breakout session cpm scheduling
play

Breakout Session: CPM Scheduling The Full Potential of the CPM - PowerPoint PPT Presentation

Breakout Session: CPM Scheduling The Full Potential of the CPM Scheduling Process Brandon Howell January 29, 2019 LAYTONCONSTRUCTION.COM 2 nd most common cause of disputes in 2016 was poorly drafted or 1/3 of all construction contracts end in


  1. Breakout Session: CPM Scheduling The Full Potential of the CPM Scheduling Process Brandon Howell January 29, 2019 LAYTONCONSTRUCTION.COM 2 nd most common cause of disputes in 2016 was poorly drafted or 1/3 of all construction contracts end in dispute incomplete / unsubstantiated claims - Arcadis: 2017 Global Construction Disputes Report

  2. What We Will Cover… • Scheduling 101 • How to organize and manage your schedule as a defense tool • Key data to monitor in the schedule to avoid liability in the case of claims • Steps needed to maintain documentation during the scheduling process

  3. Schedule in a Nutshell

  4. Organizing your Schedule as a Defense Tool • How to document delays • Backup documentation

  5. Question… When should you As soon as you realize document a delay in the there’s an impact schedule?

  6. Delay Fragnet Example

  7. Weather Delay Example

  8. Use the Notebook

  9. How do you Mitigate Delays? • Watch for trends with trouble subs • Always document the delay first • Understand the impacts and who’s responsible • Make a copy of the schedule • Prepare acceleration options

  10. Backup Documentation Delay Binder Delay Binder Delay Binder Delay Binder

  11. Table of Contents 1 Tab 1 PCO #48 – Building 21 Structural Steel Changes 2 Tab 2 PCO #58 – Bulletin L-008 Revisions to Door Hardware 3 Tab 3 RFI #13 – Unit Height Conflicts 4 Tab 4 RFI #29 – Structural Steel Clarifications 5 Tab 5 RFI #127 – Building 21 Canopy Attachment

  12. Tab 1 1 PCO #48 – Building 21 Structural Steel Changes 2 Delay Fragnet 3 4 5

  13. Tab 1 1 PCO #48 – Building 21 Structural Steel Changes 2 PCO #48 – Time Impact Analysis 3 4 5

  14. Tab 1 1 PCO #48 – Building 21 Structural Steel Changes 2 3 4 5

  15. Tab 2 1 PCO #58 – Bulletin L-008 Revisions to Door Hardware 2 Delay Fragnet 3 4 5

  16. Tab 2 1 PCO #58 – Bulletin L-008 Revisions to Door Hardware 2 3 4 5

  17. What to Monitor in the Schedule • Milestone Management • Determine responsibility • Concurrency analysis • Watch trouble subs closely

  18. Milestone Management Milestone Trending Chart 14 14 12 10 8 9 6 4 2 Baseline Projected Late Finish Projected Acceleration 0 Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 9 Month 10

  19. Determine Responsibility

  20. Concurrency Analysis Concurrent Delays Storefront / Canopy Re-Design Joint Trench Delays RFI #204 - Bored Holes in Walls Permanent Power Delays Lift Station Procurement Drywall Manpower Countertop Procurement RFI #307 - Elevator Counterweight Expansion Joint Procurement Framing Manpower Owner GC 0 10 20 30 40 50 60 70

  21. Steps to Maintain Documentation • Open communication between Scheduler and Project Team • Information that the Scheduler needs • Death by 1,000 cuts / Measles

  22. Open Communication The project team needs to let the Scheduler know of all major changes if there is a potential for schedule impact

  23. Information the Scheduler Needs • What’s the trigger? • Date any documentation was issued (RFI, ASI, etc.) • Copy of the actual document • If added scope, develop delay Fragnet • What activities are being impacted?

  24. Death by 1,000 Cuts Numerous or constant changes to the project

  25. PCO’s vs. Substantial Completion 160 15-Jul-15 147 PCO's vs. Substantial Completion 140 6-Apr-15 Contract Completion 96 120 27-Dec-14 100 Time Extension 80 18-Sep-14 104 60 10-Jun-14 40 51 2-Mar-14 20 0 22-Nov-13 PCO Start PCO Approvals Contract Completion Substantial Completion

  26. Measles Demonstration

  27. GRANITE MOUNTAIN IMPACT ANALYSIS

  28. GRANITE MOUNTAIN Impa pacts S Suc uccess essful ully O Over ercome Thr hroughout t the P he Projec ect • Power Pole – The power pole supplying the main power to the existing building was replaced with a below-grade power feed. • Rock Slide – Boulders sheared off the face of the mountain landing where the new building needed to be built. • Asbestos – The asbestos survey was found to be inaccurate causing a large amount of additional asbestos to require abatement • Lead Paint – The hazardous material survey was found to be inaccurate requiring additional lead paint to require abatement • Existing Operations – Employees were much more sensitive to dust, noise, and odors than expected. • Ground Rock – The soils report indicated that below-grade rock should not have been as large an impact as it was. • Avalanches – Snow and ice slide threats were not expected to impact the project as much as they did. • Rock Pinning and Analysis – The need to pin rock and analyze the threats to safety were not expected. • Winter – The project was originally expected to span one winter, but was required to span two.

  29. PERMANENT POWER MOVED UNDERGROUND

  30. LAYTON RELEASED TO START CONSTRUCTION

  31. CONCRETE IMPACT #10 - Potential Water Tank Rock Slide / Tank Re-Design CONCRETE IMPACT #3 - RFI #195 & 196 – Grade Beam Delay

  32. CONCRETE IMPACT #7- Snow & Ice Slides

  33. CONCRETE IMPACT #8A - Design flaws between architectural & structural CONCRETE IMPACT #8B - 2ea Missing CC3 columns on structural S302, C2 & C7

  34. CONCRETE IMPACT #14 - Hydration of leveling slabs in the vaults – Added cost of de-humid CONCRETE IMPACT #1 - Column size discrepancies (A line S302 vs A line A302)

  35. CONCRETE IMPACT #12 - 2 nd Floor Matt Slab Change Re-Sequencing from Delays

  36. FINAL COMPLETION DATE DECEMBER 2, 2015

  37. PCO #001 PCO #018 PCO #035 PCO #052 PCO #069 PCO #086 PCO #103 PCO #120 PCO #137 PCO #154 PCO #171 PCO #188 PCO #205 PCO #222 PCO #002 PCO #019 PCO #036 PCO #053 PCO #070 PCO #087 PCO #104 PCO #121 PCO #138 PCO #155 PCO #172 PCO #189 PCO #206 PCO #223 PCO #003 PCO #020 PCO #037 PCO #054 PCO #071 PCO #088 PCO #105 PCO #122 PCO #139 PCO #156 PCO #173 PCO #190 PCO #207 PCO #224 PCO #004 PCO #021 PCO #038 PCO #055 PCO #072 PCO #089 PCO #106 PCO #123 PCO #140 PCO #157 PCO #174 PCO #191 PCO #208 PCO #225 PCO #005 PCO #022 PCO #039 PCO #056 PCO #073 PCO #090 PCO #107 PCO #124 PCO #141 PCO #158 PCO #175 PCO #192 PCO #209 PCO #006 PCO #023 PCO #040 PCO #057 PCO #074 PCO #091 PCO #108 PCO #125 PCO #142 PCO #159 PCO #176 PCO #193 PCO #210 PCO #007 PCO #024 PCO #041 PCO #058 PCO #075 PCO #092 PCO #109 PCO #126 PCO #143 PCO #160 PCO #177 PCO #194 PCO #211 PCO #008 PCO #025 PCO #042 PCO #059 PCO #076 PCO #093 PCO #110 PCO #127 PCO #144 PCO #161 PCO #178 PCO #195 PCO #212 PCO #009 PCO #026 PCO #043 PCO #060 PCO #077 PCO #094 PCO #111 PCO #128 PCO #145 PCO #162 PCO #179 PCO #196 PCO #213 PCO #010 PCO #027 PCO #044 PCO #061 PCO #078 PCO #095 PCO #112 PCO #129 PCO #146 PCO #163 PCO #180 PCO #197 PCO #214 PCO #011 PCO #028 PCO #045 PCO #062 PCO #079 PCO #096 PCO #113 PCO #130 PCO #147 PCO #164 PCO #181 PCO #198 PCO #215 PCO #012 PCO #029 PCO #046 PCO #063 PCO #080 PCO #097 PCO #114 PCO #131 PCO #148 PCO #165 PCO #182 PCO #199 PCO #216 PCO #013 PCO #030 PCO #047 PCO #064 PCO #081 PCO #098 PCO #115 PCO #132 PCO #149 PCO #166 PCO #183 PCO #200 PCO #217 PCO #014 PCO #031 PCO #048 PCO #065 PCO #082 PCO #099 PCO #116 PCO #133 PCO #150 PCO #167 PCO #184 PCO #201 PCO #218 PCO #015 PCO #032 PCO #049 PCO #066 PCO #083 PCO #100 PCO #117 PCO #134 PCO #151 PCO #168 PCO #185 PCO #202 PCO #219 PCO #016 PCO #033 PCO #050 PCO #067 PCO #084 PCO #101 PCO #118 PCO #135 PCO #152 PCO #169 PCO #186 PCO #203 PCO #220 PCO #017 PCO #034 PCO #051 PCO #068 PCO #085 PCO #102 PCO #119 PCO #136 PCO #153 PCO #170 PCO #187 PCO #204 PCO #221

  38. THANK YOU! Brandon Howell Manager of Corporate Scheduling Layton Construction Company 801-556-3807 bhowell@laytonconstruction.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend