ACCC Public Forum 18 March 2004 18 March 2004 George Maltabarow - - PowerPoint PPT Presentation
ACCC Public Forum 18 March 2004 18 March 2004 George Maltabarow - - PowerPoint PPT Presentation
ACCC Public Forum 18 March 2004 18 March 2004 George Maltabarow Maltabarow George Acting Managing Director Acting Managing Director Issues Issues 1. ACCC process 1. ACCC process 2. ACCC Regulatory Framework 2. ACCC Regulatory Framework
2
Issues Issues
- 1. ACCC process
- 1. ACCC process
- 2. ACCC Regulatory Framework
- 2. ACCC Regulatory Framework
- 3. Response to Supplementary Draft
- 3. Response to Supplementary Draft
3
ACCC process ACCC process
Initial application - September 2003 Draft Determination - April 2004 Supplementary Draft - March 2005 9 months into the regulatory period we have: – no final determination in place
derogation in place for pricing purposes
– continued framework uncertainty – questions over code compliance of supplementary draft determination
4
ACCC Framework ACCC Framework
- Initially ACCC proposed
Initially ACCC proposed “ “firm firm” ” cap cap
- EA supports move away from firm cap
EA supports move away from firm cap
- However, EA believes
However, EA believes “ “modified cap modified cap” ”is designed is designed to limit capital investment to limit capital investment
5
ACCC Framework ACCC Framework
- ACCC argues that new framework alleviates need
ACCC argues that new framework alleviates need to review to review “ “every nut and bolt every nut and bolt” ”
- EA believes ACCC has abandoned notion of
EA believes ACCC has abandoned notion of economic incentives driving performance economic incentives driving performance
- utcomes
- utcomes
- Instead,
Instead, ACCC ACCC’ ’s s strategy is to second strategy is to second-
- guess
guess management and technical expertise of utilities management and technical expertise of utilities
- Regulation has become intrusive and regulates
Regulation has become intrusive and regulates behaviour rather than performance behaviour rather than performance
- Is this what
Is this what Hilmer Hilmer had in mind? had in mind?
6
ACCC Framework ACCC Framework
- ACCC now makes project by project decisions
ACCC now makes project by project decisions
- ACCC puts itself in the shoes of the utility, the
ACCC puts itself in the shoes of the utility, the management & the Board management & the Board
- BUT where is
BUT where is ACCC ACCC’ ’s s accountability when things accountability when things go wrong? go wrong?
7
Price impact Price impact
- ACCC rejected $100m
ACCC rejected $100m capex capex for EA for EA
- Price impact of including full
Price impact of including full capex capex ($283m) is: ($283m) is:
– – $0.82 per year on average end user $0.82 per year on average end user’ ’s bill s bill – – or 1.6 cents per week
- r 1.6 cents per week
- Very concerning that ACCC risks network failure
Very concerning that ACCC risks network failure for such a marginal benefit to consumers for such a marginal benefit to consumers
8
Case study: Ourimbah STS Case study: Ourimbah STS
- EA proposed replacement due to aged equipment
EA proposed replacement due to aged equipment and loading and loading
- ACCC recommended that Ourimbah be deferred
ACCC recommended that Ourimbah be deferred
- Consequences are significant for Central Coast
Consequences are significant for Central Coast residents if substation fails residents if substation fails
- 49,000 customers could face blackouts
49,000 customers could face blackouts
- Impact could be avoided for extra:
Impact could be avoided for extra:
– – 15 cents per year on final bills 15 cents per year on final bills – – or 0.3 cents per week
- r 0.3 cents per week
9
ACCC Framework ACCC Framework
- Main cap allowance
Main cap allowance
– – ACCC has moved away from FIRM cap ACCC has moved away from FIRM cap
- Excluded projects
Excluded projects
– – ACCC trying to cater for uncertain capital ACCC trying to cater for uncertain capital
- –
– regime itself uncertain regime itself uncertain
- –
– 5 5-
- year incentive period is not supported
year incentive period is not supported
- –
– Regime cannot be implemented properly under Code Regime cannot be implemented properly under Code
10
ACCC Framework ACCC Framework
- Re
Re-
- opener mechanism
- pener mechanism
– – Not subject to consultation Not subject to consultation
- –
– Not consistent with current Code Not consistent with current Code
- –
– Cannot be implemented without Code change Cannot be implemented without Code change
- –
– Replaces the pass Replaces the pass-
- through rules
through rules
- –
– Reduces flexibility of framework Reduces flexibility of framework
11
So what have we achieved? So what have we achieved?
Initial draft (April 2004) EA’s revised submission Supplementary draft (March 2005) Forecast capex $184m $283m $182m Total revenues $509m $517m $501m Firm cap
- Pass-through
- Code compliance
- ?
12
The Supplementary Draft The Supplementary Draft
- $65m cut to replacement program
$65m cut to replacement program
- Represents 40% of what we sought
Represents 40% of what we sought
- Cuts are not sustainable in long term
Cuts are not sustainable in long term
- $35m project excluded (but not funded)
$35m project excluded (but not funded)
13
191919241929 19341939194419491954195919641969197419791984198919941999 200420092014 5 Year Period Ending 30 June
Replacement Cost $‘millions (2002)
Capital Depreciation
Capex cycle: replacing assets built in 1960s
14
Age profile of EA Transmission network
M$ 0 M$ 50 M$ 100 M$ 150 M$ 200 M$ 250 M$ 300 M$ 350 M$ 400 Pre-1934 (70+) 1940 - 1944 (60 - 64) 1950 - 1954 (50 - 54) 1960 - 1964 (40 - 44) 1970 - 1974 (30 - 34) 1980 - 1984 (20 - 24) 1990 - 1994 (10 - 14) 2000 - 2004 (0 - 4) Year installed (age now) Replacement cost Substations Pow er Transformers 132kV underground 132kV ov erhead 66kV overhead (M$ 2004 real) Assets currently reaching end-of-life
SKM report on replacement
15
Capex reduction Capex reduction
- $65m rejected through PB desk top review
$65m rejected through PB desk top review
– – EA brought SKM in to verify the replacement strategy EA brought SKM in to verify the replacement strategy – – SKM proposed higher levels of replacement than put by EA SKM proposed higher levels of replacement than put by EA
- replacement strategy represents justified middle ground
replacement strategy represents justified middle ground
- Replacement of critical elements denied by ACCC
Replacement of critical elements denied by ACCC – – aging transformers & switchgear aging transformers & switchgear denied denied – – 70 year old OH line 70 year old OH line denied denied – – Ourimbah STS Ourimbah STS denied denied
- unacceptable level of safety and reliability risks
unacceptable level of safety and reliability risks
16
Next steps Next steps
- EA responded to
EA responded to ACCC ACCC’ ’s s initial draft in July 04 initial draft in July 04
- ACCC has not addressed
ACCC has not addressed EA EA’ ’s s response to: response to:
– – cuts to cuts to opex
- pex
– – rejection of past rejection of past capex capex
Step 1 Step 1 -
- Address outstanding issues
Address outstanding issues Step 2 Step 2 -
- Improve workability of excluded projects
Improve workability of excluded projects framework framework Step 3 Step 3 -
- Deliver final determination in time for
Deliver final determination in time for 2005 2005-
- 2006 prices