ATHENA SA has been involved in the Design, procurement, installation - - PDF document

athena sa has been involved in the design procurement
SMART_READER_LITE
LIVE PREVIEW

ATHENA SA has been involved in the Design, procurement, installation - - PDF document

ATHENA SA has been involved in the Design, procurement, installation and construction of steam, diesel, hydro and fossil fueled power production plants. The involvement includes all related power plant systems , such as electro


slide-1
SLIDE 1

ATHENA SA has been involved in the Design, procurement, installation and construction of steam, diesel, hydro and fossil fueled power production plants. The involvement includes all related power‐plant systems, such as electro‐mechanical fire‐protection and heating & ventilating systems, cooling towers, electrostatic and heating & ventilating systems, cooling towers, electrostatic precipitators, fuel & ash handling systems, chimneys and all required auxiliary systems, main & auxiliary buildings, workshops and road networks

1

slide-2
SLIDE 2

S.E.S. Ptolemais Unit IV ans S.E.S kardia I,II x 300 MW

Power & Energy

Public Power Corporation 1992‐1993 Contract value: 23.053.008 € Greece Complete design and construction of all the

MW

necessary works to replace the Fly Ash Handling System and the auxiliary systems in two lignite power plants. Public Power Corporation (PPC) 1985‐1992 Contract value: 1.776.262 €

S.E.S. Megalopolis ‐ Unit IV (300 MW) Cooling Tower, Chimney, Machine House, E/M erection and Auxiliary Industrial Buildings

Greece – Megalopolis In a consortium the firm implemented the complete erection of this 300 MW unit , along with all the required equipment and systems. Public Water Corporation 1982‐1984

S.E.S. Agios Dimitrios ‐ Units III & IV , 2 x 300 MW

Contract value: 12.522.488 € Kozani, Greece Design & Construction of two natural draft cooling towers of 103 m height, and 71 m base diameter. Design & construction of 200 m high chimney,

  • f reinforced concrete shell with diameter of

27 m at bottom and 13 m at top and internal brick wall stack with 8.5 m diameter

2

slide-3
SLIDE 3

Messochora Hydroelectric Power Station 950 MW

Power & Energy

Public Power Corporation 1993‐2001 Contract value: 40.784.583 € Messochora, Greece Execution of the complete civil works for the i f di h d l h construction of a discharge dam to control the water flow

  • f

Acheloos river, and the construction of substation, landscaping and road networks. Roads included the penstock , 300 m long tunnel, lined with steel plates, the underground vertical shaft 12 m diameter and 70 m height , the drainage and access

  • tunnels. (JV)

National Water Company 1998 – 2003 Contract value: 15.113.705 €

Psyttalia Electric – Thermal Cogeneration

Psyttalia Island, Greece Construction

  • f

cogeneration facilities

  • f

electric and thermal power production from energy sources resulting from combustion of the exhaust biogas from the domestic sewage

  • f the Psyttalia Sewage Treatment Plant

Public Water Corporation

S.E.S Megalopolis Unit III Ash Precipitators

Public Water Corporation 1999 – 2001 Contract value: 24.965.896 € Greece In a consortium, the firm implemented the complete design, supply, installation and commissioning of New Fly Ash Electrostatic commissioning of New Fly Ash Electrostatic Precipitators ( ESPs) including all relevant electromechanical and civil works in revamping the existing ESPs

3

slide-4
SLIDE 4

Power & Energy

Public Power Corporation PPC 1983 ‐ 1985 Contract value: 4.495.921 € Amynteo, Greece

S.E.S Amynteon Units I, II 2 x 300 MW

Design and construction of 200 m high chimney of reinforced concrete shell with 25 m diameter at bottom and 13 m at top and internal brick wall stack with 9 m diameter Public Power Corporation 1995‐1997

D.E.S Rhodes Units III , IV, V , 75 MW

Contract value: 13.665.444 € Greece In a consortium, the firm implemented design and construction and the complete E/M installation for this SEMT Pielstick Diesel Engines 3 x 23.4 MW plant, including the machine hall 50mx50mx24m concrete hi f t t k f d chimney

  • f system, tank far, area, road

networks, channells, sea water intake and exhaust gas ducts, design/installatiion of a new 200 m³/h fully automatic industrial WWTP HVAC and fire detection/protection systems.

4