airport guideway and stations
play

Airport Guideway and Stations and City Center Utilities Relocation - PowerPoint PPT Presentation

Airport Guideway and Stations and City Center Utilities Relocation Project Oversight Committee Meeting September 19, 2019 Honolulu , Hawaii Airport Guideway and Stations 53% Complete (54.5% Planned) Completed To Date: Design progression


  1. Airport Guideway and Stations and City Center Utilities Relocation Project Oversight Committee Meeting September 19, 2019  Honolulu , Hawaiʻi

  2. Airport Guideway and Stations 53% Complete (54.5% Planned) Completed To Date: Design progression at 99% (Earned value at 96% due to design resubmittals). 158 drilled shaft foundations completed, 124 columns installed, and 56 spans have been erected. 2,015 pre-cast segments have been cast. 2

  3. Airport Guideway and Stations 53% Complete (54.5% Planned) Makalapa (Pearl Harbor Naval Base Station) – 6% Complete Major Work Remaining • Conduit installation for communications at Train Control. • Structural backfill for Faregate. • Installation of 8-inch waterline – Complete. • Faregate and End Platform cabinets. 3

  4. Airport Guideway and Stations 53% Complete (54.5% Planned) Lelepaua (Honolulu International Airport) – 2% Complete Major Work Remaining Energization Status • Sample soil before over-excavation. • Station – [Date] • Energization - [Date] • Storm drain installation. • Demobilize water treatment plant. 4

  5. Airport Guideway and Stations 53% Complete (54.5% Planned) Āhua (Lagoon Drive) – 3% Complete Major Work Remaining • Installation of underground conduit from TCCR at Mauka entrance. • Mauka entrance spread footings formwork and reinforcing in preparation for concrete. 5

  6. Airport Guideway and Stations 53% Complete (54.5% Planned) (Kahauiki) Middle Street Transit Center – 0.2% Complete Major Work Remaining • Install temporary fencing. • Reach E: Coordinating AGS activities with waterline installation on Dillingham near GasPro. • HECO Zone 9: Electrical relocation work. 6

  7. City Center Utilities Relocation Status as of September 5, 2019 • Estimated Completion: February 2022 1A • Highlights on Construction Areas: ◦ 1A – Completing 24” water facility 1B ◦ 1B – Evaluating alternatives ◦ 1C – Evaluating alternatives ◦ 2 – Installing drain laterals ◦ 3 – Removing abandoned fuel lines ◦ 4 – Redesigning utility relocations ◦ 5 – Assessing roundabout removal impacts 1C ◦ 6 – Started probing and layout 2 • Highlights on Elimination Activities: ◦ Working through several options to finalize design and mitigate original work scope on Dillingham, Halekauwila, and Queen Street. 3 Key Issues Action BIC Solutions for Constraints / Scope on Dillingham HART 4 Secure Right of Way HART Decisions on Design Elements HART Legend (Focus on Dry Relocations): Finalize Designs AECOM 6 Wet / Road in Progress On Hold/Pending Construction (% in dark) On Schedule Obtain Utility Approvals AECOM 5 Pending Approvals/Permits Potential Delay Provide Timely Permits C&C Pending Final Design Behind Schedule

  8. Dillingham Wet Tie-In Point 24-inch Water Line 8

  9. Dillingham to Kaaahi Work completed:  Potholing  Sewer jackets within the roadway  Trench patching  Sewer Line GSS1352 Deleted 9

  10. Kaaahi Street to Iwilei Road Work continues:  GSS1362 manholes being epoxy coated.  Miscellaneous demonstration. Work completed:  Potholing  Sewer Jackets  Water lines GW1360 and GW1362  Drain line GSD1363 work in DAGS property.  Drain line work on remainder of GSD1363.  Drain Line 1362.1 work in private property.  Sewer line GSS1362 trench stabilization.  GSS1362 and laterals.  GSD1360 work. 10

  11. Kaaahi Street Drain line work 11

  12. Kaaahi Street Gravity Sewer Work - Completed 12

  13. Iwilei Road to North Nimitz Hwy Gravity Sewer Work - Completed  Sewer line GSS1371  Water line GW1373  Drain line GSD1376 deleted 13

  14. North Nimitz Hwy Work continues:  HECO F6 grouting completed and removal ongoing.  Miscellaneous demo.  Fuel line removal nearing completion. Work completed:  Potholing  Water Line GW1402. Multiple utility work deleted:  Water line GW1379  Sewer line GSS1396  Drain line GSD1393  Sewer line GSS1403  Drain line GSD1403 14

  15. Nimitz Fuel Line Removal 15

  16. Nimitz Unknown Utility 16

  17. HECO F6 Grouting Completed and removal ongoing 17

  18. Halekauwila Street  Sewer start up pending pole relocations.  Nan working on temporary pole relocation plan. 18

  19. Queen to Kamakee (Completed) 19

  20. Kamakee to Pensacola Work continues:  Dry utilities potholing underway but not completed due to some areas being in the sidewalk.  One-Time Review (OTR) plans received and being routed for street usage permit. DTS signature received.  Temporary Traffic Signal Plan (TTSP) submitted, under DTS review. Work completed:  Additional probing completed 6/5/19.  Potholing for wet utilities. 20

  21. Pensacola to Piikoi  DTS Street Usage permits Pensacola to Piikoi Streets received.  Wet utilities potholing underway Pensacola to Piikoi Street.  One-Time Review (OTR) plans received and being routed for street usage permit, awaiting DTS signature.  Temporary Traffic Signal Plan (TTSP) submitted, under DTS review Traffic Management Plan (TMP) accepted.  Piikoi intersection day Traffic Control Plans (TCP) accepted. Routed to DTS for street usage permit. 21

  22. Task Order 18 (Pt. 1: Pensacola to Piikoi Potholing) 22

  23. Piikoi to Kona Iki  One-Time Review (OTR) plans received and being routed for street usage permit.  Right of Entry for Brookfield Properties Retail potholing executed.  Traffic Control Plans (TCP) approved by HART.  Potholing underway.  HECO 25kv line located 9/4/19. 23

  24. 24

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend