availability of an adequate supply of electricity at a
play

Availability of an adequate supply of electricity at a - PowerPoint PPT Presentation

Criteria for a Successful Shore Power Project Criteria for a Successful Shore Power Project Availability of an adequate supply of electricity at a Availability of an adequate supply of electricity at a reasonable cost. reasonable


  1. Criteria for a Successful Shore Power Project Criteria for a Successful Shore Power Project • • Availability of an adequate supply of electricity at a Availability of an adequate supply of electricity at a reasonable cost. reasonable cost. • • Frequency of calls by cruise vessels equipped to Frequency of calls by cruise vessels equipped to connect to Shore Power. connect to Shore Power. • • Availability of the same dock and pier facility for these Availability of the same dock and pier facility for these vessels for every call. vessels for every call. • • Adequate dock and uplands space for equipment. Adequate dock and uplands space for equipment. • • Willing partners including – – utility, port and government utility, port and government Willing partners including agencies. agencies.

  2. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shoreside Installation Shoreside Installation Shore Power Description Shore Power Description Power is transmitted from an onshore substation equipped with a dual voltage dual voltage Power is transmitted from an onshore substation equipped with a transformer that will supply power to 11kV or 6.6kV class ships. transformer that will supply power to 11kV or 6.6kV class ships. Internal shore side monitoring and protection is achieved with protection relays rotection relays Internal shore side monitoring and protection is achieved with p to insure safety and protection of both ship and shore electrical systems. to insure safety and protection of both ship and shore electrica l systems. Flexibility to connect either 11kV or 6.6kV ships is achieved by two independent two independent Flexibility to connect either 11kV or 6.6kV ships is achieved by secondary breakers with Kirk secondary breakers with Kirk- -Key interlocks. Key interlocks. Power is carried to the ship through five flexible "Ship Cables" routed through a routed through a Power is carried to the ship through five flexible "Ship Cables" grounding switch. grounding switch. This grounding switch works in conjunction with the ships automation system to tion system to This grounding switch works in conjunction with the ships automa ensures safety and reliability during the cable handling from sh ensures safety and reliability during the cable handling from shore to ship. ore to ship.

  3. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Juneau, Alaska Juneau, Alaska First High Voltage Shore Power Connection First High Voltage Shore Power Connection for Cruise Ships for Cruise Ships

  4. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Juneau, Alaska Juneau, Alaska Power Cables Power Cables AmeriCable 350 KCMIL 15kV SHD- -GC CPE GC CPE AmeriCable 350 KCMIL 15kV SHD 15kV 350 15kV 350 MCM Cu MCM Cu EPR EPR Conductor Conductor Insulation Insulation Grounding Grounding Conductor Conductor CPE CPE Jacket Jacket

  5. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Juneau, Alaska Juneau, Alaska Substation 6.6 & 11 KV Breakers Substation 6.6 & 11 KV Breakers

  6. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Juneau, Alaska Juneau, Alaska

  7. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Juneau, Alaska Juneau, Alaska Design & Construction Timing Design & Construction Timing • Notice to Proceed Given by Princess • Notice to Proceed Given by Princess December 1, 2000 December 1, 2000 • On Line Early June 2001 • On Line Early June 2001

  8. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Juneau, Alaska Juneau, Alaska Electrical Energy Sales In Juneau, Alaska Electrical Energy Sales In Juneau, Alaska • Ship Hotel Electrical Loads 7 to 11 MW @ 6.6 • Ship Hotel Electrical Loads 7 to 11 MW @ 6.6 KV or 11 KV and .83 to .86 PF KV or 11 KV and .83 to .86 PF • Total Annual Shore Power Consumption is 11 - - • Total Annual Shore Power Consumption is 11 12 GWH Annually 12 GWH Annually

  9. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Seattle, Washington Seattle, Washington

  10. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Seattle, Washington Seattle, Washington Electrical Energy Sales In Seattle, Washington Electrical Energy Sales In Seattle, Washington Transformer Capacity: Transformer Capacity: • 16.25 Megawatts. • 16.25 Megawatts. • Total annual consumption 3.5 – – 4 GWH. 4 GWH. • Total annual consumption 3.5 Dual Service Delivery (Secondary) Voltage: Dual Service Delivery (Secondary) Voltage: • • 6.6kv and 11kv depending on class of ship. 6.6kv and 11kv depending on class of ship. • Both voltages are not used at the same time. • Both voltages are not used at the same time. In Seattle the Primary Voltage is 27kv. In Seattle the Primary Voltage is 27kv.

  11. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shoreside Installation Shoreside Installation System Components System Components • Transformer • Transformer • Main Metering Equipment • Main Metering Equipment • Secondary Metering Equipment • Secondary Metering Equipment • Grounding Switch • Grounding Switch • Shore Power Cable Winch • Shore Power Cable Winch • Power Cables • Power Cables

  12. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Seattle, Washington Seattle, Washington T- -30 30 T Transformer, Main & Secondary Metering Equipment Transformer, Main & Secondary Metering Equipment

  13. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shoreside Installation Shoreside Installation Power Cable Winch Power Cable Winch

  14. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shoreside Installation Shoreside Installation Installation Installation • Excavation • Excavation • Conduit Installation • Conduit Installation • Transformer Pad Installation • Transformer Pad Installation • Equipment Installation • Equipment Installation Transformer; Transformer; Main Metering Equipment; Main Metering Equipment; Secondary Metering Equipment; Secondary Metering Equipment; Grounding Switch; & Cable Winch Grounding Switch; & Cable Winch • Cable Installation • Cable Installation

  15. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shoreside Installation Shoreside Installation Equipment Equipment

  16. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shoreside Installation Shoreside Installation Commissioning & Testing Process Commissioning & Testing Process • Ship is docked • Ship is docked • Winch lowers cables into hull & cables are • Winch lowers cables into hull & cables are attached attached • Testing is completed to ensure entire • Testing is completed to ensure entire system is functional system is functional • • Commissioning is completed Commissioning is completed

  17. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shipboard Installation Shipboard Installation Shipboard Control Panel Shipboard Control Panel

  18. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shipboard Installation Shipboard Installation Shipboard Cables Connections Shipboard Cables Connections • 4 Power Connectors • 4 Power Connectors (Callenberg) (Callenberg) • 1 Neutral Connection • 1 Neutral Connection (Callenberg) (Callenberg) • 2 Control • 2 Control (Cannon Plug) (Cannon Plug) • 1 SCADA • 1 SCADA (Cannon Plug) (Cannon Plug) • Standardization of Cable • Standardization of Cable Connections Connections

  19. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shipboard Installation Shipboard Installation

  20. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Shipboard Installation Shipboard Installation CABLES FROM CABLES FROM SHORE SIDE SHORE SIDE

  21. Cruise Ship Shore Power Project Cruise Ship Shore Power Project Seattle, Washington Seattle, Washington Festooning System Festooning System

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend