2020 capital budget ten year capital plan
play

2020 Capital Budget & Ten Year Capital Plan Special Meeting - PowerPoint PPT Presentation

2020 Capital Budget & Ten Year Capital Plan Special Meeting of Council (Budget Deliberations) December 9, 2019 Municipal Buildings 2 Project #2020-34 Homer Barrett Park Washroom 3 Project #2020-34 Homer Barrett Park Washroom 4


  1. 2020 Capital Budget & Ten Year Capital Plan Special Meeting of Council (Budget Deliberations) December 9, 2019

  2. Municipal Buildings 2

  3. Project #2020-34 Homer Barrett Park Washroom 3

  4. Project #2020-34 Homer Barrett Park Washroom 4

  5. Fleet & Equipment 5

  6. Project #2020-47 New By-law Vehicle (SUV) 6

  7. Project #2020-16 Replace Pump 52 & Tanker 55 7

  8. Project #2020-16 Replace Pump 52 & Tanker 55 8

  9. Project #2020-16 Replace Pump 52 & Tanker 55 9

  10. Project #2020-16 Replace Pump 52 & Tanker 55 10

  11. Project #2017-10 Replace (R-1) ¾ ton (2012) 11

  12. Project #2017-10 Replace (R-1) ¾ ton (2012) 12

  13. Project #2020-27 Replace 2013 Z Turn Mower 13

  14. Project #2020-37 Replace (RT-04) 2007 Tandem Trailer 14

  15. Project #2020-48 Replace (R-04) 1997 Tractor 1620 15

  16. Project #2021-01 Replace #14 Tandem (2008) 16

  17. Project #2020-38 Replace Roadside Tractor & Mower 17

  18. Project #2020-40 New Asphalt Hot Box & Trailer 18

  19. Project #2020-49 New Pick Up 19

  20. Project #2020-50 Lift for Fire Trucks-Extend Existing Hoist Track 20

  21. Roads & Related 21

  22. Urban Road Reconstruction 22

  23. Project #2017-40 Craig Road – Utilities, Box Culvert & Property Acquisition County led project • Supported by Township of Springwater development • charges Approved by Council resolution SC-043-2017 • 23

  24. Project #2015-14 Flos Road 4 East – from County Road 27 to Highway 93 Proposed over 2 years • Pulverize and Double Surface Treatment • Base Repairs • Tree Trimming • 24

  25. Project #2020-08 Coughlin Road - from Horseshoe Valley Road West to Rainbow Valley Road West Pulverize and Hot Mix Asphalt • 25

  26. Project #2017-15 Lorne Street – George to William – add William from Lorne to Amelia Lorne Street • William Street • George Street to William Street Lorne Street to Amelia 26

  27. Project #2020-15 Mill Street West – from Old Penetanguishene Road to Highway 93 Design to prepare for construction in 2021 (subject to • Council approval) 27

  28. Project #2020-47 Patterson Street – from Houden Street to Queen Street East Design to prepare for construction in 2021 (subject to • Council approval) 28

  29. Resurfacing and/or Rehabilitation 29

  30. Project #2019-51 Doran Road – from County Road 27 to the Pedestrian Crosswalk Road reconstruction • Parking at school • Storm sewer installation • 30

  31. Project #2020-12 Flos Road 10 East – from 1.35km East of Old Second to Highway 93 Pulverize and double surface treatment • 31

  32. Project #2018-14 Ushers Road – from Flos Road 8 West to County Road 92 Pulverize and double surface treatment • 32

  33. Project #2020-51 Flos Road 8 West – from 500 Metres West of County Road 27 to County Road 29 (Crossland Road) Single surface treatment • 33

  34. Project #2021-33 Old Second South – from Forbes Road to Horseshoe Valley Road West Single Surface Treatment • To be completed over 3 years • 34

  35. Structures – Bridges & Culverts 35

  36. Project #2019-54 Bridge 2 – St. Vincent Street Patching deteriorated concrete • Review and possibly replace expansion joints • Remove and repair barrier system • Raise deck drains • New waterproofing and asphalt surface • Design was approved and awarded in 2019 to be complete by end of 2019, in preparation for tendering and construction in 2020. 36

  37. Water Infrastructure 37

  38. Project #2020-42 & #2018-33 Minesing & Hillsdale – New Well Capacity review in 2020 with Design, EA and • expansion in future years, if required 38

  39. Project #2016-27 Water Meter Replacement Program To be completed in 2020 • 39

  40. Wastewater Infrastructure 40

  41. Project #2020-43 Main Pumping Station (Elmvale) Upgrades at the Elmvale Main Pumping Station • 41

  42. Project #2020-44 Flow Equalization Expansion Royal Oaks pumping station • Capacity review and pipe modifications in 2020 • 42

  43. Project #2018-40 Inflow & Infiltration Abatement Program Grout open joint to prevent infiltration Cut roots and grout cracks Grout cracks to stop 43 infiltration

  44. Project #2020-30 Elmvale Wastewater Treatment Program Tertiary Filters (4) Replacement • 44

  45. Project #2020-29 Gravity Sewer Replacement/Repair Work Proposed for 2020 – Lorne Street • 45

  46. Parks & Recreation 46

  47. Project #2016-33 Trail Development 47

  48. Project #2017-21 Park Playground Upgrades (Various locations) 48

  49. Project #2020-45 Replace Doran Park Tennis Court Lights 49

  50. Project #2020-46 Replace Homer Barrett Park Rink Boards 50

  51. Project #2020-46 Replace Homer Barrett Park Rink Boards 51

  52. Project #2019-29 Replace Compressor #2 (Elmvale Arena) 52

  53. One Time Additional Gas Tax Funds 53

  54. One Time Additional Gas Tax Approved Projects Amount Total One Time Additional Gas Tax Allocation $580,420 Council Approved allocations to date: Bus Shelter – Elmvale (7,500) Flos Road 10 West (383,452) Hillsdale Crosswalk (Convert to IPS) (189,468) Total Council Approved allocations to date ($580,420) One Time Gas Tax Funds remaining to be allocated $- 54

  55. Modernization (Small & Rural) Funding 55

  56. Modernization Funding Approved Projects Amount Total Modernization Funds Received $676,935 Council Approved allocations to date: New scheduling/booking software (13,000) Hillsdale Intersection Pedestrian Signal (35,532) Total Council Approved allocations to date ($48,532) Modernization Funds remaining to be allocated $628,403 56

  57. Modernization Funding Proposed Projects Amount Requested by Exercise Equipment @ Harry Adams Park $25,000 Councillor Maw-Chapman New LED Lighting at Minesing Pavilion 20,000 Councillor Maw-Chapman Tables & Chairs – Minesing Community Centre 16,500 Councillor Maw-Chapman Community Projector (added Dec 2, 2019) 7,500 Councillor Cabral Tables & Chairs – Anten Mills Community Centre 6,800 Councillor Maw-Chapman Digital Sign Boards – Community Halls 240,000 Staff LED Lights at TNSP- existing ball diamonds 185,000 Staff Facility Access Control & Monitoring 101,650 Staff Service Delivery Review (pending Grant approval) 50,000 Staff High Shoulder Removal Equipment/Attachment 40,000 Staff 57

  58. Modernization Funding Proposed Projects Amount Requested by Loader scales – PW Yards $20,000 Staff IPADs/Tablets – Part of Work Order Mgmt Initiative 15,000 Staff Human Resources Management System 15,000 Staff Tire changer & Balancer 13,000 Staff Animal Control Software 8,500 Staff Portable PA/Speaker System – Special Events 2,500 Staff Weatherbrain Weather Stations (4) 2,000 Staff Total Proposed Projects $768,450 Modernization Funds remaining to be allocated $628,403 Surplus/(Deficit) ($140,047) 58

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.