1 iba dublin 2012 legislation and regulation related to
play

1 IBA Dublin 2012 Legislation and regulation related to the - PowerPoint PPT Presentation

1 IBA Dublin 2012 Legislation and regulation related to the operation of public and private ports 3 October 2012 contribution by Marieke G. van den Dool 2 General Contractual arrangements for development and operation of large and medium


  1. 1

  2. IBA Dublin 2012 Legislation and regulation related to the operation of public and private ports 3 October 2012 contribution by Marieke G. van den Dool 2

  3. General Contractual arrangements for development and operation of large and medium sized ports in the Netherlands • retreatment of government from port operations • enterprise-based ports services → more flexibility and efficiency → better response to consumer’s demands • landlord port model is dominant 3

  4. Landlord port model • landlord port authority is a separate legal entity with capacity to conclude contracts, enforce standards and make rules and regulations • Rotterdam: landlord port authority is a public limited company • port operations → carried out by private companies on the basis of granted concessions 4

  5. Realization of public works and transport infrastructure projects such as ports in the Netherlands • Design Build Finance Maintain- contract (“DBFM”-contract”) used by Dutch government • Integrated contract → design, realization and maintenance commissioned to contractor • Commissioning party is usually the Dutch government • Financing shifted to contractor in exchange for financial compensation (regular payments) • Long running period • Contractor is usually a consortium of companies (in order to spread risks, join forces) 5

  6. Realization of public works and transport infrastructure projects such as ports in the Netherlands • Commissioning party → output specifications • Contractor → freedom in execution of the contract → financial compensation is incentive for good performance • Contrary to Build Operate Transfer-contract (“BOT-contract”) no transfer of legal title to the object to contractor 6

  7. Realization of public works and transport infrastructure projects such as ports in the Netherlands • Special Purpose Vehicle (“SPV”) as incorporation of the consortium • SPV concludes contract with commissioning party • Usually a private company with limited liability • Financing by banks, equity capital and by loans from the government 7

  8. Realization of public works and transport infrastructure projects such as ports in the Netherlands • Transfer of legal title no prerequisite to attract financing in the Netherlands • Banks → requirement security rights, “step-in rights” (for which a three-party contract has to be concluded) 8

  9. Realization of public works and transport infrastructure projects such as ports in the Netherlands • DBFM- contract → many risks are identified prior to conclusion of the contract • Dealt with in the contract (allocation of risks) 9

  10. Realization of public works and transport infrastructure projects such as ports in the Netherlands • Disadvantages of allocation of risks: → SPV has limited funds and needs to pass risks to contractor → contractor requires compensation (more costs) → potential conflict of interests (contractor = shareholder in SPV) → more expensive for government since some risks may never materialize 10

  11. Concession of T erminals • Concession on port services to private parties is common practice • Grant by government or port authority to private parties for specific port services • Control on organization and structure of supply side • Optimization of scarce resources as land 11

  12. Concession • Concession contract concluded between private terminal operator and landlord port authority ( for example) • Long term lease for defined period of time • Legal title rests with landlord port authority → Receipt of concession fees charged on a costs-covering basis. Future upgrading and expansion. 12

  13. The Second Maasvlakte or Maasvlakte II (expansion of Rotterdam dockland area through land reclamation) • Start in 1997 • Shortage of space in port of Rotterdam as “gateway to Europe” • Respect for nature and environment and quality of living in Rhine Estuary • Expansion of port combined with expansion of recreational areas and nature • Project was only agreed with by the two Houses of Parliament in October/November 2006 after several administrative appeals 13

  14. The Second Maasvlakte or Maasvlakte II • T endency: involvement of more market forces in development of public works • Port of Rotterdam authority → major risk taker • Revenues from concession contracts and port dues • Design, Build, Maintain contract used for realization • Finance entirely arranged for by Port of Rotterdam authority 14

  15. Some facts about the Second Maasvlakte or Maasvlakte II • T otal construction costs around EUR 2.9 billion • Financed by EUR 2 billion loans from banks and EUR 700 million loans from the Dutch government and equity • Loan from Dutch government also bears interest and is meant to be refunded from the revenues • Comprises 1730 acres (700 ha) of port areas and about 7 miles (11 km) of total length of hard and soft defenses plus more than 1300 acres of harbor basin, quay walls and infrastructure 15

  16. The Second Maasvlakte or Maasvlakte II – January 2009 • Klik om de modelstijlen te bewerken / T weede niveau / Derde niveau • Vierde niveau 16

  17. The Second Maasvlakte or Maasvlakte II – July 2012 • Klik om de modelstijlen te bewerken / T weede niveau / Derde niveau • Vierde niveau 17

  18. The Second Maasvlakte or Maasvlakte II • Output specifications → contains a design based on a system-oriented approach • Shifting of more responsibility to contractor in early stage of project and involvement of market sector in design, construction and maintenance • Transparency → no wasting of public funds, avoidance of corruption 18

  19. The Second Maasvlakte or Maasvlakte II • Roles and tasks of parties involved identified at beginning of the project • enders for construction and maintenance → T before permits were issued, time efficient • enders for concession → before starting T construction, test of financial feasibility 19

  20. The Second Maasvlakte or Maasvlakte II • Programme of Requirement → contains problem statements and requirements set by Port of Rotterdam authority • Optimization of activities of contractors within this scope • Contractor → joint venture between Boskalis and Van Oord (two major Dutch dredging companies) • Incentive for contractor to investigate and execute cost-saving scenarios 20

  21. The Second Maasvlakte or Maasvlakte II • Large extent of flexibility in the contract • Flexible design → can easily be adapted to market circumstances (example: terminals are currently meant for containers, but can be transformed to receive other cargo) 21

  22. The Second Maasvlakte or Maasvlakte II • Concession process → innovative for Dutch market • Open interaction between private parties interested and Port of Rotterdam authority , simultaneous negotiations, high transparency • Contractual details were specified in advance • Sustainability → important criterion 22

  23. The Second Maasvlakte or Maasvlakte II • Volume criterion for pre-qualification of candidates at least 2 mio TEU/year measured over past year → to attract only main players in terminal and shipping industry • First: expression of interest- document • Next phase → Non-disclosure agreements → disclosure of more detailed information and award criteria by Port of Rotterdam authority • Pre-bid sessions 23

  24. The Second Maasvlakte or Maasvlakte II • Environmental management system for terminals → important weighing factor • Aim to reduce road transport in favour of transport by rail and inland waterways • Other factors of interest: − financial feasibility − competitiveness and positioning in market − technical solutions 24

  25. The Second Maasvlakte or Maasvlakte II • Concession is important port development tool → once granted control reduces • Port of Rotterdam authority designed its own its own process • Beneficial competitive pressure, both for conclusion of DBM-contract as well as concession contracts 25

  26. Pros and cons of privatization • More competition, flexibility, compliance with consumer’s demands • Downsides: − Risk of monopoly of private parties (for instance for linesman-and pilotage services in Port of Rotterdam) leading to higher rates failing any competitive pressure − Problem for the government how to supervise that rules and regulations are being complied with by private parties (example: environmental and safety-rules) 26

  27. Supervision – example of failure: Odfjell tank storage terminal • August 2012: temporarily closing down of this terminal • Immediate cause: failure of reporting a butane leak to environmental supervisory body (DCMR) by the terminal • However, several violations of fire safety of the terminal were already reported in the past, but no appropriate action was taken 27

  28. Supervision – example of failure: Odfjell tank storage terminal • DCMR → governmental Supervisor (for chemical industry) • Inspections of premises brought to light many violations of safety regulations • Odfjell was not penalized, but was granted “grace periods” by DCMR • DCMR → reluctant to take action because of negative economic effects of closing down a terminal and reaction of provincial and municipal governments 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend