BATAVIA CITY SCHOOL DISTRICT 2020 VISION CAPITAL PROJECT BATAVIA - - PowerPoint PPT Presentation

BATAVIA CITY SCHOOL DISTRICT 2020 VISION CAPITAL PROJECT BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT Developing Our 2020 Vision 1. 5 Year Condition Survey for NYSED 2. Hired Campus Construction Management 3. Hired Wendel


slide-1
SLIDE 1

BATAVIA CITY SCHOOL DISTRICT 2020 VISION CAPITAL PROJECT

slide-2
SLIDE 2

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Developing Our 2020 Vision

  • 1. 5 Year Condition Survey for NYSED
  • 2. Hired Campus Construction Management
  • 3. Hired Wendel Architects
  • 4. Buildings and Grounds Committee
  • 5. District Administration Input
  • 6. Community Input
  • 7. Completed multiple scope of work studies
  • 8. NYSED aid-ability review study process
  • 9. BOE Vote in January 2017
  • 10. Public Vote in March 2017
slide-3
SLIDE 3

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Batavia Middle School

Renovate building entrance and improve building security/access Expand music areas. Upgrade finishes in gymnasium, stair halls, auditorium and classrooms. Indoor air quality improvements. Repair canopies. Replacement of roof areas. Upgrade auditorium sound and projection systems. Upgrade lighting and PA systems.

Scope of Work 1 2 3 4 5 6 7 8

Visit www.bataviacsd.org for more information on the propositions for the Batavia Middle School.

1 2 3 4 4 5 5 7 6 8

slide-4
SLIDE 4

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Batavia High School

Auditorium upgrades including finishes, lighting and sound system, acoustical improvements and improved orchestra pit. Upgrade fire alarm systems. Expand restroom facilities. Roofing replacements. Improve parent drop-off configuration and pedestrian access to building.

Scope of Work 1 2 3 1 3 2 2 4 4 4 5 5

Visit www.bataviacsd.org for more information on the propositions for the Batavia High School.

slide-5
SLIDE 5

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Batavia High School

Improve parent drop-off configuration and pedestrian access to building.

Scope of Work 1 3 1

Visit www.bataviacsd.org for more information on the propositions for the Batavia High School.

slide-6
SLIDE 6

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Jackson Primary School

Upgrade finishes in classrooms. Expand restroom facilities. Upgrade lighting system. Exterior window replacements. Replace mechanical systems.

Scope of Work 1 2 3 4 5

Visit www.bataviacsd.org for more information on the propositions for the Jackson Primary School.

1 2 5 3 4

slide-7
SLIDE 7

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Richmond Memorial Library

Upgrade floor and wall finishes. Accessible walkway to lower parking area. Ventilation upgrades. Fire alarm system upgrades.

Scope of Work 1 2 3 4 5

Visit www.bataviacsd.org for more information on the propositions for the Richmond Memorial Library.

1 2 3 4

slide-8
SLIDE 8

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

John Kennedy Intermediate School

Classroom addition Reconfiguration of interior spaces to provide adequate special education, small group instruction and music rooms. Window replacements and roofing repairs. Upgrade lighting systems. Improve parent drop-off configuration and pedestrian access to building. Improve sound systems and acoustics.

Scope of Work 1 2 3 4 5 6

Visit www.bataviacsd.org for more information on the propositions for the John Kennedy Intermediate School.

1 2 5 3 6 4 3 4

slide-9
SLIDE 9

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

John Kennedy Intermediate School

Classroom addition Improve parent drop-off configuration and pedestrian access to building. Resurface bus drop-off

Scope of Work 1 2

Visit www.bataviacsd.org for more information on the propositions for the John Kennedy Intermediate School.

1 2 2 3 3

slide-10
SLIDE 10

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Daniel A. Van Detta Stadium at Woodward Field

Restore ticket booth and entrance gates. New 8-lane track and synthetic turf field. New press box and bleachers with locker room facilities below. Expand parking lot. New scoreboard. Existing concession building and weight room. New storage garage.

Scope of Work 1 2 3 4 5 6 7

Visit www.bataviacsd.org for more information on the propositions for the Daniel A. Van Detta Stadium at Woodward Field.

1 2 3 4 5 7 6 4

slide-11
SLIDE 11

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Project Financial Review

Project Authorization Total: $26,768,813

  • Use of $7.5 million from Capital Reserve Fund
  • Balance is aided by NYS

Additional Tax Impact: $0

slide-12
SLIDE 12

BATAVIA CITY SCHOOL DISTRICT | 2020 VISION CAPITAL PROJECT

Potential Project Schedule Durations

BOE Referendum Resolution January 10, 2017 2020 Vision Capital Project Vote March 2, 2017 Project Design Phase March 2017 - December 2017 SED Review Phase December 2017 - July 2018 Bid Phase August 2018 - September 2018 BOE Award Construction Contracts September 2018 Construction Phase September 2018 - September 2019 Project Close-out October 2019 - November 2019 Final Cost Report Submission December 2019

slide-13
SLIDE 13

BATAVIA CITY SCHOOL DISTRICT 2020 VISION CAPITAL PROJECT

Questions?