REAL ESTATE
- STAFF INTRODUCTIONS
- FHWA OVERSITE RESPONSIBILITES
- R/W ACQUISITION & USE OF PRE-QUALIFIED STAFF
- UTILITY RELOCATION PROCESS
- R/W CERTIFICATIONS
REAL ESTATE STAFF INTRODUCTIONS FHWA OVERSITE RESPONSIBILITES R/W - - PowerPoint PPT Presentation
REAL ESTATE STAFF INTRODUCTIONS FHWA OVERSITE RESPONSIBILITES R/W ACQUISITION & USE OF PRE-QUALIFIED STAFF UTILITY RELOCATION PROCESS R/W CERTIFICATIONS REAL ESTATE STAFF BETH IMMELL- LIASON FOR LPA PROJECTS PAUL
DISTRICT RESPONSIBILITIES: ASSIST WITH ACQUISITION ISSSUES AUDIT TO ASSURE THAT REQUIREMENTS ARE MET TO INSURE FUNDING IS NOT AT RISK DUE TO NON-COMPLIANCE IN ACQUISITION
ALL STAFF, BOTH INTERNAL AND CONSULTANT NEED TO BE PREQUALIFIED http://www.dot.state.oh.us/Divisions/Engineering/Consultant/Consultant/prequal-row.pdf
The following are utility coordination and utility relocation coordination tasks that are the responsibility of the LPA or the LPA’s consultant:
facilities.
listed utility owners.
project plans.
correctly shown and labeled.
conflicts with their existing facilities and request that each utility;
correctly and completely or to provide information otherwise.
reimbursable.
6. Provide copies of all utility responses/information to the District Utility Coordinator. 7. Provide each listed utility owner with a copy of each subsequent plan submittal. 8. Schedule and meet at the project site with all affected owners. 9. Request utility relocation plans, work schedules and estimates, if applicable, to be submitted one month prior to the project file date. 10. Review and approve utility relocation plans and provide District Utility Coordinator with relocation plans for ODOT review. 11. Prepare Utility Note and provide to District Utility Coordinator for review. 12. Monitor utility relocation work progress.
The following are utility coordination and utility relocation coordination tasks that are the responsibility of ODOT: 1. Provide utility contact information. 2. Review plan submissions. 3. Provide guidance to LPA to assure compliance with ODOT policies. 4. Attend utility meetings, if requested. 5. Review utility relocation plans. 6. Process utility estimates and billings. 7. Review and post Utility Notes.
BRO-763-0.96, PID 93347
area at the time of award of contract. These utilities facilities will remain in place or be relocated within the construction limits of the project as set out below. All station locations are based upon the proposed centerline of SR 763, as shown on the construction plans and are approximate unless otherwise stated. AMERICAN ELECTRIC POWER / FRONTIER COMMUNICATIONS
project that will remain in place and active during construction, which are located as follow: Pole Location Disposition Station 48+75, 80 feet left Remain Station 53+45, 71 feet left Remain Station 58+00, 142 feet left Remain
The contact person for American Electric Power is Ms. Caroline Irion, 740-774-7173. The contact person for Frontier Communications is Ms. Dena Martin, 740-354-0521. BROWN COUNTY RURAL WATER ASSOCIATION The company has multiple existing underground water facilities through the project, which are located as follow: The first existing water facility is a 4 inch PVC line, which enters the work area at station 56+30, 42 feet right and continues northwardly, along the right side of SR 763, to station 56+80, 34 feet right, continues to station 57+00, 34 feet right, continues to station 58+00, 62 feet right and continues on to exit the work area at station 58+70, 66 feet right. The second existing water facility is a 6 inch PVC line, which enters the work area at station 56+60, 42 feet right and continues northwardly, along the right side of SR 763, to station 56+80, 38 feet right, continues to station 57+00, 38 feet right, continues to station 58+00, 65 feet right and continues on to exit the work area at station 58+60, 72 feet right.
Both the first and second existing water facilities will remain active during construction, however both facilities will be deepened by 2 feet to 3 feet along their current horizontal alignment from station 56+65 through station 58+65 to clear the proposed excavation. The third existing water facility is a 3/4 inch service line, which enters the work area at station 54+37, 65 feet right and continues westwardly, to end at an existing meter at station 54+12, 29 feet
removed. Brown County Rural Water Association will have this relocation work completed by December 15th, 2016. The contact person for Brown County Rural Water Association is Mr. Gary McKenzie, 937-375- 4106, ext. 231. GENERAL COMMENTS Bidders are advised that the utility relocation plans are on file and may be reviewed at the District 9 Utilities Office.
required)
predates the rights held by the city/state
REIMBURSEMENT ELIGIBILITY OF A PUBLIC WATER LINE, SANITARY SEWER LINE, ELECTRIC, STEAM OR OTHER FACILITIES OWNED BY A GOVERNMENTAL AGENCY IS ESTABLISHED WHEN THE EXISTING FACILITIES ARE AFFECTED BY A PROJECT AND LOCATED ON PROPERTY WHERE THE PUBLIC UTILITY HAS A COMPENSABLE PROPERTY RIGHT AS FOLLOWS:
UTILITY
WITHIN THE CORPORATION LIMITS OF THE GOVERNMENT AGENCY THAT OWNS THE PUBLIC UTILITY
GOVERNMENTAL AGENCY THAT OWNS THE PUBLIC UTILITY WHERE THE UTILITY HAS A COMPENSABLE AGREEMENT WITH THE GOVERNMENTAL AGENCY HAVING JURISDICTION
http://www.aashto.org/
http://www.puco.ohio.gov/puco/
http://www.dot.state.oh.us/Divisions/Engineering/RealEstate/Pages/Manuals.aspx
(NO ROE)
(AT LEAST 1 ROE) http://www.dot.state.oh.us/Divisions/Engineering/RealEstate/Pages/Forms.aspx