A DIALOGUE WITH THE NORTHERN VIRGINIA DISTRICT November 7, 2019
1
A DIALOGUE WITH THE NORTHERN VIRGINIA DISTRICT November 7, 2019 1 - - PowerPoint PPT Presentation
A DIALOGUE WITH THE NORTHERN VIRGINIA DISTRICT November 7, 2019 1 Jeff Southard, Esq . VTCA Executive Vice President 2 Helen Cuervo, P.E. Northern Virginia District Engineer Virginia Department of Transportation 3 CONSTRUCTION 11/7/2019
1
VTCA Executive Vice President
2
Northern Virginia District Engineer Virginia Department of Transportation
3
Bill Cuttler, P.E., District Construction Engineer
5
6
7
8
10
Construction Quality Improvement Program FY20 (as of 9/23/2019) District 94.6% Target 91% State TBD Environmental Commitments District 92% (12/13) Target TBD State TBD
11
VDOT Construction On-Budget FY20 (as of 9/23/2019) District 87% Minimum Target 85% State 92% Number of District Projects 31
12
VDOT Construction On-Time FY20 (as of 11/1/2019) District 94% Minimum Target 77% State 96% Number of District Projects 32
13
14
15
16
17
18
Nicholas J. Roper, P.E. District Project Development Engineer
November 7, 2019
On-Time Performance – 56% On-Budget Performance – 73%
Projects scheduled for award in FY20
VDOT Dashboard LAP Dashboard
20
Initial Baseline 2nd Baseline
50% of the time
for on-time advertisement starting & completing right of way on time is the most influential cause
21
Initial Baseline 2nd Baseline
22
Interchange
Patriot Park
I-95 Southbound Auxiliary Lane $32M Route 286 Widening & Popes Head Interchange $290M Richmond Highway Corridor Improvements $372M
phases beginning in 2023
23
Route 29 Widening (Union Mill to Buckley’s Gate) $86M Route 1 Widening & SB Realignment in Dumfries $130M I-395 & Boundary Channel Drive Interchange $21M
bottleneck
between I-66 & Fairfax City
confession fee
design approved; construction planned in 2023
to VDOT in spring 2020
in fall 2020
Brady Hill Rd to Route 234
traffic
24
Prince William Rte 1 Widening (Featherstone-
Loudoun Northstar Blvd $98M Fairfax Springfield CBC Garage $64M
lanes from Neabsco Road to Occoquan
bus bays & transit center, bike storage, community space for events
Shreveport Drive to Route 50
2020
25
state and local funds
2019
Fairfax County
Widen Rte 28 from Old Centreville Rd to PW line (2.3 mi) $96M
Prince William County
Interchange at Route 234 Bypass & Balls Ford Rd $145M
26
Loudoun County
Route 15 North of Leesburg $210M
Fairfax County
Richmond Hwy BRT $735M
Prince William County
Route 28 Bypass $300M
27
to S. Joyce Street & Pentagon
Columbia Pike (Rte 244) and Washington Blvd (Rte 27)
advertisement in mid-2020
28
VDOT Administered
Study Limits
29
Locally Administered (Arlington)
30
31
32
Lauren C. Mollerup, P.E., District Maintenance Engineer
Note: Funding and Activities based on previous three fiscal year averages (FY 2016 – FY 2018); numbers are rounded to the nearest $5 million 34
35
36
37
38
39
40
AADT Current %. Suff. % Network % Truck % VMT
Above 3,500 54.8 5 75 59 Above 5,000 55.2 4 70 54
Secondary Current Condition and Traffic
41
AADT Current %. Suff. % Network % Truck % VMT
Above 3,500 85.1 68 94 95 Above 5,000 85.1 62 90 91
AADT Current %. Suff. % Network % Truck % VMT
Above 3,500 54.8 5 75 59 Above 5,000 55.2 4 70 54
Primary Current Condition and Traffic Secondary Current Condition and Traffic
42
AADT Current %. Suff. % Network % Truck % VMT
Above 3,500 85.1 68 94 95 Above 5,000 85.1 62 90 91
AADT Current %. Suff. % Network % Truck % VMT
Above 3,500 54.8 5 75 59 Above 5,000 55.2 4 70 54
Primary Current Condition and Traffic Secondary Current Condition and Traffic
% Suff. for ≥ 3,500 % Suff. for < 3,500
82% 75% $150M AADT ≥ 3,500 AADT < 3,500
82% 60% $225M 75% $221M 70% $219M 65% $215M
Primary Current Investment: $165M per year, FY 2020 Secondary Current Investment: $200M per year, FY2020
43
Current investment: $425M per year, FY 2020
Targets, % Sufficiency
$ Millions IS PR SC Years 1-6 Years 7-20
IS PR SC IS PR SC
Current Investment – Current Policy
88 171 227 111 193 203
82% 82% 65% $486 $507
($61) ($82)
Current Policy Proposed Targets *All amounts in 2019 dollars
44
45
46
Metal Culverts Timber Deck Bridges Concrete Girder Bridges Concrete Slab Bridges Concrete Culverts Steel Girder Bridges
47
Condition Category General Condition Rating (GCR) Description Good 9 Excellent 8 Very Good 7 Good Fair 6 Satisfactory 5 Fair Poor (Structurally Deficient) 4 Poor 3 Serious 2 Critical 1 Imminent Failure Failed
48
49
50
51
52
Current investment: $384M per year, FY 2020
Targets, % Not-SD
$ Millions IS PR SC All Systems Average GCR Years 1-50
IS PR SC
Current Investment – Current Policy
161 222 123
99% 96% 94% N/A $506
($122)
53
Description Date
Special Structures and Routine Maintenance/Operations October 2019 Comprehensive Review and Approval Request November 2019 Submission to General Assembly December 2019
54
Swinks Mill Road – July 8, 2019 Swinks Mill Road– October 18, 2019
55
10 20 30 40 50 60 70 80 90 100 2011 2012 2013 2014 2015 2016 2017 2018 2019 Interstate Primary Secondary System Percent Sufficient Goal Interstate 82% 82% Primary 87% 82% Secondary 48% 65%
56
*Note: This sufficiency excludes ratings for Interstate Express lanes and Reversible lanes.
62.9% 87.8% 80.9% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% Sufficient (%)
2019 Interstate System
Arlington Fairfax Prince William
Target = 82% County Rated Lane Miles Non-Deficient Lane Miles Percent Sufficient
Arlington 60 37 62.9% Fairfax 403 354 87.8% Prince William 132 107 80.9%
Total 594 498 83.8*%
57
81.3% 90.0% 85.5% 83.5% 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% Sufficient (%)
2019 Primary System
Arlington Fairfax Loudoun Prince William Target = 82% County Rated Lane Miles Sufficient Lane Miles Percent Sufficient
Arlington 150 122 81.3% Fairfax 741 667 90.0% Loudoun 373 319 85.5% Prince William 393 328 83.5%
Total 1657 1436 86.7%
58
44% 54% 50% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% Fairfax Loudoun Prince William
Target = 65%
59
100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000
Asphalt Tonnage
Total Interstate Primary Secondary
60
100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000
Asphalt Tonnage
Total Interstate Primary Secondary
61
Project Est. Cost Estimated Completion Contractor 1 Wilson Blvd. $3.7 12 / 2019 Martins Construction 2 123 / Route 7 $2.5M 2020 Fort Myer Const. Corp. 3 I-395 Express Lanes Widening
The Lane Construction Corp. 4 Battlefield / Route 7 $59.6M 11 / 2021 Wagman Heavy Civil Inc. 5 Kirby Road $2.3 Spring 2020 Martins Construction 6 I-66 over Williamsburg Approach Slab Jacking TBD 2020 TBD 7 Transform 66 Inside and Outside the Beltway Projects (~ 70 Bridges)
63
Project Est. Cost
Prime Consultant 1 I-66 over Route 29 TBD 2/2020 In-house 2
Run (unfunded) $5M TBD HNTB 3
$6.7M 2020 WSP 4
Co.) (unfunded) $3.5M TBD ALA 5
Catoctin Cr $4.5M 2020 WSP 6
Run $3.2M 2020 Volkert 7 I-95 over Neabsco Creek Rehabilitation Study Phase $500K TBD WSP
64
Project Est. Cost
Prime Consultant 8 Van Buren Road Bridge over Quantico Creek $1.3M 2021 WSP 9 Route 28 over Bull Run $2.5M 11/ 2019 WSP 10 King Street over I-395 $13 M 11/2019 WSP 11 Duke Street over I-395 $15 M 2020 WSP 12 W&OD Trail under Dry Mill Rd (unfunded) $200K
13
Pimmet Run $6M 2022 Alvi Associates 14 Route 29 over Cub Run Rehab $3M TBD In-house
65
Project Est. Cost
Date Prime Consultant 15 Joint Closures and rehabilitation of 3- I-495 Bridges over the DTR $5M 1 / 2020 In-house 16 Springvale Road (30%) $3M 11/ 2019 In-house 17 Sherrow Avenue (Locality) TBD TBD HDR 18
Creek TBD TBD WRA 19 I-66 Parking Garage TBD TBD AECOM 20 Rosslyn Tunnel Ceiling TBD TBD TBD 21 Davis Ave.(Rock Hill Drive)
TBD TBD Volkert 22 Soapstone Connector over the DTR TBD TBD ATCS / TY Lin
66
Project Est. Cost
Date Consultant 23 Town Center Parkway under the DTR TBD TBD Volkert 24 Old Glebe Rd. over N Glebe Rd TBD TBD HDR 25 21st Street over I-66 TBD TBD HNTB 26 Piggott Bottom Road TBD TBD HDR 27 I-95 over Powells Creek TBD TBD HNTB 28 CSX Rail over Route 1 TBD TBD TBD 29 CSX Rail over Newington TBD TBD TBD
67
Chalk location for heat Looking like new!
68
Project Est. Cost 1 Dunlop Mill Road over Sycolin Creek $1M 2 Soapstone Culvert Near Fair Lakes $1M 3 Ketoctin Church Road Bridge $500K 4 I66 EB and WB Bridges over NSRR TBD Possibly…Additional Bridges being added to an expanded SGR program TBD
69
70
Kamal Suliman, Northern Region Operations Director
72
SYSTEMIC SAFETY TREATMENTS BENEFIT/COST RATIO DEATHS INJURIES TOTAL
HIGH VISIBILITY BACKPLATES
9.0 1 106 107
FLASHING YELLOW ARROWS
12.6 1 90 91
CURVE DELINEANATION
1.7 6 104 110
PEDESTRIAN CROSSINGS
8.9 3 85 88
UNSIGNALIZED INTERSECTION
1.3 2 62 64
SHOULDER WEDGE
17.0 13 281 294
CENTERLINE RUMBLE STRIPES ON PRIMARIES
40.0 13 115 128
EDGELINE RUMBLE STRIPES ON PRIMARIES
29.8 22 331 353 TOTAL 61 1174 1235
73
SYSTEMIC SAFETY TREATMENTS TOTAL FY20 FY21 FY22 FY23 F24 FY25
HIGH VISIBILITY BACKPLATES $ 9,050,867 $ 5,239,928 $ 1,428,989 $ 2,381,950 $ 0 $ 0 $ 0 FLASHING YELLOW ARROWS $ 12,187,596 $ 5,133,403 $ 1,351,594 $ 5,702,599 $ 0 $ 0 $ 0 ENHANCED CURVE SIGNING AND MARKING $ 1,467,079 $ 91,217 $ 0 $ 0 $ 608,116 $ 767,746 $ 0 PEDESTRIAN CROSSINGS $ 9,062,487 $ 888,083 $ 928,451 $ 1,211,023 $ 1,332,125 $ 2,785,352 $ 1,917,453 UNSIGNALIZED INTERSECTION $ 927,778 $ 372,222 $ 333,333 $ 0 $ 222,222 $ 0 $ 0 CENCERLINE/EDGELINE RUMBLE STRIPS ON PRIMARIES $ 394,917 $ 34,101 $ 57,725 $ 55,937 $ 55,937 $ 135,281 $ 55,937 TOTAL (117 M Statewide) $ 33,090,724 $ 11,758,955 $ 4,100,092 $ 9,351,508 $ 2,218,400 $ 3,688,380 $ 1,973,389
74
SYSTEMIC SAFETY TREATMENTS TOTAL On-Call RAAP Start Date End Date
HIGH VISIBILITY BACKPLATES $ 9,050,867 X Dec/2019 Jun/2021 FLASHING YELLOW ARROWS $ 12,187,596 X Dec/2019 Jun/2021 ENHANCED CURVE SIGNING AND MARKING $ 1,467,079 X Feb/2022 Jun/2024 PEDESTRIAN CROSSINGS $ 9,062,487 X Feb/2020 Jun/2025 UNSIGNALIZED INTERSECTION $ 927,778 X Dec/2019 Jun/2023 CENCERLINE/EDGELINE RUMBLE STRIPS ON PRIMARIES $ 394,917 X Dec/2019 Jun/2025 TOTAL (117 M Statewide) $ 33,090,724
75
SYSTEMIC SAFETY TREATMENTS
TOTAL LOCATIONS COMPLETED LOCATIONS REMAINING LOCATIONS % TO BE COMPLETED HIGH VISIBILITY BACKPLATES 1445 234 1211 84 % FLASHING YELLOW ARROWS 851 75 776 91 % ENHANCED CURVE SIGNING AND MARKING 57 7 50 88 % PEDESTRIAN CROSSINGS 211 7 204 97 % UNSIGNALIZED INTERSECTION 187 187 100 % CENTERLINE/EDGELINE RUMBLE STRIPS ON PRIMARIES 85 Miles 38 Miles 47 Miles 55 %
76
SYSTEMIC SAFETY TREATMENTS On-Call RAAP Anticipated Advertisement
HIGH VISIBILITY BACKPLATES X March 2020 FLASHING YELLOW ARROWS X March 2020 ENHANCED CURVE SIGNING AND MARKING X July 2020 PEDESTRIAN CROSSINGS X March 2020 UNSIGNALIZED INTERSECTION X March 2020 CENCERLINE/EDGELINE RUMBLE STRIPS ON PRIMARIES X July 2020 TOTAL (117 M Statewide) $29,208,728 $2,881,996
77
78
79
80
81
Northern Virginia District Mega Projects Director Virginia Department of Transportation
82
Shirley Construction
83
84
VTCA Executive Vice President
85
86
87