A LEADING LAW FIRM WITH A APPROACH
Contractual and procurement issues in the run up to 2016 Glasgow Caledonian University – 4 October 2012 Simon Lewis, Partner, Construction
A LEADING LAW FIRM WITH A APPROACH Contractual and procurement - - PowerPoint PPT Presentation
A LEADING LAW FIRM WITH A APPROACH Contractual and procurement issues in the run up to 2016 Glasgow Caledonian University 4 October 2012 Simon Lewis, Partner, Construction Introduction Context: Increasing use of BIM across all
Contractual and procurement issues in the run up to 2016 Glasgow Caledonian University – 4 October 2012 Simon Lewis, Partner, Construction
days of the execution of contract between owner and A/E
BIM execution plan contents include:
responsible for each model (federated models)
contract documents
various project milestones
BIM execution plan contents include:
units, conventions for defining critical dimensions and modelled content
conventions, file structure and software to be utilised
BIM-related compensation and costs
and reliance for each Model Element
Levels of development: – 100: overall building massing indicative of area, height, volume, location and orientation in 3D or represented by other data – 200: model elements modelled as generalised systems or assemblies with approximate quantities, size, shape, location and orientations. Non-geometric information may also be attached – 300: model elements are modelled as specific assemblies accurate in terms of quantity, size, shape, location and
Levels of development: – 400: model elements are modelled as specific assembles that are accurate in terms of size, shape, location, quantity and
– 500: model elements are modelled as constructed assemblies actual and accurate in terms of size, shape, location, quantity and orientation. Non-geometric information may also be attached
Main features:
least through design and construction phases
developed through the AIA LODs - the tabular approach
within 30 days of the contract
increased fees. BIM deliverables at the minimum levels of development shall be included in the basic fee as negotiated (reflects experience noted in NBS BIM report of March 2011)
Requires a BIM execution plan which includes: – Overview information – Project information – Key project contacts – Project goals/BIM objectives – Organisational roles and staffing – BIM process design – BIM and facility data requirements – Collaboration procedures – Model quality control procedures – Technology infrastructure needs – Model structure – Product deliverables – Delivery strategy/contracts
– levels of BIM maturity – BIM standards and classifications – project stages and BIM-enabled information drops – model objects and model configuration management. – roles and responsibilities include information manager, design manager, model content originator and authorised content user
different project stages include the following: – definition of required LODs – formats and exchange standards to be used – defined uses for the information and authorised users – adopts the tabular approach
stages/levels of development and design contributors and design elements
BIM model for the whole of the works, or alternatively where the contractor is required to make a Design Contribution to a BIM model prepared by or under the direction of the Employer
participant may rely upon the dimensional accuracy of that model
Author and limitation on reliance by others to specific LODs. The tabular approach
addition each party waives claims against the other parties for consequential damages arising out of or relating to the use of or access to a model. Includes damages for loss of use of the project, rental expenses, loss of income or profit, costs of financing, loss of business, principal office overhead and expense, loss of reputation
reliance on a Model Element inconsistent with the appropriate LOD is entirely at that party’s risk. Further, that party indemnifies the Model Element Author from any claims arising out of such unauthorised use
relevant parties from all claims etc arising out of or related to the contractor’s or any other person’s use of electronic files
design users against any liability whether direct or consequential arising out of or in connection with the contractor’s design and is
Manager of any clashes, potential clashes, or inconsistencies between the Contractor’s design and that made by any other Design Contributor (where Contractor is contributing to a model)
the integrity of that model throughout
information plan, no project team member warrants that any electronic data delivered to the information manager or any other party is complete, technically accurate, free from defects or suitable for its intended use. Clause to be developed further
use each party’s contributions to the model for project purposes
indemnify the others in relation to IP. User of the data is responsible for verifying the accuracy of the digital representations and that their software did not corrupt the information during the transfer process
intended to vest ultimately in the Employer at the end of construction period
ConsensusDOCS or AIA save for BIM-related compensation and costs (ConsensusDOCS)
to the relevant contract documents
agreements between employer and project team only and not down the contractual chain. Is this adequate? Compare with ConsensusDOCS
– nature of express obligations to comply – is contractor obliged to procure other parties’ compliance? – priority of documents issues – is it necessary/advisable to repeat some of the protocol requirements in the main contract?
appointment, sub-contract or supply agreement
Building Contract Committee Public Sector Supplement – November 2011
Building Information Modelling protocol” as a contract document. To be included in the ERs or other suitable contract document.
would be implied and if employer fails to do so, act of prevention?
project by project basis?
and implementation. Leave it to the market
contracts?
contract right now avoids or limits the arguments in the future