Association of Cost Engineers NEC: Option C Cost Audits NEC Option - - PowerPoint PPT Presentation

association of cost engineers
SMART_READER_LITE
LIVE PREVIEW

Association of Cost Engineers NEC: Option C Cost Audits NEC Option - - PowerPoint PPT Presentation

Association of Cost Engineers NEC: Option C Cost Audits NEC Option C Cost Audits NEC Audit Provisions NEC Payment Provisions Audit Objectives Audit Plan Audit Considerations Implementation of Audit Plan Rolling


slide-1
SLIDE 1

Association of Cost Engineers

NEC: Option C Cost Audits

slide-2
SLIDE 2

NEC Option C Cost Audits

  • NEC Audit Provisions
  • NEC Payment Provisions
  • Audit Objectives
  • Audit Plan
  • Audit Considerations
  • Implementation of Audit Plan
  • Rolling Programme of Cost Audits
  • Potential Audit Problems
slide-3
SLIDE 3

Solomons Europe Limited

  • Solomons Europe is a Chartered Quantity

Surveying Practice Established in 1998

  • Provide support to UK’s Major EPC and

Industrial Services Contractors

slide-4
SLIDE 4

Solomons Europe Limited

  • Specialise in
slide-5
SLIDE 5

NEC AUDIT PROVISIONS

NEC ECC Option C Target contract with an Activity Schedule

slide-6
SLIDE 6

NEC AUDIT PROVISIONS

  • Contract Clause

– No express reference to cost audits in the NEC – 52.3 Contractor allows the PM to inspect accounts and records required to be kept at any time within the working hours

slide-7
SLIDE 7

NEC Payment Provisions

  • (50.1) Project Manager assesses the amount

due –Price for Work Done to Date

  • Defined Cost + Fee
slide-8
SLIDE 8

NEC Payment Provisions

  • Defined Cost =

– Option C:

  • Payments due to Subcontractors…

and

  • The cost of components in the Schedule of Cost

Components

slide-9
SLIDE 9

NEC Payment Provisions

  • Payment timescales

– 51.1 PM certifies a payment within one week of the assessment date – Hence, high level review of any application with more thorough audit in the following weeks – Any audit findings are then incorporated into next PM assessment of amount due

slide-10
SLIDE 10

Audit Objectives

  • Audits ensure costs paid are
  • Accurate
  • Allowable and
  • Appropriate
slide-11
SLIDE 11

Audit Plan

  • Managing Reality Book Two: Procuring an

Engineering and Construction Contract:

– Appendix 3: Audit Plan

slide-12
SLIDE 12

Audit Plan

  • The audit process should be detailed in the

Works Information

slide-13
SLIDE 13

Audit Plan

  • Audit Task Sections – Monthly Report
  • People
  • Equipment
  • Plant & Materials
  • Charges
  • Manufacture & Fabrication
  • Design
slide-14
SLIDE 14

Audit Considerations

  • Generally

– Specific contract provisions – Have payments actually been made? - access to bank statements – Allocation to correct cost codes / WBS

slide-15
SLIDE 15

Audit Considerations

  • Subcontractors

– Pre-appointment

  • Order placed in accordance with any Works

Information requirements

slide-16
SLIDE 16

Audit Considerations

  • Subcontractors

– Post-appointment

  • Properly administered

– Change control – Assessment of PWDD – Payments made within timescales – Final accounts reflect contract

slide-17
SLIDE 17

Audit Considerations

  • People

– Place of work: Working Areas: “used only for this contract” – Time capture procedure – Payslips (weekly & monthly) – Payroll burden: per Schedule of Cost Components

slide-18
SLIDE 18

Audit Considerations

  • Equipment

– Rates: reflective of current market rates (whether internal or not) – Idle plant – Purchased Equipment – Maintenance / repair

slide-19
SLIDE 19

Audit Considerations

  • Plant and Materials

– Orders – Goods received notes – Invoices – Payments – Check quants required v quants delivered

slide-20
SLIDE 20

Audit Considerations

  • Charges

– Costs necessary to carry out the works – Costs included in Working Area overheads / people overheads are not also included elsewhere

slide-21
SLIDE 21

Audit Considerations

  • Manufacture and Fabrication

– Outside the Working Areas – Should be agreed and form part of the Contract Data

  • “wholly or partly designed for the works”
slide-22
SLIDE 22

Audit Considerations

  • Design

– Outside the Working Areas – Should be agreed and form part of the Contract Data – Rates x hours + travel to Working Areas

slide-23
SLIDE 23

Rolling Programme of Cost Audits

  • Plan to cover 10% of cumulative costs
  • Plan to audit each major cost element
  • Element audit schedule to reflect programme
  • Frequency of element audits reflect relative

values

– Some elements may warrant a monthly audit: e.g. prelims, staff costs

slide-24
SLIDE 24

Potential Audit Problems

  • Vagueness of the Schedule of Cost

Components

  • Non-availability of substantiating information

may result in reduced payments

slide-25
SLIDE 25

Potential Audit Problems

  • Ability to audit down the supply chain where

no direct contractual relationship exists

  • Reluctance to provide “commercially

sensitive” substantiating information / Data protection (!)

  • Where the supporting information is held
slide-26
SLIDE 26

Summary

  • Vital for Contractors (and subcontractors) to

keep full and organised records relating to costs to demonstrate validity and appropriateness

  • Audits are a pragmatic way of ensuring

accurate allowable and appropriate costs are reimbursed

slide-27
SLIDE 27

Summary

  • Successful audits create commercial

confidence for both parties throughout the project

  • Successful audit outcomes assist early

settlement of final accounts

slide-28
SLIDE 28

Any further questions?

Feel free to call or email any of us or contact us online at:

www.solomonseurope.co.uk