Allen Rust, EIT KYTC Division of Right of Way and Utilities Rail Coordination Plans Development Agreement Process Plan Review Process PS&E Procedures Construction and Inspection Fiscal Management Tracking Procedures


  1. Allen Rust, EIT KYTC Division of Right of Way and Utilities

  2. Rail Coordination  Plans Development  Agreement Process  Plan Review Process  PS&E Procedures  Construction and Inspection  Fiscal Management  Tracking Procedures

  3. Plans Development  Determination of need for new/improved highway  Pre ‐ Design Meeting  Prepare project file  Preliminary Line and Grade Inspection  Final Plans in Hand Inspection

  4. Agreement Process  Plans submitted to Railroad  Railroad supplies cost estimates, comments, etc.  Contract Agreement Drafted

  5. Plan Review Process  Review construction plans for Railroad details  Railroad comments and requirements  Railroad detail sheet  Crossing pavement elevation sheet  Any other necessary amendments  Avoid delays in both time and money

  6. PS&E (Plans, Specifications, & Estimates Section)  Division of Construction Procurement  Special Notes for Protection of Railway Interests  Flagging notes  Insurance requirements  Train Info  Project Summary Sheet

  7. Construction and Inspection  District Utilities Supervisor coordinates all work by the Rail Companies  “Notification of Utility Relocation and/or Adjustment “ completed by District  Inspections by District  ALL WORK BY THE RAIL COMPANIES MUST BE DOCUMENTED  Invoices and Billing

  8. Fiscal Management  Final Invoice indicates work is completed  Audits  Not required for each project  Random projects are selected  Can be requested  Requests sent to Branch Manager of the External Audit Staff  Files kept for 20 years

  9. Tracking Procedures  Aware of all Railroad projects in Six ‐ Year Plan  ORACLE  Item Number  Letting Date  “RAILROAD INVOLVEMENT”  Monthly status checks

  10. Rail Coordination  Plans Development  Agreement Process  Plan Review Process  PS&E Procedures  Construction and Inspection  Fiscal Management  Tracking Procedures

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.