Orange County Public Schools

Site 205-K8-SW-6 40% Construction Community Meeting September 25, 2017

WINNER

Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ 1

slide-2
SLIDE 2

Orange County Public Schools Orange County Public Schools Site 205-K8-SW-6 40% Construction Meeting Agenda

September 25, 2017 – 6:00pm – Kaley-Lake Como Elementary Cafeteria

  • Welcome – School Board Member Nancy Robbinson
  • Introductions
  • Project Update – Architect: Harvard Jolly Architects

Construction Manager: Williams Company

  • Questions and Answers
  • Adjournment

2

slide-3
SLIDE 3

Orange County Public Schools

N

Lake Como ES Aerial 3

slide-4
SLIDE 4

Orange County Public Schools

N

Master Site Plan

Project Data

Capacity 1,335 Student Stations Building Area 161,762 Gross SF Parking Provided 136 Spaces Car Queuing Provided 132 Cars Site Area +/- 12 Acre

Gym Media Center Admin Multi Purpose Music Art CEP Kitchen Bus Loop Parent Pick Up/Drop Off Soccer Field/6 Lane Track 3-Story Classroom Bldg Hardcourt Lockers Future Portables Stormwater Exfiltration Beneath Field Baseball Field Tot Youth Courtyard

Gore St Bumby Ave

4

15 Ft Buffer 15 Ft Buffer

slide-5
SLIDE 5

Orange County Public Schools

5

View from Gore St

slide-6
SLIDE 6

Orange County Public Schools

6

Bird’s-Eye from Gore Street

slide-7
SLIDE 7

Orange County Public Schools

7

Bird’s-Eye from Bumby Ave

slide-8
SLIDE 8

Orange County Public Schools

Construction Update and Milestones

  • Notice to Proceed (NTP) was issued February 7, 2017.
  • Tilt wall panels were completed on June 30, 2017.
  • Structural Steel Erection was completed on July 24, 2017.
  • Roofing work has started and will be completed by October 13, 2017
  • Window installation started and will be completed by September 30, 2017
  • Exterior painting to start mid-October.
  • Interior work is in progress.
  • Project will be 40% complete as of September 30, 2017.
  • Project remains on schedule for Substantial Completion on May 14, 2018.

8

slide-9
SLIDE 9

Orange County Public Schools

Aerial Photo- Late January 2017

9

slide-10
SLIDE 10

Orange County Public Schools

Aerial Photo- Late April 2017

10

slide-11
SLIDE 11

Orange County Public Schools

Aerial Photo- Late May 2017

11

slide-12
SLIDE 12

Orange County Public Schools

Aerial Photo- Late July 2017

12

slide-13
SLIDE 13

Orange County Public Schools

Aerial Photo- Late August 2017

13

slide-14
SLIDE 14

Orange County Public Schools

Aerial Photo- Late September 2017

14

slide-15
SLIDE 15

Orange County Public Schools

Slab On Grade Pour Tilt Panel Rebar

15

slide-16
SLIDE 16

Orange County Public Schools

Tilt Panel Erection Steel Erection 16

slide-17
SLIDE 17

Orange County Public Schools

Lightweight Installation Roofing Installation 17

slide-18
SLIDE 18

Orange County Public Schools

QUESTIONS?