on grid management charge cost of service study
SMART_READER_LITE
LIVE PREVIEW

Briefing on grid management charge cost of service study results - - PowerPoint PPT Presentation

Briefing on grid management charge cost of service study results April Gordon Director, Financial Planning and Procurement Board of Governors General Session July 26, 2017 2016 Cost of Service Study Overview Tariff requirement as part of


slide-1
SLIDE 1

Briefing on grid management charge cost of service study results

April Gordon Director, Financial Planning and Procurement Board of Governors General Session July 26, 2017

slide-2
SLIDE 2

2016 Cost of Service Study Overview

  • Tariff requirement as part of current rate structure
  • Tri-annual study in which activity based costing (ABC)

and the revenue requirement components are used to set forth the GMC percentages used to calculate the annual grid management charge rates

Evolution of the GMC Rates Triannual Cost of Service Study's New GMC Percentages

X

Annual Revenue Requirement

/

Estimated GMC Volumes

=

GMC Rates

Slide 2

  • The study also updates the EIM percentages and

transmission ownership rights fee.

slide-3
SLIDE 3

There are 9 process codes and 140 tasks used as part

  • f the ISO activity based costing system

Page 3

Direct Process Codes

Develop Infrastructure Develop Markets Manage Market & Reliability Data & Modeling Manage Market & Grid Manage Operations Support & Settlements Support Customers & Stakeholders

Indirect Process Codes

Manage Human Capabilities Plan & Manage Business Support Business Services

Time and costs associated with direct processes are allocated directly to the GMC cost categories:

  • Market services
  • System operations
  • Congestion revenue

rights services

Time and costs associated with indirect processes are allocated to the GMC cost categories proportional to direct costs.

slide-4
SLIDE 4

Gained efficiencies and reallocation of resources to meet needs leads to change in percentages

Market Services Change – Primarily driven by the addition of 15-minute market and reallocation of resources to create real time market desk (24x7) System Operations Change – Primarily due to process efficiencies implemented since the last cost of service study

Slide 4

GMC Old Percentages 2016 Rates Using Old Percentages New Percentages 2016 Rates Using New Percentages Increase / (Decrease) in Percentages Increase / (Decrease) in Rates Market Services 27% 0.0850 $ 32% 0.1038 $ 5% 0.0188 $ System Operations 70% 0.2979 $ 66% 0.2781 $

  • 4%

(0.0198) $ CRR Services 3% 0.0049 $ 2% 0.0034 $

  • 1%

(0.0015) $

Note: Rates are per MWh

slide-5
SLIDE 5

EIM fee uses real time portions of the GMC

Market Services

Day Ahead Market Real Time Market

System Operations

Balancing Authority Services Real Time Dispatch

CRR Services

Grid Management Charges

Slide 5

slide-6
SLIDE 6

Projected impact to the EIM rate is minimal

Market Services Change – Primarily driven by the addition of 15-minute market and reallocation of resources to create 24X7 real time market desk System Operations Change – Primarily due to process efficiencies implemented since the last cost of service study

Slide 6

GMC EIM Real Time Activity Old Percentages 2016 Rates Using Old Percentages New Percentages 2016 Rates Using New Percentages Increase / (Decrease) in Percentages Increase / (Decrease) in Rates Market Services Real Time Market 61% 0.0519 $ 79% 0.0823 $ 19% 0.0304 $ System Operations Real Time Dispatch 45% 0.1341 $ 39% 0.1078 $

  • 6%

(0.0263) $ Old Total 0.1860 $ New Total 0.1901 $ Note: Rates are per MWh

slide-7
SLIDE 7

The transmission ownership rights fee remains $0.24/per MWh.

Page 7

  • Transmission ownership rights represent transmission capacity on

facilities that are located within the ISO balancing authority area that are wholly or partially owned by an entity that is not a participating transmission owner.

  • Fee offsets the system operations GMC rate.

– Annual revenue ~$650k

  • TOR fee remains $0.24/per MWh
slide-8
SLIDE 8

Next Steps*

Date Event May 24 Stakeholder Meeting **No findings or objections addressed** July 13 Present 2018 GMC update to EIM Governing Body July 26 Present 2018 GMC update to Board of Governors August Amend Tariff September File amended Tariff with FERC December 2018 Revenue Requirement presented to Board of Governors for approval January 1 New percentages go into effect *Dates are subject to change

Slide 8