WOOD FRAME SOFT-STORY BUILDING RETROFIT PROGRAM City of Los Angeles Department of Building and Safety WOOD FRAME SOFT STORY BUILDINGS Wood frame buildings with the following criteria : Built before 1980 Consists of 2 or more stories


slide-1
SLIDE 1

WOOD FRAME SOFT-STORY BUILDING RETROFIT PROGRAM

City of Los Angeles Department of Building and Safety

slide-2
SLIDE 2

WOOD FRAME SOFT STORY BUILDINGS

 Wood frame buildings with the following criteria:

  • Built before 1980
  • Consists of 2 or more stories
  • Residential with 4 or more units and/or commercial
slide-3
SLIDE 3

TUCK-UNDER PARKING

slide-4
SLIDE 4

GARAGE DOORS/STEEL GATES CONSIDERED AS OPENINGS

slide-5
SLIDE 5

COMMERCIAL STORE FRONT

slide-6
SLIDE 6

WHY RETROFIT?

Without proper strengthening, the soft-story floor becomes weak and may suffer structural damage or complete failure during and/or after an earthquake.

slide-7
SLIDE 7

SOLUTION! ELIMINATE SOFT, WEAK, OR OPEN WALL LINE

SHEAR WALLS MOMENT FRAME

Concrete walls or masonry walls are prohibited.

slide-8
SLIDE 8

COMPILE A LIST OF WOOD FRAME BUILDINGS BUILT BEFORE 1980

Obtain information from:

  • Housing Department
  • Tax Assessors
  • Building Records

STEP 1

slide-9
SLIDE 9

USE GOOGLE MAPS TO PERFORM ONLINE SURVEY

30,000 surveyed

6,000 classified as “No” 24,000 classified as “Possible”

STEP 2

slide-10
SLIDE 10

CONDUCT SITE VISIT EVALUATION

24,000 buildings classified

as “Possible soft-story” were evaluated and surveyed.

STEP 3

slide-11
SLIDE 11

SURVEY POSSIBLE SOFT-STORY BUILDINGS

slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14

COMPLIE FINAL LIST OF SOFT-STORY WOOD BUILDINGS

 There are 13,500 currently

identified as wood soft-story buildings in the City of Los Angeles

 78% are 2 stories or more  22% are 3 stories or more  99% are apartments/condos

STEP 4

slide-15
SLIDE 15

ESTABLISH RETROFIT CRITERIA

Strengthen soft, weak or open wall line ONLY :

 The Design Base Shear

  • 75% of current requirement under ASCE 7

 Story Drift Limitations

  • Not to exceed 0.025 times the story height

Exception Buildings greater than 2 stories with horizontal structural irregularities shall meet the additional

requirements under ASCE 7, for the entire story with weak or open wall lines.

STEP 5

slide-16
SLIDE 16

ESTABLISH ORDINANCE

STEP 6

slide-17
SLIDE 17

NOTIFY BUILDING OWNERS

 Where to obtain help  Ordinance description  Timeline for compliance  Webpage for guidance STEP 7

slide-18
SLIDE 18

ISSUE TECHNICAL RETROFIT BULLETIN FOR CONSTRUCTION PROFESSIONALS

 Structural Design

  • Prescriptive
  • Alternative Methods

 Permitting Process

  • Required submittal package

STEP 8

slide-19
SLIDE 19

SEND ORDER TO COMPLY

 Compliance requirements  Compliance timeline  Appeal procedures STEP 9

slide-20
SLIDE 20

TIME LIMIT FOR RETROFIT

4 years

From the date of the Order to Comply

2 years

From the date of the Order to Comply

1 year

From the date of the Order to Comply

Submit

  • 1. Proof of previous

retrofit or,

  • 2. Retrofit Plans

and design or,

  • 3. Plans for

demolition Obtain permit to retrofit or demolish Complete Construction

slide-21
SLIDE 21

MAKE THE PROGRAM COST RECOVERY

TO SUPPORT A SPECIAL PLAN CHECK AND INSPECTION TEAM

13,500 projects at

$665 of average plan check and permit fees,

$ 9 million total revenue for the 4-year program

$2.25 million per year to support a special plan check and inspection team Cost will be recovered.

STEP 10

slide-22
SLIDE 22

QUESTIONS AND COMMENTS

For further information, please contact Catherine Nuezca Gaba

Chief of Wood Frame Soft-story Program

(213) 482-0435 or Catherine.NuezcaGaba@lacity.org