B05 4 Global Correlator 402.06.05 R. Cavanaugh U. Illinois Chicago - - PowerPoint PPT Presentation

b05 4 global correlator 402 06 05
SMART_READER_LITE
LIVE PREVIEW

B05 4 Global Correlator 402.06.05 R. Cavanaugh U. Illinois Chicago - - PowerPoint PPT Presentation

B05 4 Global Correlator 402.06.05 R. Cavanaugh U. Illinois Chicago and Fermilab, L3 Manager, HL-LHC Global Correlator 402.06.05 Directors Review of US-CMS HL-LHC Upgrades 2-3 February 2016 R. Cavanaugh, 2015 February 2-3 Director's


slide-1
SLIDE 1

B05 – 4 Global Correlator 402.06.05

  • R. Cavanaugh U. Illinois Chicago and Fermilab,

L3 Manager, HL-LHC Global Correlator 402.06.05 Director’s Review of US-CMS HL-LHC Upgrades 2-3 February 2016

1

Director's Review – L1 Trigger Overview

  • R. Cavanaugh, 2015 February 2-3
slide-2
SLIDE 2

§ WBS definition § Basis of Estimate § Schedule § Cost and Labor Profiles § Risk and Contingency § R&D status and plans § ES&H and QA § Summary

2

Outline

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

slide-3
SLIDE 3

3

402.06 Organization Chart to L3

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

402.06 Trigger Jeff Berryhill (FNAL) 402.06.03 Calorimeter Trigger Wesley Smith (UW) 402.06.04 Muon Trigger Darin Acosta (UF) 402.06.05 Global Correlator Rick Cavanaugh (UIC/FNAL)

slide-4
SLIDE 4

§ R.C. (U. Illinois Chicago and Fermilab) § CMS Particle Flow & Tau ID Convener 2007-2008 § Fermilab LHC Physics Center Coordinator 2010-2013 § Phase-1 Stage-1 Global Calorimeter Trigger § Wesley Smith (U. Wisconsin) – US CMS HL-LHC L3 Calorimeter Trigger Project Manager § CMS Trigger Project Manager 1994-2007, § Trigger Coordinator 2007 – 2012 § Trigger Performance and Strategy Working Group 2012 - 2015 § US CMS L2 Trigger Project Manager (construction and operations) 1998 – present § US CMS Phase 1 Upgrade L2 Trigger Project Manager 2013 – present § Sridhara Dasu (U. Wisconsin) § US CMS L3 Manager Calorimeter Trigger (construction & operations) 1998 – present § US CMS L3 Manager Phase 1 Calorimeter Trigger Upgrade 2013 – present § Author of original and upgrade cal. trig. Algorithms 1994 – present § Darin Acosta (U. Florida) § CMS Trigger (co)Project Manager, 2012-16 § EMU Track-Finder, 1998- present § Ivan Furic (U.Florida) § CSC and EMU Track-Finder projects, 2008-present § Alexi Safonov (TAMU) § CSC Trigger Motherboards § Jeff Berryhill (Fermilab) § CMS & US CMS Phase-1 Stage-1 Calorimeter Trigger Project Manager

4

CMS Correlator Management Experience

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 3

slide-5
SLIDE 5

§ Tom Gorski (U. Wisconsin) – Electrical Engineer – Lead Engineer § Over a decade of engineering on the CMS Calorimeter Trigger § Delivered final phase of original Regional CMS Calorimeter Trigger § Delivered Phase 1 Layer-1 Calorimeter Trigger Upgrade Electronics § Ales Svetek (U. Wisconsin) – Firmware Engineer § 3 years on Phase 1 Calorimeter Trigger Upgrade Firmware § (4 years ATLAS Beam Conditions Monitor Firmware, DAQ, Commissioning, Detector Operations) § Marcelo Vicente (U. Wisconsin) – Firmware Engineer § 3 years on Phase 1 Calorimeter Trigger Upgrade Firmware + HCAL Firmware § 2 Years on ECAL Phase 1 Upgrade Trigger Primitive Generation Electronics (oSLB, oRM) § Jes Tikalski (U. Wisconsin) – Software Engineer § 3 years on Phase 1 Calorimeter Trigger Upgrade Software and embedded systems § Alex Madorsky (U. Florida) – Electrical Engineer § Over a decade of engineering on CMS Trigger, EMU, Track-Finder (since 1999) § Eric Hazen (Boston U.) – Electrical Engineer § Long history of engineering on CMS hadron calorimeter electronics and trigger § Shouxiang Wu (Boston U.) – Electrical Engineer § Long history of engineering on CMS hadron calorimeter electronics and trigger

