the development consent process
play

The Development Consent Process Information event about the - PowerPoint PPT Presentation

The Development Consent Process Information event about the application process for Communities The Development Consent Process DEVELOPER PI NS SofS Decision Acceptance Exam ination Pre-application Pre-examination Recom m endation 1 Year


  1. The Development Consent Process Information event about the application process for Communities

  2. The Development Consent Process DEVELOPER PI NS SofS Decision Acceptance Exam ination Pre-application Pre-examination Recom m endation 1 Year + 1 Year Thames Tideway Tunnel – How to take part in the application process

  3. 3 Key messages 1 .W e are im partial 2 .You need to register to take part in the exam ination 3 .The Exam ining Authority w ill be appointed shortly Thames Tideway Tunnel – How to take part in the application process

  4. We are impartial • The Planning Inspectorate (PINS) is an agency of Department of Communities and Local Government (DCLG) • PINS project team provides advice to communities, applicants and others about how to take part in the process and supports the decision makers (Examining Authority) in the running of the examination • Examining Authority Panel members are vetted for conflicts of interest before they are appointed Thames Tideway Tunnel – How to take part in the application process

  5. You need to register to take part in the examination • Register a relevant representation to become an “Interested Party” – special status • Easiest way to register is to complete a form online via our website, on the Thames Tideway Tunnel project page. • Your relevant representation can be a list of your main points – you can provide a more detailed representation at a later date if you want to. Thames Tideway Tunnel – How to take part in the application process

  6. The examining authority will be appointed shortly • Panel of up to 5 Examining Inspectors will be appointed after the close of the registration period – known as the “Panel”. • Examining Inspectors are appointed according to their expertise and availability – interested parties will be informed directly about their appointment • All communication with the Panel must be in public, either in writing or at hearings Thames Tideway Tunnel – How to take part in the application process

  7. Our project page Press this button to register Thames Tideway Tunnel – How to take part in the application process

  8. Relevant Representation Form • 1 form per named individual – can’t register as husband and wife or as a family • Can register as a group of residents • Interest in land • Mailing preference • You must provide a summary of your views (recommended no more than 500 words) • If posting send the completed form to us (NOT the Council) by the deadline Thames Tideway Tunnel – How to take part in the application process

  9. Whose views are you representing? • You can register both as an individual and on behalf of another person or interest group. • If you are making your views on behalf of an interest group you may be asked to provide information about its membership and how it is constituted. • The Examining authority will ask you in what capacity you are presenting written and verbal submissions – you need to be clear about this. Thames Tideway Tunnel – How to take part in the application process

  10. Why do I need to fill in a form? • Required in legislation • Provides us with all the information we need to be able to administer the application process • Allows the Panel members to make an initial assessment of what they consider the principal issues to be. Thames Tideway Tunnel – How to take part in the application process

  11. How will you use my personal details? • Your contact details w ill not be published online , nor your signature (avoid using your signature). Be careful about mentioning the personal details of 3 rd parties • such as neighbours in any representations you make. • This is a public process and you should be mindful that what you write in any representation will be published on our website and made available in paper form at designated “deposit” locations. Thames Tideway Tunnel – How to take part in the application process

  12. What if I don’t fill in the form? • Your participation in the examination will be at the Panel’s discretion – written representations and hearings • You will not be invited to the Preliminary Meeting • You will not be informed directly about the examination timetable or any procedural decisions made by the Panel during the examination Thames Tideway Tunnel – How to take part in the application process

  13. I don’t have access to email or internet • Email / internet is quicker, more convenient and easier for you and us • Paper relevant representation forms are available on request by calling our helpline (0303 444 5000) • Paper forms will be allocated a reference number specific to you - your name and address details will be filled in before the form is sent to you. • Paper copies of all the application documents and representations made at the examination will be made available at the deposit locations. Thames Tideway Tunnel – How to take part in the application process

  14. Effective ways to participate • Consider forming a group with neighbours or others with the same views as you. Nominate a spokesperson(s). • It is not necessary to read the whole application – site specific sections / topics • Read the examination timetable and keep up to date with the progress of the examination regularly online or by visiting one of the deposit locations. • Keep written submissions concise and to the point. • Stick to any agenda issued by the Panel in advance of any hearings – the Panel will control the proceedings. • Hearings are intended to supplement the written process, not an opportunity to make speeches. Thames Tideway Tunnel – How to take part in the application process

  15. What happens during the examination? • Interested Parties can make a written representation or rely on their relevant representation. • Interested Parties can comment on others’ representations. • Interested Parties can respond to written questions posed by the Panel. • Interested Parties can request that an Open Floor Hearing is held. • Interested Parties can attend and speak at Open Floor or Issue Specific Hearings Thames Tideway Tunnel – How to take part in the application process

  16. Further advice and information Helpline: 0303 444 5000 Project em ail address: thamestunnel@infrastructure.gsi.gov.uk Advice Notes and inform ation available on our w eb page ( search “Planning I nspectorate Tham es Tunnel”) : http: / / infrastructure.planningportal.gov.uk/ thames (set it as a “favourite”) Thames Tideway Tunnel – How to take part in the application process

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend