The Australian Energy Regulator TasNetworks electricity - - PowerPoint PPT Presentation

the australian energy regulator
SMART_READER_LITE
LIVE PREVIEW

The Australian Energy Regulator TasNetworks electricity - - PowerPoint PPT Presentation

The Australian Energy Regulator TasNetworks electricity distribution regulatory proposal and tariff structure statement (TSS) 2017-19 Public Forum 17 March 2016 Agenda MORNING SESSION Public forum on TasNetworks regulatory


slide-1
SLIDE 1

The Australian Energy Regulator

TasNetworks’ electricity distribution regulatory proposal and tariff structure statement (TSS) 2017-19 Public Forum 17 March 2016

slide-2
SLIDE 2

Agenda

MORNING SESSION Public forum on TasNetworks’ regulatory

proposal

Noon – 12:30pm – Lunch AFTERNOON SESSION Public forum on TasNetworks’ Tariff

Structure Statement (TSS)

slide-3
SLIDE 3

Morning session

TasNetworks’ presentation of its

distribution regulatory proposal

Consumer Challenge Panel (CCP)

presentation of initial views

AER presentation of its issues paper Q&A Next steps

slide-4
SLIDE 4

Tribunal decision

On 26 February 2016 the Australian

Competition Tribunal handed down its decision on the limited merits review of the AER’s April and May 2015 ACT and NSW decisions

We are considering the decision carefully It is still too early to say what the impact

  • f the Tribunal decisions will be

We will consult with stakeholders once we

have a better idea of the way forward

slide-5
SLIDE 5

Presentation - TasNetworks’ presentation of its regulatory proposal

slide-6
SLIDE 6

Presentation - CCP presentation of its initial views

slide-7
SLIDE 7

Presentation - AER issues paper

slide-8
SLIDE 8

Key points

TasNetworks submitted its 2017-19 regulatory

proposal on 29 January 2016

Following an AEMC rule change, this is a two-

year proposal that aligns TasNetworks’ distribution and transmission timelines from 1 July 2019

This reset takes place under the new 15 month

determination assessment timetable

Final decision due no later than 30 April 2017

slide-9
SLIDE 9

TasNetworks reset timeline

Step Date

TasNetworks submitted its regulatory proposal to AER Jan 2016 AER published issues paper March 2016 AER to hold public forum on issues paper 17 March 2016 Submissions on regulatory proposal close 28 April 2016 AER to publish draft determination Sept 2016* AER to hold public forum on draft determination TBA TasNetworks to submit revised proposal to AER TBA Submissions on revised proposal and draft determination close TBA AER to publish final determination No later than 30 April 2017

slide-10
SLIDE 10

Key points

TasNetworks has proposed decreases in its

revenue requirement from the current period

TasNetworks has proposed a rate of return of

6.04 percent, consistent with the AER’s rate of return guideline

However, TasNetworks has departed from the

rate of return guideline with a value of 0.25 for gamma

TasNetworks has indicated that the Tribunal

decision will influence its revised proposal

slide-11
SLIDE 11

TasNetworks - Proposed revenue requirement

Source: AER analysis

slide-12
SLIDE 12

TasNetworks - capex

Source: AER Analysis

slide-13
SLIDE 13

TasNetworks - capex

Capex in the current regulatory period is five per

cent lower than the AER allowance

Costs associated with bushfire recovery and full-

retail contestability not passed through

The 2017-22 capex forecast is a 6.6 percent

lower than current expenditure

slide-14
SLIDE 14

TasNetworks – capex key drivers

Source: Source: TasNetworks, Regulatory proposal, January 2016, pp. 11, 72

slide-15
SLIDE 15

TasNetworks - opex

Source: TasNetworks, Regulatory proposal RIN response, January 2016; AER, Final decision PTRM for Aurora 2012–17; TasNetworks (D), Economic Benchmarking RIN response 2014–15; TasNetworks (D), Economic Benchmarking RIN response 2013–14; Aurora, Economic Benchmarking RIN response 2006–13; AER analysis.

20 40 60 80 100 120 $Million June 2017 Reported Estimated AER approved forecast Proposed

slide-16
SLIDE 16

TasNetworks - opex

TasNetworks submits that its forecast opex is 13.1

per cent lower than average opex for the current period

Forecast opex built on efficiencies achieved since the

Transend/Aurora merger

TasNetworks submits that the AER’s benchmarking

analysis provides strong evidence that the base year

  • pex is efficient

Step changes are one of the key opex drivers

slide-17
SLIDE 17

TasNetworks Change in unsmoothed revenue

Source: AER Analysis

slide-18
SLIDE 18

Questions?

slide-19
SLIDE 19

Next steps

Submissions due by 28 April 2016 Draft decision expected in around

September 2016

Final decision due by 30 April 2017 AER contact:

  • TASelectricity2017@aer.gov.au