5

CMS Correlator Engineering Experience

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 3

slide-6
SLIDE 6

WBS Definition

6

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

slide-7
SLIDE 7

7

Level-1 Trigger Architecture

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

Sorting/Merging Layer Muon Track-Finder MPC CSC DT LB RPC Global Correlations (Matching, PT, Isolation, vertexing, etc.) Splitters fan-out fan-out ECAL EB HCAL HB HCAL HF

single xtal

Regional Calo Trigger Layer Global Calo Trigger Layer

Calorimeter Trigger Muon Trigger

Tracker Track-Finding

Track Trigger

GEM + iRPC Global Trigger Tracker Stubs HGCAL

  • n-det

HGCAL

  • ff-det

U.S. Covers fraction DR Question 1

slide-8
SLIDE 8

§ Without L1 Tracks

§ mis-assignment of high pT to low pT muons § rate flattens above O(30) GeV

§ Match L1 Tracks & Muons

§ better resolution

  • sharper turn-on

§ large rate reduction

  • factor O(5-10) at 20 GeV

8

Example: Correlating L1 Tracks & Muons

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

From CMS Technical Proposal: CERN-LHCC-2015-10 DR Question 1

slide-9
SLIDE 9

§ Electrons

§ Match L1 tracks to EM-clusters

  • reduces rate by factor O(8-10) at 20 GeV

§ Challenge: tracker material

  • Retain high efficiency for finding L1 track

§ Possible solution:

  • Different selections high vs low pT electrons

§ Efficiency ~95% in barrel

9

Example: Correlating L1 Tracks & EM-clusters

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

From CMS Technical Proposal: CERN-LHCC-2015-10 DR Question 1

slide-10
SLIDE 10

§ Photons

§ Isolate EM-clusters from L1 tracks

  • reduces diphoton rate by factor O(5)

for 20 GeV leading photon

§ Challenge: tracker material

  • Photon conversions

§ Possible solution:

  • Apply annulus track isolation cone

§ Example:

§ track iso of EM-cluster above 20 GeV

§ H to γγ signal eff: ~90%; Bkg eff: ~30%

10

Example: Correlating L1 Tracks & EM-clusters

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

From CMS Technical Proposal: CERN-LHCC-2015-10 DR Question 1

slide-11
SLIDE 11

§ Taus

§ Try two (early) approaches

  • start w/ calo cluster (TkCaloTaus)

– match to tracks – apply track-based isolation

  • start w/ tracks (TkEmTaus)

– match to EM-cluster

§ Either algorithm able to

§ maintain ~50 kHz rate with ~50% eff. for H to ττ signal § Rate reduced by factor O(5-6)

11

Example: Correlating L1 Tracks & Calo-clusters

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

(GeV)

vis T

E

MC

τ

50 100 150 200

Efficiency

0.2 0.4 0.6 0.8 1 1.2

  • τ

+

τ → VBF H CaloTaus TkCaloTaus (CaloTaus and Tracks) TkEmTaus (EM and Tracks)

CMS PhaseII Simulation PU=140, 14 TeV

From CMS Technical Proposal: CERN-LHCC-2015-10 DR Question 1

slide-12
SLIDE 12

[GeV/c]

T

jet p 50 100 150 200 250 300 Efficiency 0.75 0.8 0.85 0.9 0.95 1

CMS Phase-2 Simulation Efficiency for |z(jet) - z(true)| < 1cm All-hadronic ttbar, <PU>=140 > 20 GeV

