alan sorum maritime operations project manager the
play

Alan Sorum Maritime Operations Project Manager The objective of - PowerPoint PPT Presentation

Alan Sorum Maritime Operations Project Manager The objective of this study was to analyze the maritime implications for TAPS tankers under distress anchoring at Mid-PWS PPOR. The waters of PWS are very deep, limiting the number and


  1. Alan Sorum – Maritime Operations Project Manager

  2. The objective of this study was to analyze the maritime implications for TAPS tankers under distress anchoring at Mid-PWS PPOR. The waters of PWS are very deep, limiting the number and availability of safe anchorages for large deep draft tankers. Anchorage locations for large tankers frequenting PWS require: — Adequate water depth and swinging room — Suitable holding ground — Be protected from weather.

  3. PWS PPOR Map 11

  4. Project Sequence — Summary of Wind Climatology — Pre-Simulation Interviews with Local Subject Matter Experts and Agency Stakeholders — Simulations Conducted — Post-Simulation Interviews — Simulation Results — Conclusions - Recommendations

  5. Summary of Wind Climatology — Analysis conducted by Dr. Peter Olsson of the Alaska Experimental Forecast Facility UAA — Wind roses plotted for multiple sites in PWS — A wind rose is a graphical representation of a wind climatology that incorporates both speed and direction — Goal was to use actual wind conditions in ship simulations of PPOR sites

  6. Wind Rose North Smith Island

  7. Pre-Simulation Interviews Safeguard Marine conducted 16 interviews to assure accurate ship simulations with individuals from: — Southwest Alaska Pilots Association — ADEC — Active and retired TAPS industry representatives — Active and retired TAPS ship captains — Retired PWS assist tugboat operators — US Department of Interior — PWSRCAC — ADF&G — NOAA

  8. PPOR 1 and PPOR SGM 1

  9. PPOR 2 and 3

  10. Simulations — 34 simulations were conducted at the AVTEC Marine Training Center in Seward, Alaska — Vessel position was plotted every three minutes — After the ship anchor was deployed, movement was monitored for an hour — Exit interviews were conducted immediately after each of the specific simulations were completed

  11. Recommendations 1. Both North Smith Island and the alternative location at North Smith Island should not be considered a viable PPOR as simulations of tankers consistently grounded. 2. Outside Bay should not be considered a viable PPOR for tankers as it is too close to a ten fathom curve, and does not provide a safe swing area for tankers at anchor. 3. McPherson Bay is a viable PPOR for tankers. The site allows enough swing area for tankers at anchor, and provides some protection from the majority of environmental conditions. 4. The PPOR identified in the Prince William Sound Subarea Contingency Plan in North and South Prince William Sound should be similarly assessed for their capability to provide potential refuge for tankers in distress.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend