April 2012
& Audit Review April 2012 Keno Hill Project Overview Water - - PowerPoint PPT Presentation
& Audit Review April 2012 Keno Hill Project Overview Water - - PowerPoint PPT Presentation
Demand Side Management & Audit Review April 2012 Keno Hill Project Overview Water Treatment & Environmental Exploration Monitoring Reclamation & & District Remediation Development KENO HILL SILVER DISTRCIT
Keno Hill Project Overview KENO HILL SILVER DISTRCIT
Water Treatment & Environmental Monitoring Reclamation & Remediation Environmental Consulting & Closure Planning Underground Mining Keno Hill District Mill Exploration & District Development
- Identified areas which allow Alexco to:
Reduce peak usage Reduce total energy usage Identify possible efficiencies Further reduce energy footprint
KEY Reasons for Involvement
2011 Demand Side Management Energy Audit
- Mutually beneficial partnership between YEC & Alexco
Demand Side Energy Consultants
Study Scope
1. Observation of Keno Hill Project
- perational
procedures 2. Comparison of
- ther projects to
Keno Hill Project 3. Analysis of utilization rates &
- perational
parameters 4. Final report & recommendations to Alexco & YEC 1 week at site Off-site consulting work Database comparison for efficiency gains Large equipment such as: air compressors, crushers, blower, ball mill … Operational recommendations & capital projects
Typical Energy Profile
0.00 200.00 400.00 600.00 800.00 1,000.00 1,200.00 1,400.00 1,600.00 3/18/2012 14:45 3/19/2012 3:45 3/19/2012 16:45 3/20/2012 5:45 3/20/2012 18:45 3/21/2012 7:45 3/21/2012 20:45 3/22/2012 9:45 3/22/2012 22:45 3/23/2012 11:45 3/24/2012 0:45 3/24/2012 13:45 3/25/2012 2:45 3/25/2012 15:45 3/26/2012 4:45 3/26/2012 17:45 3/27/2012 6:45 3/27/2012 19:45
- Base Load = Daily Steady State
Operations
- All infrastructure must be sized
to peak load
- Peaks are associated with ore
crushing operations
Recommendations of Demand Side Audit
- 1. Instillation of an ammeter in Mill
- perators cab
- 2. Convert plant lighting to T5 HO
fluorescents & LED’s for outdoors
- 3. Re-commission mill air system
- 4. Initiate compressed air leak
reduction program
- 5. Commission the air blower inlet
modulation
- 6. Re-apply variable frequency drives to
Mine ventilation
- 7. Optimize plant process thru program
logic controller
- 8. Install electrical sub-metering for
Mine
- 9. kWh per tonne as performance
measure 10.Install capacitors on the 600V Mill
Status of Recommendations
Investigation of alternate lighting options (LED’s) - in progress Mill compressed air system has been re-commissioned Ongoing air leak reduction program at Mill & Mine Additional variable frequency drives have been installed Program logic control on filter presses implemented Evaluation of site power distribution & metering options - in progress Cost benefit analysis & design of power factor correction unit for the Mill – in progress
Power Factor (PF)
- Power Factor is a measure of how
effectively the power is being used and is a ratio of “active power” used to the “apparent power” required which is a combination of both active power & reactive power
- 0.85 for normal operations
- 0.75 for peak loading conditions
- For every unit of power
required to run upwards of 15-20% more power needs to be provided
- 0.95 – 0.98 PF with correction
- PF = Active Power / Apparent Power
Future Considerations
- Increased use of variable frequency drives on motors
- Power factor correction studies
- Energy measuring devices
- Alternative lighting sources
- Proper equipment sizing & selection
- Ongoing evaluation of operational practices
Alexco Contact Info Peter Johnson – Construction Manager
Vancouver Head Office 1150 – 200 Granville St. Vancouver, BC V6C 1S4 T: 604-633-4888 F: 604-633-4887 Whitehorse Office #3 Calcite Business Centre 151 Industrial Road Whitehorse, Yukon Y1A 2V3 T: 867-633-4881 F: 867-633-4882 Keno Hill Silver District Elsa, Yukon Y0B 1G0 T: 867-996-2330 F: 867-995-2600