T

| < 2.0, p η Jet |

§ Find Primary Vertex

§ Fast: histogram z position of track, weighted by track pT

  • Millimeter-level precision

§ Match tracks to PV

§ Match tracks to calo-only jets

§ Calculate vertex of each jet § Require jets have similar vertex (e.g. within 1 cm) § Efficiency nearly 95% for jets with pT above 50 GeV

12

Example: Event Vertexing

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

From CMS Technical Proposal: CERN-LHCC-2015-10 DR Question 1

slide-13
SLIDE 13

§ Determine MHT from

§ calo-jets matched to common vertex § tracks-only matched to primary vertex

§ Example: Signal <MET> ≈ 200 GeV:

§ track-only MET

  • Rate comes in well below 750kHz menu limit
  • Efficiency 80%-85% with few 10s kHz rate

§ calo-only MET or MHT

  • Completely out of reach

13

Example: Event Vertexing

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

From CMS Technical Proposal: CERN-LHCC-2015-10 DR Question 1

slide-14
SLIDE 14

e's μ's τ's γ's jets Σ's development e's μ's τ's γ's jets Σ's development e's μ's τ's γ's jets Σ's development e's μ's τ's γ's jets Σ's development

14

Model for L1 Correlator Trigger Hardware

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

Global Processing Regional Processing Crate A (“barrel-”) Crate B (“barrel+”)

… … … …

Crate D (“endcap+”) L1 Calo L1 Muons L1 Tracks L1 Calo L1 Muons L1 Tracks L1 Calo L1 Muons L1 Tracks

Based on successful Phase 1 Architecture for CMS Calorimeter Trigger

Global Trigger

Base processors on existing CMS Virtex7 trigger processor boards

Calculate global sums (MET, SET, etc), sort

  • bjects, remove duplicates/ghosts, etc

Inspired by particle flow (PF already used at HLT in Run-I)

L1 Objects DR Question 1

slide-15
SLIDE 15

15

Correlator Trigger Workflow

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

preprocess+distribute L1 calo, L1 muons, L1 tracks

Match L1 tracks to L1 Calo-clusters Match L1 tracks to L1 muons Use L1 tracks to find primary vertex

Calculate L1 track corrected

  • bjects and characteristics

Match L1 tracks to primary vertex Calculate L1 track isolation of objects

0.5 μs 1.0 μs 1.5 μs 2.0 μs 2.5 μs DR Question 1

slide-16
SLIDE 16

§ WBS includes all Engineering and Technical activities as well as M&S to produce the Correlator L1 Trigger electronics. § The system takes as its input data on optical fibers from the CMS Track, Calorimeter, and Muon Triggers and provides processed trigger data for the CMS Global Trigger. § WBS includes managing production of the boards, engineering in support of the production of the boards, procurement of the optical components, FPGAs and all other components on the Correlator L1 Trigger electronics. § WBS also includes fabrication of the PCBs and assembly of the finished Correlator L1 Trigger electronics. § Costs associated with production of boards are assumed to be consistent with the costs experienced with the Phase 1 Trigger Upgrade with appropriate economies of scale applied when quotes justify them.

§ Less expensive optical parts and FPGAs lack bandwidth to process trigger data in planned number of cards and crates, resulting in a multiplication of the system in size by factors of 2-4, which costs significantly more in both M&S and labor.

§ Technology extrapolations may potentially reduce costs but not included.

16

WBS Overview

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-17
SLIDE 17

§ 402.06.05.01 Correlator Trigger Management

§ 402.06.05.01.01 Correlator Trigger Milestones, Interfaces § 402.06.05.01.02 Correlator Trigger Travel

§ 402.06.05.02 Regional Correlator Trigger

§ 402.06.05.02.01 Regional Correlator Trigger M&S (Detail Next Slide) § 402.06.05.02.02 Regional Correlator Trigger Engineering § 402.06.05.02.03 Regional Correlator Trigger Technical Work § 402.06.05.02.04 Regional Correlator Trigger FW § 402.06.05.02.05 Regional Correlator Trigger SW

§ 402.06.05.03 Global Correlator Trigger

§ 402.06.05.03.01 Global Correlator Trigger M&S (Detail Next Slide) § 402.06.05.03.02 Global Correlator Trigger Engineering § 402.06.05.03.03 Global Correlator Trigger Technical Work § 402.06.05.03.04 Global Correlator Trigger FW § 402.06.05.03.05 Global Correlator Trigger SW

§ 402.06.05.04 Correlator Trigger Infrastructure

§ 402.06.05.04.01 Crates and Power Supplies M&S § 402.06.05.04.02 Cables, Fibers and Patch Panel M&S § 402.06.05.04.03 Test Facilities M&S § 402.06.05.04.04 Infrastructure Engineering § 402.06.05.04.05 Infrastructure Technical Work

17

402.06.05 WBS: Correlator Trigger

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-18
SLIDE 18

§ 402.06.05.0X (X=2,3) (Regional, Global) Correlator Trigger M&S

§ 402.06.05.0X.01 Corr. Trig. Preproduction Optics § 402.06.05.0X.02 Corr. Trig. Preproduction FPGAs § 402.06.05.0X.03 Corr. Trig. Preproduction Misc. Comp. § 402.06.05.0X.04 Corr. Trig. Preproduction PCB Fabrication § 402.06.05.0X.05 Corr. Trig. Preproduction Assembly § 402.06.05.0X.06 Corr. Trig. Optics § 402.06.05.0X.07 Corr. Trig. FPGAs § 402.06.05.0X.08 Corr. Trig. Misc. Comp. § 402.06.05.0X.09 Corr. Trig. PCB Fabrication § 402.06.05.0X.10 Corr. Trig. Assembly

18

Correlator Trigger M&S Detail

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-19
SLIDE 19

§ M&S costs are based on escalated prices of similar components used for the Phase 1 upgrade of the L1 trigger. § Labor costs are estimated from engineers currently

  • n staff, or on standard rates as needed. Effort

calculated as per the Phase 1 Trigger Upgrade Project. § International travel is estimated at $3K per trip, and domestic travel is estimated at $1K per trip.

19

Basis of Estimate Overview

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-20
SLIDE 20

§ Assume ~350 tracks sent from track trigger at 100 bits per track

§ 35 kb per BX

§ Assume similar amount of information from calorimeter and muon triggers

§ 35 kb + 35 kb = 70kb per BX

§ Total input to Correlator is 105 kb per BX

§ Total Bandwidth at 40 MHz: 4.2 Tbs

§ Assume present day boards with 80x10 Gbps links running 192 bits at 40 MHz with 80% packing efficiency

§ CTP7 ($15.4k) can handle 492 Gbs

§ Number of boards per task (physics object reco/ID)

§ Regional: total number of boards per task: 4.2 Tbs / 0.492 Tbs ≈ 9 § Global: total number of boards per task: 3 (one third of regional-layer)

§ Number of boards:

§ 7 tasks = 6 physics objects {e, γ, μ, τ, jets, sums} + 1 dev (test new algos in situ) § (7x9=63 system, 2 test stand, 10 spare) 75 regional boards at $15.4k each, § (7x3=21 system, 1 test stand, 3 spare) 25 global boards at $15.4k each.

§ Infrastructure

§ Power Supplies, Fibers, Patch Panels summed to $17k/crate of 12 cards

§ Total Cost: $1.8M (US pays for $1M)

20

Cost Estimate (from CMS HL-LHC TP)

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-21
SLIDE 21

§ R&D M&S

§ 2 prototype cards at $20k apiece in FY17,18,19 each § $13K ($15K) in FY17 (18,19) for crates and other testing infrastructure.

§ Production M&S costs

§ (63 system, 2 test stand, 10 spare) 75 regional boards at $15.4k each, § (21 system, 1 test stand, 3 spare) 25 global boards at $15.4k each. § Design one board for both, different FW

§ Production Board M&S breakdown

§ Based on costs of the Phase 1 cards § FPGA costs (Virtex plus ZYNQ) of $6.6k. § Optical Components $3.6K, § Miscellaneous Components $1.4k, § Printed Circuit Board $2k § Assembly $1.8k.

