Allen Rust, EIT KYTC Division of Right of Way and Utilities

slide-2
SLIDE 2

Rail Coordination

 Plans Development  Agreement Process  Plan Review Process  PS&E Procedures  Construction and Inspection  Fiscal Management  Tracking Procedures

slide-3
SLIDE 3

Plans Development

 Determination of need for new/improved highway  Pre‐Design Meeting  Prepare project file  Preliminary Line and Grade Inspection  Final Plans in Hand Inspection

slide-4
SLIDE 4

Agreement Process

 Plans submitted to Railroad  Railroad supplies cost estimates, comments, etc.  Contract Agreement Drafted

slide-5
SLIDE 5

Plan Review Process

 Review construction plans for Railroad details

 Railroad comments and requirements  Railroad detail sheet  Crossing pavement elevation sheet  Any other necessary amendments

 Avoid delays in both time and money

slide-6
SLIDE 6

PS&E

(Plans, Specifications, & Estimates Section)

 Division of Construction Procurement  Special Notes for Protection of Railway Interests

 Flagging notes  Insurance requirements  Train Info

 Project Summary Sheet

slide-7
SLIDE 7

Construction and Inspection

 District Utilities Supervisor coordinates all work by the

Rail Companies

 “Notification of Utility Relocation and/or Adjustment

“ completed by District

 Inspections by District  ALL WORK BY THE RAIL COMPANIES MUST BE

DOCUMENTED

 Invoices and Billing

slide-8
SLIDE 8

Fiscal Management

 Final Invoice indicates work is completed  Audits

 Not required for each project  Random projects are selected  Can be requested  Requests sent to Branch Manager of the External Audit

Staff

 Files kept for 20 years

slide-9
SLIDE 9

Tracking Procedures

 Aware of all Railroad projects in Six‐Year Plan  ORACLE

 Item Number  Letting Date  “RAILROAD INVOLVEMENT”

 Monthly status checks

slide-10
SLIDE 10

Rail Coordination

 Plans Development  Agreement Process  Plan Review Process  PS&E Procedures  Construction and Inspection  Fiscal Management  Tracking Procedures