Airport Guideway and Stations and City Center Utilities Relocation - - PowerPoint PPT Presentation

airport guideway and stations
SMART_READER_LITE
LIVE PREVIEW

Airport Guideway and Stations and City Center Utilities Relocation - - PowerPoint PPT Presentation

Airport Guideway and Stations and City Center Utilities Relocation Project Oversight Committee Meeting September 19, 2019 Honolulu , Hawaii Airport Guideway and Stations 53% Complete (54.5% Planned) Completed To Date: Design progression


slide-1
SLIDE 1

Airport Guideway and Stations and City Center Utilities Relocation

Project Oversight Committee Meeting September 19, 2019  Honolulu, Hawaiʻi

slide-2
SLIDE 2

2

Airport Guideway and Stations

53% Complete (54.5% Planned)

Completed To Date: Design progression at 99% (Earned value at 96% due to design resubmittals). 158 drilled shaft foundations completed, 124 columns installed, and 56 spans have been erected. 2,015 pre-cast segments have been cast.

slide-3
SLIDE 3

3

Airport Guideway and Stations

53% Complete (54.5% Planned) Makalapa (Pearl Harbor Naval Base Station) – 6% Complete

Major Work Remaining

  • Conduit installation for communications at Train Control.
  • Structural backfill for Faregate.
  • Installation of 8-inch waterline – Complete.
  • Faregate and End Platform cabinets.
slide-4
SLIDE 4

4

Major Work Remaining

  • Sample soil before over-excavation.
  • Storm drain installation.
  • Demobilize water treatment plant.

Energization Status

  • Station – [Date]
  • Energization - [Date]

Airport Guideway and Stations

53% Complete (54.5% Planned) Lelepaua (Honolulu International Airport) – 2% Complete

slide-5
SLIDE 5

5

Major Work Remaining

  • Installation of underground conduit from TCCR at Mauka entrance.
  • Mauka entrance spread footings formwork and reinforcing in preparation for concrete.

Airport Guideway and Stations

53% Complete (54.5% Planned) Āhua (Lagoon Drive) – 3% Complete

slide-6
SLIDE 6

6

Major Work Remaining

  • Install temporary fencing.
  • Reach E: Coordinating AGS activities with waterline installation on

Dillingham near GasPro.

  • HECO Zone 9: Electrical relocation work.

Airport Guideway and Stations

53% Complete (54.5% Planned) (Kahauiki) Middle Street Transit Center – 0.2% Complete

slide-7
SLIDE 7

City Center Utilities Relocation

  • Estimated Completion: February 2022
  • Highlights on Construction Areas:
  • 1A – Completing 24” water facility
  • 1B – Evaluating alternatives
  • 1C – Evaluating alternatives
  • 2 – Installing drain laterals
  • 3 – Removing abandoned fuel lines
  • 4 – Redesigning utility relocations
  • 5 – Assessing roundabout removal impacts
  • 6 – Started probing and layout
  • Highlights on Elimination Activities:
  • Working through several options to finalize design

and mitigate original work scope on Dillingham, Halekauwila, and Queen Street.

1A 2 3 5 6 1B 1C 4

Legend (Focus on Dry Relocations): Wet / Road in Progress Construction (% in dark) Pending Approvals/Permits Pending Final Design On Hold/Pending On Schedule Potential Delay Behind Schedule Status as of September 5, 2019

Key Issues

Action BIC Solutions for Constraints / Scope on Dillingham HART Secure Right of Way HART Decisions on Design Elements HART Finalize Designs AECOM Obtain Utility Approvals AECOM Provide Timely Permits C&C

slide-8
SLIDE 8

8

Dillingham Wet Tie-In Point

24-inch Water Line

slide-9
SLIDE 9

Work completed:

  • Potholing
  • Sewer jackets within the

roadway

  • Trench patching
  • Sewer Line GSS1352 Deleted

Dillingham to Kaaahi

9

slide-10
SLIDE 10

Work continues:

  • GSS1362 manholes being epoxy coated.
  • Miscellaneous demonstration.

Work completed:

  • Potholing
  • Sewer Jackets
  • Water lines GW1360 and GW1362
  • Drain line GSD1363 work in DAGS

property.

  • Drain line work on remainder of

GSD1363.

  • Drain Line 1362.1 work in private

property.

  • Sewer line GSS1362 trench stabilization.
  • GSS1362 and laterals.
  • GSD1360 work.

Kaaahi Street to Iwilei Road

10

slide-11
SLIDE 11

11

Kaaahi Street

Drain line work

slide-12
SLIDE 12

Kaaahi Street

Gravity Sewer Work - Completed

12

slide-13
SLIDE 13
  • Sewer line GSS1371
  • Water line GW1373
  • Drain line GSD1376 deleted

13

Iwilei Road to North Nimitz Hwy

Gravity Sewer Work - Completed

slide-14
SLIDE 14

Work continues:

  • HECO F6 grouting completed and

removal ongoing.

  • Miscellaneous demo.
  • Fuel line removal nearing

completion. Work completed:

  • Potholing
  • Water Line GW1402.

Multiple utility work deleted:

  • Water line GW1379
  • Sewer line GSS1396
  • Drain line GSD1393
  • Sewer line GSS1403
  • Drain line GSD1403

14

North Nimitz Hwy

slide-15
SLIDE 15

15

Nimitz Fuel Line Removal

slide-16
SLIDE 16

16

Nimitz Unknown Utility

slide-17
SLIDE 17

HECO F6 Grouting Completed and removal ongoing

17

slide-18
SLIDE 18

Halekauwila Street

  • Sewer start up pending pole

relocations.

  • Nan working on temporary

pole relocation plan.

18

slide-19
SLIDE 19

Queen to Kamakee

(Completed)

19

slide-20
SLIDE 20

Work continues:

  • Dry utilities potholing underway

but not completed due to some areas being in the sidewalk.

  • One-Time Review (OTR) plans

received and being routed for street usage permit. DTS signature received.

  • Temporary Traffic Signal Plan (TTSP)

submitted, under DTS review. Work completed:

  • Additional probing completed

6/5/19.

  • Potholing for wet utilities.

Kamakee to Pensacola

20

slide-21
SLIDE 21

Pensacola to Piikoi

  • DTS Street Usage permits

Pensacola to Piikoi Streets received.

  • Wet utilities potholing underway

Pensacola to Piikoi Street.

  • One-Time Review (OTR) plans

received and being routed for street usage permit, awaiting DTS signature.

  • Temporary Traffic Signal Plan

(TTSP) submitted, under DTS review Traffic Management Plan (TMP) accepted.

  • Piikoi intersection day Traffic

Control Plans (TCP) accepted. Routed to DTS for street usage permit.

21

slide-22
SLIDE 22

Task Order 18 (Pt. 1: Pensacola to Piikoi Potholing)

22

slide-23
SLIDE 23

Piikoi to Kona Iki

  • One-Time Review (OTR) plans

received and being routed for street usage permit.

  • Right of Entry for Brookfield

Properties Retail potholing executed.

  • Traffic Control Plans (TCP)

approved by HART.

  • Potholing underway.
  • HECO 25kv line located 9/4/19.

23

slide-24
SLIDE 24

24