§ Production Infrastructure M&S Breakdown

§ Based on costs of the Phase 1 Infrastructure § Power Supplies, Fibers, Patch Panels summed to $17k/crate of 12 cards

21

M&S for Production and R&D

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

NB: Assumed Phase 1 μTCA Form Factor smaller than other FF’s considered (e.g. ATCA) means costs are higher since overall card infrastructure is amortized

  • ver fewer channels ⇒ most

conservative cost model DR Question 2

slide-22
SLIDE 22

§ Electronics Engineering and Technical work to design, produce, and test the Correlator Trigger electronics § Software Engineering to produce the software to program, test, operate, diagnose, configure, validate and read out the Correlator L1 Trigger upgrade electronics.

§ This includes software to interface with the Trigger Online System

§ Firmware Engineering to implement the full functionality

  • f the Correlator L1 Trigger upgrade electronics

§ Including implementing the trigger algorithms, diagnostics, data acquisition and readout.

§ SW and FW produced in releases for testing boards, commissioning boards and operating them under initial, low, medium and high luminosity HL-LHC conditions. § All labor costs based on actual costs for corresponding tasks for the Phase 1 Trigger Upgrade

22

Correlator Trigger Labor

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-23
SLIDE 23

§ The Correlator Trigger labor for the R&D period FY17-19 includes:

§ 3514 FTE hours/year divided equally between University-based Electronic, Firmware and Software Engineers § 502 FTE hours/year of Fermilab-based Electronic Engineering for FY18,19.

§ The Correlator Trigger labor for the production phase FY20-23 includes:

§ 3012 FTE hours/year divided equally between University-based Electronic, Firmware and Software Engineers § 251 FTE hours/year of Fermilab-based Electronic Engineering.

23

Correlator Trigger Labor FTE

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-24
SLIDE 24

24

Construction Schedule

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

FY25 FY24 FY23 FY22 FY21 FY20 FY19 FY18 FY17

CD4 CD1 CD2CD3 CD0

Specification and Technology R&D Trigger TDR

Pre- production

Installation

LS 2 LS 3 Physics Physics

LHC Schedule

CDR PDR CD3A FDR

Prototyping and Demonstrators Production Readiness Review Production and Test Test & Commission

Reality Check:

  • Ph. 1 Cal. Trig. Board: CTP7

1st Proto: Q4/CY13 6 Pre. Prod. Proto: Q2-3/CY14 1st Production Board: Q1/CY15 50 Board Production Complete Q2CY15 Installation Complete: Q2/CY15 Commissioned, Operations start: Q3/CY15 ⇒ 21 Months: 1st prototype to pp operations

slide-25
SLIDE 25

25

Cost: through FY 23

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

Cost = AY $k (No Contingency)

L3 Area M&S* Labor Total R&D Global Correlator 1221k 1044k 2265k 1417k

*Includes travel NB: escalation at 3%/year starting in FY17 DR Question 2

slide-26
SLIDE 26

26

Cost Profile

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

100 200 300 400 500 600 700 800 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25

AY k$

R&D Construction

DR Question 2

slide-27
SLIDE 27

27

Labor FTE Profile

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

0.2 0.4 0.6 0.8 1 1.2

FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25

FNAL Engineer FNAL Tech University Engineer University Tech

DR Question 2

slide-28
SLIDE 28

§ M&S: 50%

§ Based on conceptual design documented in CMS HL-LHC Technical Proposal § Items based on existing Phase 1 Trigger upgrade with documented costs

§ Travel: 20%

§ Based on LOE required as determined from Phase 1 Trigger Upgrade

§ Labor: 50%

§ Based on expert judgment using documented experience of similar work required for the Phase 1 Trigger Upgrade § Development of activities defined at a conceptual level informed by the experience of the Phase 1 Trigger Upgrade § Technical requirements are moderately challenging, but straightforward extrapolation from the Phase 1 Trigger Upgrade

§ Note: Phase 1 Upgrade production/installation finished in

  • 2015. Commissioning still underway.

§ Using recent data for labor, M&S in the cost, contingency, risk estimates

28

Contingency Calculation

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-29
SLIDE 29

§ C&S understood since based on Phase 1 Trigger Upgrade Systems experience § Boards are extrapolations of existing Phase 1 Trigger Upgrade Boards

§ Using most conservative costing model (construct with Phase 1 hardware) § R&D and technology advances offer opportunities to reduce cost.

§ C&S based on experience of the same team that built and wrote software and firmware for Phase 1 Trigger Upgrade

§ Exploiting new commercial tools offer opportunities to reduce amount of custom written FW and SW § Opportunities already realized in Phase 1 Cal. Trig. Upgrade

29

Cost and Schedule Risks

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-30
SLIDE 30

§ Senior Engineer becomes unavailable (Low Risk)

§ Hire new engineer, subcontract to consulting firm, use FNAL engineer

§ Software or Firmware does not meet requirements (Low Risk)

§ Hire extra expert effort to recover schedule and help personnel

§ Boards are delayed (design, manufacture or testing) (Low Risk)

§ Hire extra effort to speed up testing schedule

§ Vendor non-performance (Low Risk)

§ Acquire spending authority to use alternative vendors (while original funds are being unencumbered).

§ Input or output electronics (non-trigger) delayed (Low Risk)

§ Built in capabilities of trigger electronics provide signals for their own inputs &

  • utputs

30

Managed Trigger Risks & Mitigation

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 2

slide-31
SLIDE 31

§ None § Since global correlator trigger has full self-test capabilities, satisfying performance requirements validated w/o requiring connected inputs or outputs. § Trigger electronics can store up sequences of test patterns and inject them into the front end of the trigger electronics at speed § These patterns are based on actual LHC pp data taken before LS3 § Trigger electronics can receive output, process and record this at speed for subsequent readout by DAQ.

31

External Dependencies

02-Feb-2016 R. Cavanaugh B01-4: HL-LHC Global Correlator

slide-32
SLIDE 32

§ Safety: follows procedures in CMS-doc-11587, FESHM

§ L3 Manager (R.C.) responsible for applying ISM to trigger upgrade.

  • Under direction of US CMS Project Management.

§ Modules similar to others built before, of small size and no high voltage

§ Quality Assurance: follows procedures in CMS-doc-11584

§ Regularly evaluate achievement relative to performance requirements and appropriately validate or update performance requirements and expectations to ensure quality. § QA: Equipment inspections and verifications; Software code inspections, verifications, and validations; Design reviews; Baseline change reviews; Work planning; and Self-assessments. § All modules have hardware identifiers which are tracked in a database logging QA data through all phases of construction, installation, operation and repair.

§ Graded Approach:

§ Apply appropriate level of analysis, controls, and documentation commensurate with the potential to have an environmental, safety, health, radiological, or quality impact. § Four ESH&Q Risk levels are defined and documented in CMS-doc-11584.

32

Trigger ESH&Q

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 4

slide-33
SLIDE 33

§ After full testing at institute, shipped to CERN

§ All tests recorded (of all types) for individual boards in database § Tests use and validate software and firmware test release

§ Acceptance Testing in Electronics Integration Center (EIC) at CERN

§ Individual labs for Muon, Calorimeter, (and now) Correlator Triggers § Boards retested to validate institute test results § Tests use software and firmware test release

§ Integration Testing in EIC

§ Row of racks with DAQ, Trigger, Central Clock, Crates of other subsystem electronics § Operation of a vertical slice with electronics to be tested installed. § Tests use and validate software and firmware commissioning release

§ Integration Testing at P5: Global Runs

§ Test with all CMS with cosmics when beam not running/with beam when running § Electronics installed in final locations with final cables § Full-scale tests with full CMS DAQ/Trigger/Clocking § Tests use software and firmware commissioning release

§ Handover to Operations at P5: Global Runs/Parallel Operation

§ After testing completes, continue with Global Runs/Parallel Operation § Validate software and firmware initial operational release

33

QA/QC: Testing and Validation

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 3

slide-34
SLIDE 34

§ Goal:

§ Allow development of correlation trigger electronics – specify:

  • Planned Algorithms
  • Necessary trigger primitives
  • Link counts and formats

§ Plan (with CMS HL-LHC Technical Proposal Milestones):

§ Initial definition of trigger algorithms, primitive objects and inter-layer

  • bjects (TP

.L1.1) – 2QCY16 § Baseline definition of trigger algorithms, primitive objects and interchange requirements with subdetectors. (TP .L1.3) – 2QCY17 § Detailed software emulator demonstrates implementation of core HL- LHC trigger menu with baseline objects (TP .L1.4) – 4QCY17

  • Used to inform the final implementation of the trigger hardware.

34

Correlator Trigger Algorithm R&D

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 1

slide-35
SLIDE 35

§ Closely related to hardware R&D conducted for Calorimeter Trigger (WBS 402.06.03)

§ Similar HW R&D and Milestones

§ Hardware R&D Milestones - I

§ Initial demonstration of key implementation technologies (TP .L1.2) – 4QCY16

  • e.g. > 25 Gb data links, general applicability across HL-LHC
  • Start construction of initial prototype circuits for demonstration of

feasibility of trigger design, leads to:

§ Definition of hardware technology implementation baseline (TP .L1.5) – 1QCY18

  • Testing and revisions of prototypes.
  • Used with algorithm and emulation baseline to define what is

needed for →

35

HL-LHC Correlator HW R&D

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 1

slide-36
SLIDE 36

§ Hardware R&D Milestones – II

§ Full-function correlator prototypes produced which allow local comparison with emulator (TP.L1.6) – 4QCY18

  • First boards which have sufficient channels, processing capability and

bandwidth optical links to meet the requirements of the final boards

  • These boards will cover only a portion of the correlator processing logic,

however, and only local comparisons will be possible between hardware behavior and the emulator.

§ Demonstrator trigger system shows correlator integration and scaling, global/full-chain comparison with emulator (TP.L1.7) – 4QCY19

  • End-to-end comparisons over a slice of the detector which include

multiple full-capability prototype boards and the prototype full-capability infrastructure

  • Goal of demonstrating a prototype trigger system with its infrastructure

and testing environment capable of being connected to its front end detector for test-beam validation to follow.

§ Final Milestone:

§ HL-LHC Trigger TDR (TP.L1.8) – 1Q2020

  • Based on results from Trigger Demonstrators.

36

HL-LHC Correlator HW R&D

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 1

slide-37
SLIDE 37

§ Phase 1 upgrade: two generations (V5, V6) before production boards—similar path reasonable for HL-LHC § Today: CTP7 (V7) a very capable “Gen 0” demonstrator for HL-LHC

§ Supporting HL-LHC Tracking Trigger and Calorimeter Trigger R&D § Comparatively “young” platform (< 2 years old) w/ new technology

§ Develop Correlator Trigger “Gen 0” test stand

§ Two CTP7 boards for regional correlation layer § One CTP7 board for global correlation layer § One crate plus fibers and patch panels

§ Evolve test stand with next generation prototype boards § Locate test stand at UW or FNAL – Make available as common facility for US-CMS

§ Establish baseline trigger algorithms between hardware and emulator § Explore algorithms beyond baseline (inspired by particle flow)

37

HL-LHC Correlator Demonstrator

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

DR Question 1

slide-38
SLIDE 38

Summary

38

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger

slide-39
SLIDE 39

§ R&D Program will result in designs for the HL-LHC Correlator Trigger that will meet technical performance requirements § Scope and Specifications of this Trigger are sufficiently well-defined to support the C&S estimates § Based upon common hardware platforms and components § ES&H, QA plans, C&S based on experience with original trigger construction and Phase-1 upgrade § Management and Engineering teams are experienced with sufficient design skills, having designed and built

  • riginal CMS trigger and Phase-1 Upgrade

39

Conclusions: HL-LHC

02-Feb-2016 R. Cavanaugh HL-LHC Correlator Trigger