TAB 01 Date of Council Meeting: April 24, 2017 TOWN OF LEESBURG - - PDF document

tab 01
SMART_READER_LITE
LIVE PREVIEW

TAB 01 Date of Council Meeting: April 24, 2017 TOWN OF LEESBURG - - PDF document

TAB 01 Date of Council Meeting: April 24, 2017 TOWN OF LEESBURG TOWN COUNCIL WORK SESSION Subject: East Market Street (Route 7) / Battlefield Parkway Interchange Staff Contact : Tom Brandon, Capital Projects Manager, Public Works & Capital


slide-1
SLIDE 1

Date of Council Meeting: April 24, 2017 TOWN OF LEESBURG TOWN COUNCIL WORK SESSION Subject: East Market Street (Route 7) / Battlefield Parkway Interchange Staff Contact: Tom Brandon, Capital Projects Manager, Public Works & Capital Projects Calvin Grow, Transportation Engineer, Public Works & Capital Projects Renée LaFollette, Director, Public Works & Capital Projects Council Action Requested: Information only. Staff Recommendation: Information only. Commission Recommendation: Not applicable. Fiscal Impact: A new grade-separated interchange between East Market Street and Battlefield Parkway is estimated to cost $58 million. This order-of-magnitude estimate was prepared based on comparable interchanges in the area. As part of the ongoing studies to select a preferred alternative for the interchange, the estimated cost will be refined. However, based on work performed to date, the estimated project cost appears to be in the right order of magnitude. To date the Northern Virginia Transportation Authority (NVTA) has awarded a total of $33 million to the project. This existing funding is sufficient for preparation or the required Interchange Justification Report, preparation of an environmental document, design, right-of-way acquisition, relocation of utilities, and a portion of the construction. The remainder of the funding has not been secured. The Town will continue to apply for major project funding sources for full funding of the project, including NVTA regional funding and Virginia Department of Transportation (VDOT) Smart Scale. Other potential smaller funding programs from VDOT, NVTA and other sources will also be evaluated. Work Plan Impact: None. This project is included in the Department of Public Works and Capital Projects work plan. The studies, design and construction of the interchange are being administered by the Virginia Department of Transportation, in cooperation with the Town of Leesburg and Loudoun County. Executive Summary: The initial stages are underway for the development of a grade-separated interchange to replace the signalized East Market Street (Route 7) / Battlefield Parkway intersection. The project will also include modification of the existing Cardinal Park Drive intersection with East Market Street. As part of the preliminary design and the development of an Interchange Justification Report, various alternative interchange configurations have been developed and are being evaluated. This initial work on the project, including the preliminary design, traffic studies, Interchange Justification Report, and environmental document is scheduled to be completed in spring 2018. Scheduling of final design and construction of the interchange is dependent on future funding.

TAB 01

slide-2
SLIDE 2

East Market Street (Route 7) / Battlefield Parkway Interchange April 24, 2017 Page 2 Background: East Market Street (Route 7) is one of the most congested corridors in Leesburg. This highway carries inter-state and intra-state traffic from the west and south to the employment corridors and activity centers in the Dulles area and Washington, DC metropolitan region. Current weekday traffic on East Market Street is estimated to be 85,000 vehicles per day and current traffic on Battlefield Parkway is estimated to be 15,000 vehicles per day. During the afternoon peak hour, approximately 8,000 vehicles pass through the Battlefield Parkway intersection resulting in routine

  • congestion. Also, the existing East Market Street signalized intersections with Battlefield Parkway

and Cardinal Park Drive have some of the highest accident rates in Loudoun County In addition to motorized vehicle issues, East Market Street acts as a barrier separating residential areas from retail and business areas. Project Scope In 2016, the Town entered into an agreement with the Northern Virginia Transportation Authority (NVTA) for funding of preliminary studies and design for the interchange. The Town also executed a separate agreement with the Virginia Department of Transportation (VDOT) in which they are administering the work on the project. The purpose of the project is to:

  • Reduce recurring congestion at the Route 7 and Battlefield Parkway intersection
  • Improve safety
  • Improve accessibility for pedestrian and bicycle traffic crossing Route 7

One of the required steps to construct a new highway interchange is to develop an Interchange Justification Report (IJR). The purpose of the IJR is to provide a reliable forecast of future traffic conditions, develop and evaluate alternatives, and select an alternative that best meets the project needs. Alternatives Four alternative interchange configurations for Battlefield Parkway, and four optional treatments of the Cardinal Park Drive intersection have been developed for the project (drawings included in the VDOT presentation attached): The alternatives that have been developed for the Battlefield interchange are:

  • Alternate 1: Hybrid Diamond Interchange with a cloverleaf loop ramp in the northeast

quadrant – Variations of this type of interchange are found at several locations along Route 7 east of Leesburg.

  • Alternate 2: Compressed Urban Diamond – This type of interchange is at the intersection of

Route 7 and Fairfax County Parkway near Dranesville.

  • Alternate 3: Diverging Diamond Interchange – This type of interchange configuration was

recently constructed at the I-66 / Route 15 intersection in Haymarket.

  • Alternate 4: Single Point Urban Interchange- An example of this type of interchange

configuration is at the Route 7 / Loudoun County Parkway intersection in Ashburn.

slide-3
SLIDE 3

East Market Street (Route 7) / Battlefield Parkway Interchange April 24, 2017 Page 3 Cardinal Park

  • Option A: Green T – This type of intersection allows the westbound through Route 7 traffic

to continue freeflow without a traffic signal. Westbound left turn to Cardinal Park Drive would be controlled by a signal. This is similar to the intersection configuration on the Bypass at Fort Evans Road. The left turning traffic from Cardinal Park Drive is separated from the westbound Route 7 traffic by a barrier, and would not have direct access to the Bypass.

  • Option B: Right-In/Right-Out/Left-In – This type of intersection would not allow left turns

from Cardinal Park Drive to westbound Route 7. Traffic wishing to go westbound would use Trailview Boulevard/Russell Branch Parkway and go through the new interchange. All other movements at the intersection would be allowed and would be contolled by a signal, except for Route 7 westbound through traffic, which would be free flowing.

  • Option C: Right-In/Right-Out – This type of intersection would allow traffic to leave the

Cardinal Park area and travel eastbound, but would not allow traffic to turn left and travel

  • westbound. Westbound Route 7 traffic would not have access into Cardinal Park.
  • Option D: Right-In Only – With this type of intersection, all traffic leaving Cardinal Park

would use Trailview Boulevard/Russell Branch Parkway to the new interchange at Battlefield

  • Parkway. Also, westbound Route 7 traffic would use the Battlefield Parkway interchange and

Russell Branch Parkway to access the Cardinal Park area. Public Outreach The development and approval of the IJR will include significant outreach to impacted stakeholders. Information about the project is available on the Town’s website, and on a project web page maintained by VDOT, which is located

  • n

their website at http://www.virginiadot.org/projects/northernvirginia/rt_7_at_battlefield_pkwy.asp. VDOT will begin meeting with individual business and property owners later this spring. A formal Public Hearing will be held after completion of the draft IJR. This hearing is tentatively scheduled for 1st Quarter of Calendar Year 2018. Schedule Below is the tentative schedule for approval of the IJR and the project design.

  • Spring 2017: Meetings with business owners, Public Information Meeting, and identification
  • f a preferred alternative.
  • Summer 2017: Complete preliminary design
  • Fall 2017: Conditional IJR approval
  • Early 2018: Public Hearing, additional briefings to Town Council and Board of Supervisors
  • Early 2018: Town and County endorsements
  • Spring 2018: Design approval

Final design, right-of-way acquisition, utility relocation and construction will be scheduled after full project funding has been finalized. Attachment: VDOT Presentation

slide-4
SLIDE 4

Route 7 (East Market Street) Interchange at Battlefield Parkway Town of Leesburg Project No: 0007-253-109 UPC 106573

April 2017 William Dunn, PE VDOT Project Manager John Maddox, PE Consultant Project Manager

slide-5
SLIDE 5

Project Limits

2

slide-6
SLIDE 6

Project Purpose and Scope

Project Purpose

  • Improve safety and pedestrian/vehicle flow by building a grade-separated interchange which will allow

Route 7 to become a limited-access highway through the Town of Leesburg Corporate Limits

Ongoing Efforts

  • Traffic Analysis
  • Interchange Alternatives Screening
  • Interchange Justification Report (IJR)
  • NEPA Environmental Studies
  • Preliminary Design

3

Next Steps

  • Design Public Hearing
  • Design Approval

E MARKET ST STATION DR CARDINAL PARK DR

slide-7
SLIDE 7

Route 7 at Battlefield Pkwy Interchange Alternatives

  • Alternative 1 – Single Loop Hybrid Interchange
  • Alternative 2 – Compressed Diamond Interchange
  • Alternative 3 – Diverging Diamond Interchange (DDI)
  • Alternative 4 – Single Point Urban Interchange (SPUI)

Note: Levels of Service (LOS) on subsequent slides reflect Right-In/Right-Out at Cardinal Park Drive (Option C)

4

slide-8
SLIDE 8

Advantages

  • LOS C or better at ramp traffic signals
  • Minimizes number of lanes on bridge over Route 7
  • Desirable spacing between Ramps A/D and Russell Branch Pkwy
  • No impact to transmission utility poles
  • Loop reduces weaving volume along WB Route 7
  • Improved pedestrian and bicycle accommodations

5

Alternative 1 Single Loop Hybrid Interchange

Disadvantages

  • Greater right of way impacts

compared to Alts 2 and 4

Ramp B Loop Ramp C Ramp A Ramp D

slide-9
SLIDE 9

Alternative 2 Compressed Diamond Interchange

Advantages

  • Less right of way impacts compared to Alts 1 and 3
  • No impact to transmission utility poles
  • Desirable spacing between Ramps A/D and Russell

Branch Pkwy

  • Improved pedestrian and bicycle accommodations

Disadvantages

  • LOS E in PM peak at Ramp B/C traffic signal
  • 10-lane bridge over Route 7
  • Increased weaving volume along WB Route 7 compared to Alt 1

Ramp B Ramp A Ramp C Ramp D

6

slide-10
SLIDE 10

Disadvantages

  • Transmission utility poles will be located inside of Ramps A and D
  • Impacts undeveloped portions of Leegate and Lowe’s developments
  • Inadequate spacing between Ramps A/D and Russell Branch Pkwy
  • Pedestrian and bicycle accommodations less desirable
  • Increased weaving volume along WB Route 7 compared to Alt 1

7

Alternative 3 Diverging Diamond Interchange (DDI)

Advantages

  • LOS C or better for ramp traffic signals
  • Minimizes number of lanes on bridge over

Route 7

Ramp A Ramp B Ramp D Ramp C

slide-11
SLIDE 11

Disadvantages

  • Requires an 8-lane and a more complex and expensive bridge
  • ver Route 7
  • Pedestrian and bicycle accommodations less desirable
  • Increased weaving volume along WB Route 7 compared to Alt 1
  • Higher construction cost

8

Alternative 4 Single Point Urban Interchange (SPUI)

Advantages

  • Less right of way impacts compared to Alts 1 and 3
  • Maximizes distance between interchange ramps and

Russell Branch Pkwy

  • No impact to transmission utility poles
  • LOS D at interchange ramp traffic signal

Ramp B Ramp C Ramp D Ramp A

slide-12
SLIDE 12

Route 7 at Battlefield Pkwy Alternatives Comparison

Criteria

No Build Alt 1: Single Loop Hybrid Alt 2: Compressed Diamond Alt 3: DDI Alt 4: SPUI

Intersection LOS

  • LOS F

LOS C

LOS E

LOS C

LOS D

Distance between interchange ramps and Russell Branch Pkwy

N/A ○ ○

  • Impacts to transmission lines
  • Amount of weaving along WB Route 7

N/A ○ ○ ○ ○

Pedestrian and bicycle accommodations

○ ○ ○

Size/complexity of bridge

N/A ○

7 lanes

10 lanes

  • 6 lanes
  • 8 lanes

Right of way impacts

N/A ○ ○

Construction cost

N/A ○

$38.7 M

$39.1 M

$39.3 M

$40.6 M

9

Legend

○ ○

  • Excellent

Favorable Fair Unfavorable Poor

slide-13
SLIDE 13

Route 7 at Cardinal Park Drive

  • Option A: Green T

− No NB left-turn access to the Bypass

  • Option B: Left In/Right In/Right Out
  • Option C: Right In/Right Out
  • Option D: Right In

10

slide-14
SLIDE 14

Route 7 Eastbound Route 7 Westbound Cardinal Park Drive

Right Turn Lane Concrete Channelizing Island Concrete Median Concrete Median

Route 7 at Cardinal Park Drive

Option A: Green T

Advantages

  • Eliminates the WB Route 7 signal
  • Minimizes impact to Cardinal Park Drive traffic
  • Reduces diversion to Battlefield Pkwy and Russell

Branch Pkwy

  • Prevents weaving from Battlefield Pkwy to Cardinal

Park Drive

Disadvantages

  • EB Route 7 morning queues extend past

Bypass on-ramp

  • Poor LOS for signalized movements
  • Signal remains on EB Route 7
  • EB rear end crash potential
  • No access to Bypass from Cardinal Park Drive
slide-15
SLIDE 15

Route 7 at Cardinal Park Drive

Option A: Green T - Diverted Movements

12

EB queues back up beyond Bypass ramp in the AM

slide-16
SLIDE 16

Route 7 Eastbound Route 7 Westbound Cardinal Park Drive

Right Turn Lane Grass Median

Route 7 at Cardinal Park Drive

Option B: Left In/Right In/Right Out

Concrete Island

Advantages

  • Eliminates the WB Route 7 signal
  • Allows left turns to Cardinal Park Drive
  • Reduces diversion to Battlefield Pkwy and Russell

Branch Pkwy

  • Prevents weaving from Battlefield Pkwy to

Cardinal Park Drive

Disadvantages

  • EB Route 7 morning queues extend past

Bypass on-ramp

  • Poor LOS for signalized movements
  • Signal remains on EB Route 7
  • EB rear end crash potential
  • Prohibits left turns from Cardinal Park Drive

Concrete Channelizing Island Concrete Median

slide-17
SLIDE 17

Route 7 at Cardinal Park Drive

Option B: Left In/Right In/Right Out - Diverted Movements

14

EB queues back up beyond Bypass ramp in the AM

slide-18
SLIDE 18

Route 7 Eastbound Route 7 Westbound Cardinal Park Drive

Right Turn Lane Concrete Island Grass Median Grass Median

Route 7 at Cardinal Park Drive

Option C: Right In/Right Out

Advantages

  • Eliminates all signals on Route 7
  • Reduces the potential for rear end crashes
  • EB Route 7 queues do not extend to Bypass
  • Prevents weaving from Battlefield Pkwy to Cardinal Park

Drive

Disadvantages

  • Poor LOS and long delays for right turn

from Cardinal Park Drive

  • Potential for angle crashes
  • Diverts Cardinal Park Drive left turns to

Russell Branch Pkwy and Battlefield Pkwy

slide-19
SLIDE 19

Route 7 at Cardinal Park Drive

Option C: Right In/Right Out - Diverted Movements

16

slide-20
SLIDE 20

Route 7 Eastbound Route 7 Westbound Cardinal Park Drive

Right Turn Lane Grass Median Grass Median

Route 7 at Cardinal Park Drive

Option D: Right In

Remove Existing Turn Lane

Disadvantages

  • Diverts Cardinal Park Drive traffic to Russell

Branch Pkwy and Battlefield Pkwy impacting LOS

Advantages

  • Eliminates all signals on Route 7
  • Reduces the potential for rear end crashes
  • EB Route 7 morning queues do not extend to Bypass
  • No LOS deficiencies
  • Prevents weaving from Battlefield Pkwy to Cardinal Park

Drive

slide-21
SLIDE 21

Route 7 at Cardinal Park Drive

Option D: Right In - Diverted Movements

18

slide-22
SLIDE 22

Route 7 at Cardinal Park Drive Options Comparison

Criteria

No Build Option A: Green T Option B: Left In/Right In/Right Out Option C: Right In/ Right Out Option D: Right In

Removal of signals along Route 7

  • Minimizes the potential for EB queues

to extend to the Bypass

  • Intersection LOS and delays

○ ○

  • Reduces the potential for rear end

and angle crashes along Route 7

○ ○ ○

Accommodates existing traffic at Cardinal Park Drive

○ ○

  • 19

Legend

○ ○

  • Excellent

Favorable Fair Unfavorable Poor

slide-23
SLIDE 23

20

Project Funding

Construction Phase Budget Preliminary Engineering $4 million Right-of-Way & Utilities $9 million Construction $45 million TOTAL $58 million Funding Budget NVTA Funding to Date $33 million Additional Funding Needed $25 million

slide-24
SLIDE 24

21

Project Schedule / Next Steps

Milestone Date Public Information Meeting Spring 2017 Meet with Business Owners Spring 2017 Identify Preferred Alternative Spring 2017 Preliminary Design Submission Summer 2017 Conditional IJR Approval Fall 2017 D-B RFQ November 2017 Public Hearing Early 2018 Briefings to Town Council and County Board Early 2018 Town and County Endorsements Early 2018 D-B RFP May 2018 Design Approval Spring 2018

slide-25
SLIDE 25

22

Questions?

slide-26
SLIDE 26

Thank you

23

William Dunn, PE VDOT Project Manager 703-259-2950 William.Dunn@VDOT.Virginia.gov Contact Information: James Zeller, PE VDOT Project Development Engineer – Loudoun County 703-259-3220 James.Zeller@VDOT.Virginia.gov