PLAYING A CHANGING GAME: A Shift in Ownership of Non-Traditional - - PowerPoint PPT Presentation

playing a changing game a shift in ownership of non
SMART_READER_LITE
LIVE PREVIEW

PLAYING A CHANGING GAME: A Shift in Ownership of Non-Traditional - - PowerPoint PPT Presentation

PLAYING A CHANGING GAME: A Shift in Ownership of Non-Traditional Risks AGC 2018 Conference on Surety Bonding & Construction Risk Management Adrian Pellen , SVP Infrastructure Segment Leader January 30, 2018 Naples, FL Agenda 1


slide-1
SLIDE 1

PLAYING A CHANGING GAME: A Shift in Ownership of Non-Traditional Risks

AGC 2018 Conference on Surety Bonding & Construction Risk Management

Adrian Pellen , SVP – Infrastructure Segment Leader January 30, 2018 Naples, FL

slide-2
SLIDE 2

1

February 5, 2018

Agenda

slide-3
SLIDE 3

MARSH

2

February 5, 2018

Agenda Risks

1. What’s the Issue? 2. Macro Trends 3. Non-Traditional Risks – Site Conditions (Environmental, Archaeological, Paleontological) – Weather Events – Other Risk Issues (Permitting etc). 4. Management/Negotiating Strategies 5. Risk Transfer Products 6. Q&A

slide-4
SLIDE 4

MARSH

3

February 5, 2018

What’s the Current Condition? The Issue

Owners are transferring risks that they have traditionally retained

slide-5
SLIDE 5

4

February 5, 2018

Macro Trends

slide-6
SLIDE 6

MARSH

5

February 5, 2018

Macro Trends What’s Creating the Conditions? - Advisors

Lagging Efficiency Looming Boom

Source: BCG, 2015 – Value Creators Report Source: McKinsey, 2017 - Global Infrastructure Initiative

slide-7
SLIDE 7

MARSH

6

February 5, 2018

Macro Trends What’s Creating the Conditions? - Advisors

VfM

Source: IO, 2015 – Assessing Value for Money

slide-8
SLIDE 8

7

February 5, 2018

Non-Traditional Risks In Review

slide-9
SLIDE 9

MARSH

8

February 5, 2018

Risk Allocation Standards?

Source: FHWA

slide-10
SLIDE 10

MARSH

9

February 5, 2018

Non-Traditional Risks Site Conditions

Archaeological/Paleontological Contamination/HazMat

slide-11
SLIDE 11

MARSH

10

February 5, 2018

Non-Traditional Risks Site Condition: Environmental & Hazmat – Contract Examples

12.2.4 Costs and Delays. Except for Owner Release(s) of Hazardous Materials, except as set forth in Sections 12.2.3 and 12.3 and without limiting Owner’s role or responsibilities set forth in Section 12.2.5, Contractor shall not be entitled to any compensation due to increased costs or delays associated with the discovery, handling, storage, removal, remediation, transport, treatment or disposal of Hazardous Materials, including contaminated groundwater, encountered in construction of the Project or Utility Adjustments. 12.3.2 Reimbursement for Certain Costs. Owner shall compensate Contractor for 100% of Contractor’s reasonable, out-of-pocket costs and expenses directly attributable to the handling, transport, removal and disposal of Pre-existing Hazardous Materials encountered by Contractor. The foregoing notwithstanding, none of the following costs and expenses shall be chargeable to Owner under this Section 12.3.2: (i) costs and expenses to the extent attributable to Contractor Releases of Hazardous Materials or Owner Releases of Hazardous Materials (without prejudice to any rights in respect of a Compensation Event under clause (j) of the definition of Compensation Event); (ii) delay and disruption costs and expenses; (iii) costs and expenses that could be avoided by the exercise of commercially reasonable efforts to mitigate and reduce cost; and (iv) Contractor’s administrative and overhead expenses arising out of or relating to Pre-existing Hazardous Materials “Pre-existing Hazardous Materials” ……Contractor shall have the burden of proof as to any Hazardous Materials not identified as being present

slide-12
SLIDE 12

MARSH

11

February 5, 2018

Non-Traditional Risks Site Condition: Environmental & Archaeological – Contract Examples

Compensation Event means any of the following: (l) The discovery of any Undisclosed Archaeological Remains during the carrying out of the Construction Work; (m) The discovery of any Undisclosed Regulated Environmental Condition during the carrying out of the Construction Work; Undisclosed Archaeological Remains means any Archaeological Remains that, as at the Setting Date, were neither: (a) known to Developer; or (b) could reasonably have been identified by an appropriately qualified and experienced contractor or engineer exercising due care and skill and Good Industry Practice in the same or equivalent circumstances, including through review and analysis of the Reference Information or publicly available information (including, without limitation, the Final Environmental Impact Statement). Undisclosed Regulated Environmental Condition means any Regulated Environmental Condition that existed on a part of the Project Right of Way prior to the date on which the Department provided the Project Right of Entry to the relevant part of the Project Right of Way and that represents an additional or materially different condition to those described in the Regulated Materials Baseline Report (including conditions that were incorrectly identified (even if otherwise depicted or described) or that manifest themselves in a new location not identified or anticipated in the report), excluding any Regulated Environmental Condition that (a) could reasonably have been identified or discovered by an appropriately qualified and experienced contractor or engineer exercising due care and skill and Good Industry Practice based on the information set forth in the Regulated Materials Baseline Report or (b) arises from the Pre-Existing Gas Wells.

slide-13
SLIDE 13

MARSH

12

February 5, 2018

Non-Traditional Risks Site Conditions

slide-14
SLIDE 14

MARSH

13

February 5, 2018

Non-Traditional Risks Weather Events – Contract Examples

  • 13. RELIEF EVENTS

13.1 Relief Event Defined 13.1.1 Included Events In this Agreement, "Relief Event" means any of the following events, conditions, or circumstances (x) during the Operating Period only, if the outdoor ambient temperature in the XXXXX City Centre, as reported by Environment XXXX, falls below -40°C (without wind-chill) or above +40°C (each, a "Temperature Exceedance");

What about construction phase? High threshold

slide-15
SLIDE 15

14

February 5, 2018

Risk Management

slide-16
SLIDE 16

MARSH

15

February 5, 2018

Management Strategies

  • Precedence on similar projects/Common Standard
  • Quantification and Value for Money Argument: Shift Back
  • Sharing – capped amount, co-sharing
  • Probabilistic modeling
  • Risk Mapping & Scenario Analysis
  • Transfer via contract
  • Purchase Insurance

Negotiation Continued Assessment Risk Transfer

slide-17
SLIDE 17

16

February 5, 2018

Risk Transfer

slide-18
SLIDE 18

MARSH

17

February 5, 2018

Risk Transfer What’s Available?

  • Environmental Insurance

– Insurable

  • 3rd Party Liability: Bodily Injury, Property Damage and Cleanup

– Potentially Insurable

  • CERCLA Liability for NODS
  • Unknown Pre-existing Conditions
  • 1st Party Cleanup & Delay Losses

– Excluded

  • Known pre-existing conditions

– Key Notes: Schedule Contracts & Disclose Site Assessment Report

slide-19
SLIDE 19

MARSH

18

February 5, 2018

Risk Transfer What’s Available?

  • Archaeologically/Paleontological Discoveries

– Insurable

  • As add on to Builder’s Risk (Domestic)

LexArchaeology℠ provides first-party coverage for expenses and construction completion delays that arise due to the unexpected discovery at a construction site of archaeological resources of significant interest

  • Covers assessment, continuing expenses and other delay costs

– Overseas product available for select clients – Excluded

  • Liquidated Damages

– Key Notes: Heavily Underwritten

slide-20
SLIDE 20

MARSH

19

February 5, 2018

Risk Transfer What’s Available?

  • Weather Insurance

– Insurable

  • Financial Loss Arising out of Various Specified Perils
  • Temperature (hot/cold)
  • Precipitation (snow/rain)

– Overseas product available for select clients – Key Notes:

  • Define threshold “Critical Event”
  • Definite Deductible
  • Select Limit
slide-21
SLIDE 21

20

February 5, 2018

Q&A

slide-22
SLIDE 22

MARSH

21

February 5, 2018

Thank You

Questions? Comments? Queries?

Adrian Pellen Senior Vice President Infrastructure Segment Leader – US & Canada National Construction Practice Marsh USA Inc. 540 West Madison, Chicago, IL, 60661 Direct 312 627 6146 | Mobile 312 607 3865 adrian.pellen@marsh.com www.marsh.com