Bamboo As a Viable Alternative to Steel Reinforcement in Concrete
TYSON BALDREY, RANDY HOLMBERG, ALLAN JOHNSTON RSR-2265 INSTRUCTOR: LORNE ATWOOD APRIL 5, 2018
Bamboo As a Viable Alternative to Steel Reinforcement in Concrete - - PowerPoint PPT Presentation
Bamboo As a Viable Alternative to Steel Reinforcement in Concrete TYSON BALDREY, RANDY HOLMBERG, ALLAN JOHNSTON RSR-2265 INSTRUCTOR: LORNE ATWOOD APRIL 5, 2018 Research Question We intended to validate, through experimentation and analysis,
TYSON BALDREY, RANDY HOLMBERG, ALLAN JOHNSTON RSR-2265 INSTRUCTOR: LORNE ATWOOD APRIL 5, 2018
Why Bamboo?
Steel reinforcement bar (rebar) Limited availability in developing
counties
Higher expense than bamboo Large carbon footprint in
manufacturing
Bamboo Natural, sustainable, renewable Low carbon footprint More readily available than steel in
import-dependent countries
We intended to validate, through experimentation and analysis, the structural suitability
National Geographic, 1980 Global natural bamboo habitat
We hypothesized the following:
that bamboo does not offer as much
strength as that of steel rebar
that using bamboo in some cases offers a
cost-effective alternative to using steel rebar
that the injected bamboo is somewhat
stronger than non-injected bamboo
Karthik, Ram Mohan Rao, and Awoyera (2016) – found a growing trend toward finding suitable alternatives to high-embodied energy materials like steel for both developing and developed countries Xiao, Inoue, & Paudel (2007) – states builders are developing, testing, & using bamboo as low-cost, low-carbon alternative Rahman, M.; Rashid, M.; et alai. (2011) – studied cost & availability Vanasupa (2011) – found that cellular structure absorbs water, causing swelling, expansion; voids, loss of adhesion Agarwala et alai, (2014) – tests to improved cohesion Agarwala, Nandab, & Maitya, 2014 – more testing is needed Varma & Paduvil (2007) – skilled labour is needed Agarwala, A.; Nandab, B.; & Maitya, D., 2014 – more training must be done
Bamboo Water Absorption Concrete Cylinder Compression Bamboo Reinforcement Beam Bending Steel Rebar Reinforcement Beam Bending Bamboo Tension Test Bamboo Deflection Test
Bamboo
in 20” (508mm) lengths @ avg.
10mm dia.
Elastomeric Polyurethane
high workability broad availability favorable tensile & compressive properties
Coarse Sand & Elastomeric Polyurethane
mixture
waterproofing and binding agent ratio [3/4] sand : [1] polyurethane
Concrete
8.93% water 19.37% cement 28.35% fine aggregate 43.37% course aggregate
Carbon Steel Rebar
in 20” (508mm) lengths @ 10mm dia.
Forney F-450F: Cylinder Compression Forney Q-400D: Beam Compression Tinius Olsen UTM: Bamboo Tension Deflection Apparatus: Bamboo Deflection
To allow for injection
Clean out debris
Let set for 7 days
For future tests
For placing in beam moulds (20” or 508mm)
In polyurethane lacquer and In polyurethane sealant and sand mixture (1 part polyurethane : 3/4 part sand). Let cure for 7 Days.
42 8 57 18 98 17 112 26 386 508 104 508 107 508 100 508 100 508 9 15 18 17 10 15 19 18 11 100 200 300 400 500 Non-Injected, Non-Coated Non-Injected, Non-Coated Non-Injected, Coated Non-Injected, Coated Injected, Non- Coated Injected, Non- Coated Injected, Coated Injected, Coated Rebar 1 2 3 4 5 6 7 8 9
Weight (Grams) Length (mm) Diameter (mm)
kinds of samples Collect length, weight, and diameter
In temperature regulated area For calculating average 21.9°C
8 104 15.29 1.95 17 103.78 15.69 4.16 18 107 17.25 4.27 23 106.48 17.68 5.49 17 100 15.25 4.32 24 99.06 17.29 6.15 26 100 18.00 6.60 30 100.30 18.60 7.60 10 20 30 40 50 60 70 80 90 100 110 120 Weight (Grams) Length (mm) Diameter (mm) Weight Per Length (g/25.4mm) Weight (Grams) Length (mm) Diameter (mm) Weight Per Length (g/25.4mm) Origonal data After Soak Non-Injected (Non-Coating) Non-Injected (Coated with Sand & Poly.) Injected (Non-Coated) Injected (Coated with Sand & Poly.) Original Data
9.00 5.00 7.00 4.00
0.30 0.40 0.44 2.04 0.60 2.21 1.21 1.84 0.99
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00 5.50 6.00 6.50 7.00 7.50 8.00 8.50 9.00 9.50 Non-Injected (Non-Coating) Non-Injected (Coated with Sand & Poly.) Injected (Non-Coated) Injected (Coated with Sand & Poly.)
Difference in data Weight (Grams) Difference in data Length (mm) Difference in data Diameter (mm) Difference in data Weight Per Length (g/25.4mm)
Using standard ratio and adding to each batch to suit
Performing a slump test for each batch of concrete
24 hours before removed from moulds
After 24 hours
Temperature controlled at 25°C for 28 days.
To evaluate the
standardization of our concrete mixture
Cylinders are loaded into
the compression machine and put under increasing load until failure.
ASTM International, 2018
Observed Fracture Modes
459.00 295.45 485.90 401.75 442.20 430.00 443.77 56.62 36.44 60.06 49.56 54.55 53.04 54.77 175.00 95.00 170.00 115.00 115.00 130.00 141.00 50 100 150 200 250 300 350 400 450 500 1 2 3 4 5 6 Average
Load (kN) Compressive Strength (MPa) Slump (cm)
Beams are loaded into
the machine and incrementally loaded until failure.
Majority of the beams
failed due to flexure cracks rather than catastrophic separation
38.57 151.85 50.69 16.6 61.53 51.66 33.1 4.9 19.31 6.44 2.11 7.82 6.57 4.21 20 40 60 80 100 120 140 160 Non-Injected (Coated with Sand & Poly.) Rebar Injected (Coated with Sand & Poly.) Non-Injected (Coated with Sand & Poly.) Injected (Coated with Sand & Poly.) Injected (Coated with Sand & Poly.) Non-Injected (Coated with Sand & Poly.) 1 2 3 4 5 6 7
Loading (kN) Modulus of Rupture (MPa)
29.42 54.63 3.74 6.94 0.00 10.00 20.00 30.00 40.00 50.00 60.00 Non-Injected (Coated with Sand & Poly.) Injected (Coated with Sand & Poly.)
Loading (kN) Modulus of Rupture (MPa)
Set distance between pin supports 17 inches
Measure deflection
18.56 18.56 10.28 10.28 18.34 18.34 9.1 9.1 5 5 4 6 6 5 7 7 2 4 6 8 10 12 14 16 18 20 Injected (Coated with Sand & Poly.) Injected (Coated with Sand & Poly.) Injected (Non-Coated) Injected (Non-Coated) Non-Injected (Coated with Sand & Poly.) Non-Injected (Coated with Sand & Poly.) Non-Injected (Non- Coating) Non-Injected (Non- Coating) 1A 1B 2A 2B 3A 3B 4A 4B
Average Diameter (mm) Change in Height (=Deflection) 61 61 60 60 61 62 60 58 56 56 56 54 55 57 53 51 10 20 30 40 50 60 70 Injected (Coated with Sand & Poly.) Injected (Coated with Sand & Poly.) Injected (Non-Coated) Injected (Non-Coated) Non-Injected (Coated with Sand & Poly.) Non-Injected (Coated with Sand & Poly.) Non-Injected (Non- Coating) Non-Injected (Non- Coating) 1A 1B 2A 2B 3A 3B 4A 4B
Height from Baseline (mm) Deflected Height From Baseline (mm)
10mm Bamboo #3M Carbon Steel Rebar
LOAD = 147 N
398.78 107.36 140.69 398.78 34.93 34.93 47.44 47.44 25.00 25.00
33.33
0.00 50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00 450.00 Steel Rebar Bamboo Coated, Non-Injected Bamboo Coated, Injected Weight (g)
Material Used
Weights of Individual Components of Reinforcement Bars (per 20-inch)
Total Carbon Steel Bamboo Polyurethane Coating Sand Polyurethane Injection
*Costs based on local retail purchase prices
Cost as Compared to Steel Coated, Non-injected Coated, Injected Percent Savings in Cost 56.4% 21.2%
$1.49 $0.65 $1.17 $1.49 $0.45 $0.45 $0.19 $0.19 $0.01 $0.01 $0.52 $0.00 $0.20 $0.40 $0.60 $0.80 $1.00 $1.20 $1.40 $1.60 Steel Rebar Bamboo, Coated, Non-Injected Bamboo, Coated, Injected Material Cost
Material Used
Cost per Unit of Length (20-inch)
Total Carbon Steel Bamboo Polyurethane Coating Sand Polyurethane Injection
Weight as Compared to Steel Coated, Non- Injected Coated, Injected Percent Savings in Weight 73.1% 64.7%
Injected bamboo was indeed stronger than
bamboo by itself. It held 1/3 the load of a standard steel rebar reinforced beam.
Injected bamboo is 21.2% more cost effective
than steel rebar.
Injected bamboo is 3 times lighter than steel
rebar.
Injected bamboo has a lower deflection
magnitude than that of non-injected bamboo.
Water absorption still occurred within the
bamboo.
Our Hypothesis
√
Bamboo does not offer as much strength as that of steel rebar.
√
In some cases, using bamboo offers a cost-effective alternative to using steel rebar.
√
Injected bamboo is stronger than non- injected bamboo.
Therefore, within the confines of our testing parameters, bamboo is a viable alternative to steel reinforcement.
Bamboo slippage within concrete beams Unpredictability of castings process Human error Time constraints Cost & donation constraints Material availability restrictions Limitations of testing equipment Tensile test Small sample groups Limited experience in field of bamboo research
Applied structural testing of
natural injectable material (i.e. Chicle and Latex)
Alternate material combinations In depth global financial analysis
More structural analysis of
bamboo sub-species
Conduct a long-term use study Degradation of in-situ bamboo
Structural application of bamboo
laminates
Application of genetic
engineering and high yield bamboo production
Further study of thermal expansion
rates of bamboo
Thank you to all those who contributed their time, materials, & expertise.