paramount uni fi ed paramount uni fi ed school di stri ct
play

PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL - PowerPoint PPT Presentation

PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL DI STRI CT MEASURE AA MEASURE AA February 2008 February 2008 Update Update McCarthy Building Companies McCarthy Building Companies LPA - - Architects Architects LPA


  1. PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL DI STRI CT MEASURE AA MEASURE AA February 2008 February 2008 Update Update McCarthy Building Companies McCarthy Building Companies LPA - - Architects Architects LPA

  2. Paramount High School Paramount High School Three independent sets of drawings. Three independent sets of drawings. Phase I Phase I 1) 1) Stadium and Athletic Complex Stadium and Athletic Complex Phase II Phase II 2) 2) Stadium Field House Stadium Field House Phase III Phase III 3) 3) Gymnasium, Science Building, Library, Classroom Gymnasium, Science Building, Library, Classroom renovation and West Campus Mini- -gym and Auditorium gym and Auditorium renovation and West Campus Mini renovation renovation

  3. Stadium and Athletic Complex ROSECRANS AVE. RESTROOM TICKET/ MAINTENANCE ACCESS ROAD CONCESSIONS BLDG SHOT VISITOR ENTRY 2000 SEATS PUT HIGH FIELD JUMP HOUSE FOOTBALL SOCCER 195’ X 360’ PARKING D - ZONE 9 LANE TRACK AND FIELD POLE VAULT DISCUS TRIPLE JUMP / LONG JUMP HOME ENTRY TICKET/ CONCESSIONS 4000 SEATS PRESS BOX / RESTROOM GYM HARD 380’ COURTS BASEBALL FIELD MAINTENANCE BLDG CLASSROOM BLDG LPA Paramount High School

  4. Status – – Phase I Phase I Status Stadium & Athletic Complex Stadium & Athletic Complex Timeline – – May 2007 May 2007 – – October 2007 October 2007 Timeline Master planning and design drawings are complete. The are complete. The � Master planning and design drawings � documents have been submitted to the Department of State documents have been submitted to the Department of State Architecture (DSA) for approval. Currently the estimated date Architecture (DSA) for approval. Currently the estimated date of approval is March 31, 2008. of approval is March 31, 2008. The pre- -fabricated fabricated bleacher and press box system bleacher and press box system have been have been � The pre � bid through a competitive process and a contractor selected. bid through a competitive process and a contractor selected. All fabrication and layout drawings are complete and have All fabrication and layout drawings are complete and have been submitted to DSA for review. been submitted to DSA for review. Demolition and Earthwork bid through completion of process, Demolition and Earthwork bid through completion of process, � � which includes existing stadium, support buildings and which includes existing stadium, support buildings and infrastructure. Earthwork will follow immediately and infrastructure. Earthwork will follow immediately and continue for approximately 8 weeks. continue for approximately 8 weeks.

  5. continued continued The bid process for remaining scope will start upon approval � The bid process for remaining scope will start upon approval � of drawings. Remaining scope includes: of drawings. Remaining scope includes: – Track Track – – Football / soccer field Football / soccer field – – Baseball field Baseball field – – Restroom buildings Restroom buildings – Construction to start upon selection of the lowest qualified Construction to start upon selection of the lowest qualified � � bidder and subsequent board of approval to award. bidder and subsequent board of approval to award.

  6. Demolition – – in progress in progress Demolition

  7. Status – – Phase I I Field House Phase I I Field House Status Timeline – – September 2008 September 2008 – – January 2010 January 2010 Timeline Drawings are currently in design development and due to � Drawings are currently in design development and due to � project team for review on 2/29/08. project team for review on 2/29/08. Upon review and approval of documents LPA Architects will Upon review and approval of documents LPA Architects will � � move forward with construction documents. move forward with construction documents. Project is scheduled for DSA submittal early summer 2008. Project is scheduled for DSA submittal early summer 2008. � � Upon DSA approval construction is scheduled to begin Upon DSA approval construction is scheduled to begin � � Fall/Winter 2008. Fall/Winter 2008.

  8. Cockrill Field becomes Field House Field becomes Field House Cockrill (East view) (East view)

  9. Field House (West view) Field House (West view)

  10. Status – – Phase I I I Gymnasium, Science Phase I I I Gymnasium, Science Status Building, Library, Classroom Renovation and Building, Library, Classroom Renovation and West Campus Mini- -gym and Auditorium gym and Auditorium West Campus Mini Renovation Renovation Timeline – – December 2007 December 2007 – – August 2010 August 2010 Timeline Drawings are currently in design development and scheduled � Drawings are currently in design development and scheduled � to complete for project team review early April 2008. to complete for project team review early April 2008. Upon approval of drawings LPA Architects will move into Upon approval of drawings LPA Architects will move into � � construction documents. construction documents. Estimated time frame of submittal to DSA, Summer 2008. Estimated time frame of submittal to DSA, Summer 2008. � � Estimated Construction start Spring 2009. Estimated Construction start Spring 2009. � � The project team is currently looking at the phasing options The project team is currently looking at the phasing options � � with the most expeditious schedule and minimum amount of with the most expeditious schedule and minimum amount of disruption to each campus. disruption to each campus.

  11. Perspective View of North-East Elevation PHS Gym expansion PHS Gym expansion

  12. Interior Perspective View - Hall of Champions

  13. Science / Medical Health Building Perspective Perspective View of West Elevation

  14. Library Expansion Perspective Perspective View of North Elevation

  15. West Campus- Development EXISTING JOINT USE BACKSTOP SOCCER OVERLAY 225’ x 360’ PARAMOUNT BOULEVARD CLEARWATER AUDITORIUM Mini-Gym Locker Room 280’ Reno. HARD SOFTBALL COURTS FIELD PARKING THIRD STREET LPA Paramount High School

  16. West Campus Clearwater Auditorium Interior Improvements Concept

  17. West Campus Mini Gym Interior

  18. K- -8 Campuses 8 Campuses K Add mini- -gymnasiums for future middle grade campuses gymnasiums for future middle grade campuses � Add mini � Add flexible science laboratory classrooms for future middle Add flexible science laboratory classrooms for future middle � � grade programs grade programs Improve ingress/egress for some campuses Improve ingress/egress for some campuses � � Renovate some old libraries � Renovate some old libraries � Replace old portable classrooms with newer classrooms that Replace old portable classrooms with newer classrooms that � � will extend the life of the school. will extend the life of the school. Add inclement weather coverings, as needed. � Add inclement weather coverings, as needed. � Renovate communication systems at campuses to provide Renovate communication systems at campuses to provide � � consistent safety in all areas. consistent safety in all areas.

  19. Status Status Currently planning with staff at future middle grade campuses � Currently planning with staff at future middle grade campuses � to establish facility needs for reconfiguration changes. to establish facility needs for reconfiguration changes. Meet with architects to begin design drawings for mini- -gyms. gyms. Meet with architects to begin design drawings for mini � � February, 2008 February, 2008

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend