association of cost engineers
play

Association of Cost Engineers NEC: Option C Cost Audits NEC Option - PowerPoint PPT Presentation

Association of Cost Engineers NEC: Option C Cost Audits NEC Option C Cost Audits NEC Audit Provisions NEC Payment Provisions Audit Objectives Audit Plan Audit Considerations Implementation of Audit Plan Rolling


  1. Association of Cost Engineers NEC: Option C Cost Audits

  2. NEC Option C Cost Audits NEC Audit Provisions • NEC Payment Provisions • Audit Objectives • Audit Plan • Audit Considerations • Implementation of Audit Plan • Rolling Programme of Cost Audits • Potential Audit Problems •

  3. Solomons Europe Limited • Solomons Europe is a Chartered Quantity Surveying Practice Established in 1998 • Provide support to UK’s Major EPC and Industrial Services Contractors

  4. Solomons Europe Limited • Specialise in

  5. NEC AUDIT PROVISIONS NEC ECC Option C Target contract with an Activity Schedule

  6. NEC AUDIT PROVISIONS • Contract Clause – No express reference to cost audits in the NEC – 52.3 Contractor allows the PM to inspect accounts and records required to be kept at any time within the working hours

  7. NEC Payment Provisions • (50.1) Project Manager assesses the amount due – Price for Work Done to Date • Defined Cost + Fee

  8. NEC Payment Provisions • Defined Cost = – Option C: • Payments due to Subcontractors… and • The cost of components in the Schedule of Cost Components

  9. NEC Payment Provisions • Payment timescales – 51.1 PM certifies a payment within one week of the assessment date – Hence, high level review of any application with more thorough audit in the following weeks – Any audit findings are then incorporated into next PM assessment of amount due

  10. Audit Objectives • Audits ensure costs paid are • Accurate • Allowable and • Appropriate

  11. Audit Plan • Managing Reality Book Two: Procuring an Engineering and Construction Contract: – Appendix 3: Audit Plan

  12. Audit Plan • The audit process should be detailed in the Works Information

  13. Audit Plan • Audit Task Sections – Monthly Report • People • Equipment • Plant & Materials • Charges • Manufacture & Fabrication • Design

  14. Audit Considerations • Generally – Specific contract provisions – Have payments actually been made? - access to bank statements – Allocation to correct cost codes / WBS

  15. Audit Considerations • Subcontractors – Pre-appointment • Order placed in accordance with any Works Information requirements

  16. Audit Considerations • Subcontractors – Post-appointment • Properly administered – Change control – Assessment of PWDD – Payments made within timescales – Final accounts reflect contract

  17. Audit Considerations • People – Place of work: Working Areas: “used only for this contract” – Time capture procedure – Payslips (weekly & monthly) – Payroll burden: per Schedule of Cost Components

  18. Audit Considerations • Equipment – Rates: reflective of current market rates (whether internal or not) – Idle plant – Purchased Equipment – Maintenance / repair

  19. Audit Considerations • Plant and Materials – Orders – Goods received notes – Invoices – Payments – Check quants required v quants delivered

  20. Audit Considerations • Charges – Costs necessary to carry out the works – Costs included in Working Area overheads / people overheads are not also included elsewhere

  21. Audit Considerations • Manufacture and Fabrication – Outside the Working Areas – Should be agreed and form part of the Contract Data • “wholly or partly designed for the works”

  22. Audit Considerations • Design – Outside the Working Areas – Should be agreed and form part of the Contract Data – Rates x hours + travel to Working Areas

  23. Rolling Programme of Cost Audits • Plan to cover 10% of cumulative costs • Plan to audit each major cost element • Element audit schedule to reflect programme • Frequency of element audits reflect relative values – Some elements may warrant a monthly audit: e.g. prelims, staff costs

  24. Potential Audit Problems • Vagueness of the Schedule of Cost Components • Non-availability of substantiating information may result in reduced payments

  25. Potential Audit Problems • Ability to audit down the supply chain where no direct contractual relationship exists • Reluctance to provide “commercially sensitive” substantiating information / Data protection (!) • Where the supporting information is held

  26. Summary • Vital for Contractors (and subcontractors) to keep full and organised records relating to costs to demonstrate validity and appropriateness • Audits are a pragmatic way of ensuring accurate allowable and appropriate costs are reimbursed

  27. Summary • Successful audits create commercial confidence for both parties throughout the project • Successful audit outcomes assist early settlement of final accounts

  28. Any further questions? Feel free to call or email any of us or contact us online at: www.solomonseurope.co.uk

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend