Breakout Session: CPM Scheduling The Full Potential of the CPM - - PowerPoint PPT Presentation

breakout session cpm scheduling
SMART_READER_LITE
LIVE PREVIEW

Breakout Session: CPM Scheduling The Full Potential of the CPM - - PowerPoint PPT Presentation

Breakout Session: CPM Scheduling The Full Potential of the CPM Scheduling Process Brandon Howell January 29, 2019 LAYTONCONSTRUCTION.COM 2 nd most common cause of disputes in 2016 was poorly drafted or 1/3 of all construction contracts end in


slide-1
SLIDE 1

Breakout Session: CPM Scheduling

The Full Potential of the CPM Scheduling Process

Brandon Howell January 29, 2019

LAYTONCONSTRUCTION.COM

2nd most common cause of disputes in 2016 was poorly drafted or incomplete / unsubstantiated claims 1/3 of all construction contracts end in dispute

  • Arcadis: 2017 Global Construction Disputes Report
slide-2
SLIDE 2
  • Scheduling 101
  • How to organize and manage your schedule as a

defense tool

  • Key data to monitor in the schedule to avoid

liability in the case of claims

  • Steps needed to maintain documentation during

the scheduling process

What We Will Cover…

slide-3
SLIDE 3

Schedule in a Nutshell

slide-4
SLIDE 4
  • How to document delays
  • Backup documentation

Organizing your Schedule as a Defense Tool

slide-5
SLIDE 5

Question…

When should you document a delay in the schedule? As soon as you realize there’s an impact

slide-6
SLIDE 6

Delay Fragnet Example

slide-7
SLIDE 7

Weather Delay Example

slide-8
SLIDE 8

Use the Notebook

slide-9
SLIDE 9

How do you Mitigate Delays?

  • Watch for trends with trouble subs
  • Always document the delay first
  • Understand the impacts and who’s

responsible

  • Make a copy of the schedule
  • Prepare acceleration options
slide-10
SLIDE 10

Backup Documentation

Delay Binder Delay Binder Delay Binder Delay Binder

slide-11
SLIDE 11

1 2 3 4 5 Table of Contents

Tab 1 PCO #48 – Building 21 Structural Steel Changes Tab 2 PCO #58 – Bulletin L-008 Revisions to Door Hardware Tab 3 RFI #13 – Unit Height Conflicts Tab 4 RFI #29 – Structural Steel Clarifications Tab 5 RFI #127 – Building 21 Canopy Attachment

slide-12
SLIDE 12

1 2 3 4 5 PCO #48 – Building 21 Structural Steel Changes

Delay Fragnet

Tab 1

slide-13
SLIDE 13

1 2 3 4 5 PCO #48 – Building 21 Structural Steel Changes

Tab 1

PCO #48 – Time Impact Analysis

slide-14
SLIDE 14

1 2 3 4 5 PCO #48 – Building 21 Structural Steel Changes

Tab 1

slide-15
SLIDE 15

1 2 3 4 5 PCO #58 – Bulletin L-008 Revisions to Door Hardware

Delay Fragnet

Tab 2

slide-16
SLIDE 16

1 2 3 4 5 PCO #58 – Bulletin L-008 Revisions to Door Hardware

Tab 2

slide-17
SLIDE 17
  • Milestone Management
  • Determine responsibility
  • Concurrency analysis
  • Watch trouble subs closely

What to Monitor in the Schedule

slide-18
SLIDE 18

Milestone Management

2 4 6 8 10 12 14 Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 9 Month 10

Milestone Trending Chart

Baseline Projected Late Finish Projected Acceleration

14 9

slide-19
SLIDE 19

Determine Responsibility

slide-20
SLIDE 20

Concurrency Analysis

10 20 30 40 50 60 70 Framing Manpower Expansion Joint Procurement RFI #307 - Elevator Counterweight Countertop Procurement Drywall Manpower Lift Station Procurement Permanent Power Delays RFI #204 - Bored Holes in Walls Joint Trench Delays Storefront / Canopy Re-Design

Concurrent Delays

Owner GC

slide-21
SLIDE 21
  • Open communication between Scheduler and

Project Team

  • Information that the Scheduler needs
  • Death by 1,000 cuts / Measles

Steps to Maintain Documentation

slide-22
SLIDE 22

Open Communication

The project team needs to let the Scheduler know of all major changes if there is a potential for schedule impact

slide-23
SLIDE 23

Information the Scheduler Needs

  • What’s the trigger?
  • Date any

documentation was issued (RFI, ASI, etc.)

  • Copy of the actual

document

  • If added scope, develop

delay Fragnet

  • What activities are

being impacted?

slide-24
SLIDE 24

Death by 1,000 Cuts

Numerous or constant changes to the project

slide-25
SLIDE 25

PCO’s vs. Substantial Completion

22-Nov-13 2-Mar-14 10-Jun-14 18-Sep-14 27-Dec-14 6-Apr-15 15-Jul-15 20 40 60 80 100 120 140 160

PCO's vs. Substantial Completion

PCO Start PCO Approvals Contract Completion Substantial Completion

Time Extension Contract Completion

96 51 147 104

slide-26
SLIDE 26

Measles Demonstration

slide-27
SLIDE 27

GRANITE MOUNTAIN

IMPACT ANALYSIS

slide-28
SLIDE 28

GRANITE MOUNTAIN Impa pacts S Suc uccess essful ully O Over ercome Thr hroughout t the P he Projec ect

  • Power Pole – The power pole supplying the main power to the existing building was replaced with a below-grade power feed.
  • Rock Slide – Boulders sheared off the face of the mountain landing where the new building needed to be built.
  • Asbestos – The asbestos survey was found to be inaccurate causing a large amount of additional asbestos to require abatement
  • Lead Paint – The hazardous material survey was found to be inaccurate requiring additional lead paint to require abatement
  • Existing Operations – Employees were much more sensitive to dust, noise, and odors than expected.
  • Ground Rock – The soils report indicated that below-grade rock should not have been as large an impact as it was.
  • Avalanches – Snow and ice slide threats were not expected to impact the project as much as they did.
  • Rock Pinning and Analysis – The need to pin rock and analyze the threats to safety were not expected.
  • Winter – The project was originally expected to span one winter, but was required to span two.
slide-29
SLIDE 29
slide-30
SLIDE 30
slide-31
SLIDE 31

PERMANENT POWER MOVED UNDERGROUND

slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36

LAYTON RELEASED TO START CONSTRUCTION

slide-37
SLIDE 37
slide-38
SLIDE 38

CONCRETE IMPACT #3 - RFI #195 & 196 – Grade Beam Delay CONCRETE IMPACT #10 - Potential Water Tank Rock Slide / Tank Re-Design

slide-39
SLIDE 39
slide-40
SLIDE 40

CONCRETE IMPACT #7- Snow & Ice Slides

slide-41
SLIDE 41
slide-42
SLIDE 42

CONCRETE IMPACT #8A - Design flaws between architectural & structural CONCRETE IMPACT #8B - 2ea Missing CC3 columns on structural S302, C2 & C7

slide-43
SLIDE 43
slide-44
SLIDE 44

CONCRETE IMPACT #1 - Column size discrepancies (A line S302 vs A line A302) CONCRETE IMPACT #14 - Hydration of leveling slabs in the vaults – Added cost of de-humid

slide-45
SLIDE 45
slide-46
SLIDE 46

CONCRETE IMPACT #12 - 2nd Floor Matt Slab Change Re-Sequencing from Delays

slide-47
SLIDE 47
slide-48
SLIDE 48

FINAL COMPLETION DATE DECEMBER 2, 2015

slide-49
SLIDE 49

PCO #001 PCO #002 PCO #003 PCO #004 PCO #005 PCO #006 PCO #007 PCO #008 PCO #009 PCO #010 PCO #011 PCO #012 PCO #013 PCO #014 PCO #015 PCO #016 PCO #017 PCO #018 PCO #019 PCO #020 PCO #021 PCO #022 PCO #023 PCO #024 PCO #025 PCO #026 PCO #027 PCO #028 PCO #029 PCO #030 PCO #031 PCO #032 PCO #033 PCO #034 PCO #035 PCO #036 PCO #037 PCO #038 PCO #039 PCO #040 PCO #041 PCO #042 PCO #043 PCO #044 PCO #045 PCO #046 PCO #047 PCO #048 PCO #049 PCO #050 PCO #051 PCO #052 PCO #053 PCO #054 PCO #055 PCO #056 PCO #057 PCO #058 PCO #059 PCO #060 PCO #061 PCO #062 PCO #063 PCO #064 PCO #065 PCO #066 PCO #067 PCO #068 PCO #069 PCO #070 PCO #071 PCO #072 PCO #073 PCO #074 PCO #075 PCO #076 PCO #077 PCO #078 PCO #079 PCO #080 PCO #081 PCO #082 PCO #083 PCO #084 PCO #085 PCO #086 PCO #087 PCO #088 PCO #089 PCO #090 PCO #091 PCO #092 PCO #093 PCO #094 PCO #095 PCO #096 PCO #097 PCO #098 PCO #099 PCO #100 PCO #101 PCO #102 PCO #103 PCO #104 PCO #105 PCO #106 PCO #107 PCO #108 PCO #109 PCO #110 PCO #111 PCO #112 PCO #113 PCO #114 PCO #115 PCO #116 PCO #117 PCO #118 PCO #119 PCO #120 PCO #121 PCO #122 PCO #123 PCO #124 PCO #125 PCO #126 PCO #127 PCO #128 PCO #129 PCO #130 PCO #131 PCO #132 PCO #133 PCO #134 PCO #135 PCO #136 PCO #137 PCO #138 PCO #139 PCO #140 PCO #141 PCO #142 PCO #143 PCO #144 PCO #145 PCO #146 PCO #147 PCO #148 PCO #149 PCO #150 PCO #151 PCO #152 PCO #153 PCO #154 PCO #155 PCO #156 PCO #157 PCO #158 PCO #159 PCO #160 PCO #161 PCO #162 PCO #163 PCO #164 PCO #165 PCO #166 PCO #167 PCO #168 PCO #169 PCO #170 PCO #171 PCO #172 PCO #173 PCO #174 PCO #175 PCO #176 PCO #177 PCO #178 PCO #179 PCO #180 PCO #181 PCO #182 PCO #183 PCO #184 PCO #185 PCO #186 PCO #187 PCO #188 PCO #189 PCO #190 PCO #191 PCO #192 PCO #193 PCO #194 PCO #195 PCO #196 PCO #197 PCO #198 PCO #199 PCO #200 PCO #201 PCO #202 PCO #203 PCO #204 PCO #205 PCO #206 PCO #207 PCO #208 PCO #209 PCO #210 PCO #211 PCO #212 PCO #213 PCO #214 PCO #215 PCO #216 PCO #217 PCO #218 PCO #219 PCO #220 PCO #221 PCO #222 PCO #223 PCO #224 PCO #225

slide-50
SLIDE 50

THANK YOU!

Brandon Howell

Manager of Corporate Scheduling Layton Construction Company 801-556-3807 bhowell@laytonconstruction.com