Airport Guideway and Stations and City Center Utilities Relocation
Project Oversight Committee Meeting September 19, 2019 Honolulu, Hawaiʻi
Airport Guideway and Stations and City Center Utilities Relocation - - PowerPoint PPT Presentation
Airport Guideway and Stations and City Center Utilities Relocation Project Oversight Committee Meeting September 19, 2019 Honolulu , Hawaii Airport Guideway and Stations 53% Complete (54.5% Planned) Completed To Date: Design progression
Project Oversight Committee Meeting September 19, 2019 Honolulu, Hawaiʻi
2
Completed To Date: Design progression at 99% (Earned value at 96% due to design resubmittals). 158 drilled shaft foundations completed, 124 columns installed, and 56 spans have been erected. 2,015 pre-cast segments have been cast.
Major Work Remaining
Major Work Remaining
Energization Status
Major Work Remaining
Major Work Remaining
Dillingham near GasPro.
and mitigate original work scope on Dillingham, Halekauwila, and Queen Street.
Legend (Focus on Dry Relocations): Wet / Road in Progress Construction (% in dark) Pending Approvals/Permits Pending Final Design On Hold/Pending On Schedule Potential Delay Behind Schedule Status as of September 5, 2019
Key Issues
Action BIC Solutions for Constraints / Scope on Dillingham HART Secure Right of Way HART Decisions on Design Elements HART Finalize Designs AECOM Obtain Utility Approvals AECOM Provide Timely Permits C&C
24