bonita peak cag 2 28 2019 peter butler ph d
play

Bonita Peak CAG 2/28/2019 Peter Butler, Ph.D. Draft IRAP Summary - PowerPoint PPT Presentation

Bonita Peak CAG 2/28/2019 Peter Butler, Ph.D. Draft IRAP Summary Addresses 26 Sites Out of 46 Sites and Two Study Areas. Actions Are Interim; More May Be Done at these Sites. Adaptive Management Approach. Enables Early


  1. Bonita Peak CAG 2/28/2019 Peter Butler, Ph.D.

  2. Draft IRAP Summary   Addresses 26 Sites Out of 46 Sites and Two Study Areas.  Actions Are Interim; More May Be Done at these Sites.  Adaptive Management Approach.  Enables Early Actions at Multiple Sites to Speed Up Process.  Smaller Sites, Generally Privately Owned.  No BLM Owned Sites; One at least Partly Owned by Forest Service.

  3. Five Possible Alternatives   A. Move Mine Drainage Away from Mine Waste – 20 sites.  B. Divert Upland Flow around Mine Waste. – 11 sites.  C. Remove Sediment from Ponds Treating Drainage – 8 sites.  D. Remove In-Stream Mine Waste – 2 sites.  E. Cover Recreation Sites with Human Health Risk – 5 sites.

  4. An Example of Costs   Alternative A – Diversion/Isolation Total Capital Cost: $1,082,000  Total Annual O&M Cost (15 years): $1,890,000  Total Periodic O&M Cost (15 years): $301,000   Total Alternative Cost (PV): $2,411,000  ---------------------------------------------------------  Total Capital Cost A+B+C+D= $3.8 million.  Total Present Value Cost A+B+C+D= $8.3 million.

  5. Concerns in Comments   High Costs – Possible Double Counting .  A. Divert Drainage – Capital Cost: $55,000/site; Total PV: $120,000/site.  B. Divert Stormwater - Capital Cost: $91,000/site; Total PV: $173,000/site.  C. Excavate Sediment - Capital Cost: $175,000/site; Total PV: $425,000/site.  D. In-Stream Waste - Capital Cost: $170,000/site; Total PV: $312,000/site.

  6. Lack of Estimated Benefits   Lots of Water Quality Data Showing Toxic Metal Concentrations.  No Estimates of Possible Metal Reductions at Sites.  No Estimates of How Sites Are Affecting Water Quality in Nearby Streams.  No Estimates of How Alternatives Will Improve Aquatic Life.

  7. Lack of Prioritization   No Prioritization between Sites in IRAP .  Costs Should Be Allocated by Site Not Alternative.  Estimate Metal Reductions per Unit Cost (Biggest Bang for the Buck).  No Prioritization with Other Possible Projects .  Compare Cost/Benefit to Doing Additional Work at Some Sites vs. BMP’s at All Sites.  Compare Cost/Benefit to More Fully Using Treatment at Gladstone.

  8. Adaptive Management   Theoretically, Could be Quite Useful.  Need to Estimate Costs and Benefits of Action, Implement Action, Compare Actual Costs and Benefits to Estimated.  So Far, No Estimates of Benefits and No Plan or Dollars Allocated for Analysis after Interim Action Implementation.  Potentially Responsible Parties (PRP’s) Don’t Like Uncertainty of Adaptive Management.

  9. Questions? 

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend