1 - BUNDLE PRODUCT What do we mean. Some History A pipeline bundle - - PowerPoint PPT Presentation

1 bundle product what do we mean some history a pipeline
SMART_READER_LITE
LIVE PREVIEW

1 - BUNDLE PRODUCT What do we mean. Some History A pipeline bundle - - PowerPoint PPT Presentation

S afe C lean S mart F air A nywhere 1 - BUNDLE PRODUCT What do we mean. Some History A pipeline bundle is a package of subsea well or step out field development facilities. Typically pipelines control umbilicals and manifolds. The Manifold


slide-1
SLIDE 1
slide-2
SLIDE 2

Safe Clean Smart Fair Anywhere

slide-3
SLIDE 3

What do we mean. Some History 1 - BUNDLE PRODUCT

slide-4
SLIDE 4

A pipeline bundle is a “package of subsea well or step out field development

  • facilities. Typically pipelines control umbilicals and manifolds.
slide-5
SLIDE 5
slide-6
SLIDE 6

The Manifold facility is integrated into the tow head

slide-7
SLIDE 7

The Bundle is towed to location using CDTM

slide-8
SLIDE 8

The Long Trek West

1978 1980

slide-9
SLIDE 9

Aerial View - Wester Fabrication Facility

slide-10
SLIDE 10

2 - Why CDTM - Fatigue Life

Controlled Depth Towing Method By controlling the depth at which the bundle is towed, the pipeline system is not subjected to wave and surface current

  • effects. This allows acceptable level of

fatigue within the bundle system. Tow durations of 6 days have been successfully achieved.

slide-11
SLIDE 11

Towed Production Systems - CDTM in Practice

A data highway runs the length of the bundle and allows acoustic commands made at one end of the bundle to be implemented at the other, for example for valve actuation or acoustic spool metrology. Towmaster’s real-time display of bundle shape and water depth.

slide-12
SLIDE 12
slide-13
SLIDE 13

3 – BASIC ENGINEERING PRINCIPLES

slide-14
SLIDE 14

Controlled Depth Tow Method

1000 mm Chain attachment strap 76 mm chain 5000 mm Weight of chain on seabed

  • Chains attached at

regular intervals along the bundle.

  • Ensures accurate

weight control to approximately 0.5%.

  • Weight of chain links on

seabed is submerged weight of bundle.

  • Chains can be easily cut

by ROV to trim bundle for tow if required.

slide-15
SLIDE 15

Anchor Chains

With typically 3” chain, a tow speed of 4 knots produces an uplift force of 50N/m

slide-16
SLIDE 16

4 – EVOLUTION OF THE BUNDLE PRODUCT

slide-17
SLIDE 17

BUNDLE LENGTH

The length of Bundles towed and installed by Subsea 7 is a function

  • f the fabrication site

length. Beach tie in has been performed but not recommended in North Sea. The site at Wick has been developed from 2km to 8

  • km. However, the Subsea

tie back length is not restricted. Viz Mobil Skene. 2 off 7.5km bundles with a mid point tie in structure.

slide-18
SLIDE 18

A Bundle may be as simple as a pipe in a pipe, or may contain many lines Gullfaks 01 MCP-01 Bypass bundle - 2.4km pipe-in-pipe

Why consider a Bundle?

slide-19
SLIDE 19

High Levels of Thermal Insulation Shell Gannet U=0.75W/m2K

slide-20
SLIDE 20

Typical Cross Section

5 - BUNDLE DESIGN

slide-21
SLIDE 21

BASIC PRINCIPLES

Constructability & Economics Engineering Service Requirements

slide-22
SLIDE 22

Bundle Cross Section

Heat Transfer Low Cof G

slide-23
SLIDE 23
slide-24
SLIDE 24

6 - BUNDLE C0NSTRUCTION AT WICK

slide-25
SLIDE 25

Site Layout

HOLDBACK WINCH CH7800

Seaward

WESTER OFFICE/CANTEEN FABRICATION SHOP 2

A99 to WICK A99 to JOHN O’GROATS

PIPE STORAGE AREA 3

TRACK 1 TRACK 2 TRACK 3 TRACK 4

HOLDBACK WINCH CH2600 STORES FABRICATION SHOP 1 TRACK CHICANE A99 BRIDGE PIPE STORAGE AREA 2 PIPE STORAGE AREA 1 FABRICATION SHOP 3 LAUNCHWAY HASTIGROW OFFICE/CANTEEN TRACKS 1 AND 2

Landward

slide-26
SLIDE 26
  • All materials subject to initial inspection
  • Identification numbers checked and recorded
  • Materials quarantined if required
  • Weekly checks on long term storage carried out
  • Permanent works are carefully weighed and

dimensionally checked

  • Information input into PRABOS for resultant

buoyancy calculations

Material Handling & Weight Control

slide-27
SLIDE 27

Shop Welding

slide-28
SLIDE 28

10 inches Double Jointing at Fabrication Shop

slide-29
SLIDE 29

Production Welding

Pipelines are normally 100% Tig welded. Automatic welding now is Economic & Reliable. Shop conditions allow welding

  • f exotic material.

13Cr, 22Cr, Inconel lined pipe have been used extensively in Bundles.

slide-30
SLIDE 30

Creation of Bundle Cross Section

slide-31
SLIDE 31

Pipeline Packaging

slide-32
SLIDE 32
  • Fabricated in lengths
  • f 700m to 7.5km
  • Configuration to allow

attachment of spacers

  • Polypropylene and

polyurethane field joints

  • Low density polyurethane

half shells inside sleeve pipe

Configuration & Insulation

slide-33
SLIDE 33

Tube & Cable Installation

  • Installation of:
  • Hydraulic Tubes
  • Chemical Injection Tubes
  • Power and Signal Cables
  • Utilises on site deployment

system

  • Coated or uncoated
  • Various material types
  • Final pre-tensioning if

required

slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36

Semi automatic and Automatic processes are normally used for carrier pipe welding

slide-37
SLIDE 37
slide-38
SLIDE 38

Inner Bundle assembled showing spacer pitch Carrier pipe sleeved, ready for closing welds

slide-39
SLIDE 39

7 - T0WHEADS &TRANSPORTATION

slide-40
SLIDE 40

Tow Heads

Bouyancy Force in shallow water

slide-41
SLIDE 41

Tow Heads

Integrated buoyancy 8 Slot Manifold

slide-42
SLIDE 42

Tow Heads

Offloading Tow Head in Wick Harbour

slide-43
SLIDE 43

Tow Heads

There are however designs to avoid

slide-44
SLIDE 44

Tow Heads

Mud Mats & Detachable Buoyancy

slide-45
SLIDE 45

Tow Heads

Integrated buoyancy can be flooded or grouted to create gravity based stability. Obviating piling means control modules can be pre-installed and commissioned on site

slide-46
SLIDE 46

Tow Heads

Oil & Gas Development presents challenges!

slide-47
SLIDE 47

Tow Heads

Planning and preparation have allowed this to be performed more than 40 times.

slide-48
SLIDE 48

Towhead Delivery/Tie-In

  • Large structures by sea to Wick Harbour
  • Smaller towheads by road
  • Final towhead alignment and bundle tie-in
slide-49
SLIDE 49

8 - BUNDLES LAUNCH

slide-50
SLIDE 50

Launch way transition from site to sea

slide-51
SLIDE 51

Launch

slide-52
SLIDE 52
slide-53
SLIDE 53
slide-54
SLIDE 54
slide-55
SLIDE 55
slide-56
SLIDE 56

9 – TYPICAL TOW FLEET

slide-57
SLIDE 57

Tow Fleet

slide-58
SLIDE 58
  • Currently specialised pipelay vessels have full schedules
  • Bundle installation is not tied to a specific vessel

Lead Tug Trail Tug Guard Vessel Flooding\Ballast Vessel

Not Vessel Specific

slide-59
SLIDE 59

10 – SPECIFIC ADVANTAGE of the BUNDLE PIPELINE SYSTEM

slide-60
SLIDE 60

Removes need for separate CP of each pipe

Carrier pipe anodes protect the whole pipeline system. Inside bundle there is a biocide protected oxygen free environment. No coatings, no corrosion. Within pipe-in-pipe systems, the pipeline material and insulation is in a dry air environment. CP design for materials susceptible to damage by CP system e.g. 13% Cr is much simpler with less design risk. Anode procurement and installation time minimised.

slide-61
SLIDE 61

Subsea 7 has experience of a wide range of materials optimised for a wide range of fluids

Subsea 7 has installed bundles with the following pipeline materials Carbon steel ( HFI and Seamless) 22% Cr Duplex stainless steel 25%Cr Super duplex Stainless Steels 13% Cr Steel 316L lined pipes 904L Lined pipes Alloy 825 Lined pipes Plastic liners Lined pipes offer the cheapest solution to corrosive field conditions, and can be installed by CDTM without risk of internal buckling

slide-62
SLIDE 62

System Fully Commissioned Onshore

Prior to launch, all electrical and hydraulic interfaces can be tested Full Site Integration testing with Christmas tree can be undertaken All Manifold valves can be installed and tested prior to launch Multiphase Flow Meters can be installed prior to launch if towhead/manifold is not piled Hydrotesting is completed onshore with only leak testing required offshore Structures up to 380 Tonnes have been installed, including SCM’s, Chokes and MFM’s.

slide-63
SLIDE 63

11 – BUNDLE APPLICATIONS

slide-64
SLIDE 64

RISER CAISSON

slide-65
SLIDE 65

Chevron Alba Caisson. Obviates the need for heavy lift vessel

slide-66
SLIDE 66
slide-67
SLIDE 67

Kerr Mcgee Leadon Field

No trenching. On botton stability achieved by flooding the carrier pipe

Infield construction. Schedule very short. Very narrow pipeline. Corridor suits turret moored FPSO. Mid point riser structure for both well sites

slide-68
SLIDE 68

12 – S7 BUNDLE INSTALLATIONS

slide-69
SLIDE 69

Åsgard Heidrun

Norway Norway

Osprey Cormorant Claymore Frigg East Murchison Piper Saltire Thelma Cyrus Scapa Alba Gannet Embla Dan

Denmark Denmark Wick Wick

Gulfaks Bruce

Scotland Scotland

Buckland Keith Leadon Skene Sycamore

Bundle Locations