PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL - - PowerPoint PPT Presentation

paramount uni fi ed paramount uni fi ed school di stri ct
SMART_READER_LITE
LIVE PREVIEW

PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL - - PowerPoint PPT Presentation

PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL DI STRI CT MEASURE AA MEASURE AA February 2008 February 2008 Update Update McCarthy Building Companies McCarthy Building Companies LPA - - Architects Architects LPA


slide-1
SLIDE 1

PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL DI STRI CT MEASURE AA MEASURE AA

February 2008 February 2008 Update Update

McCarthy Building Companies McCarthy Building Companies LPA LPA -

  • Architects

Architects

slide-2
SLIDE 2

Paramount High School Paramount High School

Three independent sets of drawings. Three independent sets of drawings.

1) 1)

Phase I Phase I Stadium and Athletic Complex Stadium and Athletic Complex

2) 2)

Phase II Phase II Stadium Field House Stadium Field House

3) 3)

Phase III Phase III Gymnasium, Science Building, Library, Classroom Gymnasium, Science Building, Library, Classroom renovation and West Campus Mini renovation and West Campus Mini-

  • gym and Auditorium

gym and Auditorium renovation renovation

slide-3
SLIDE 3

Stadium and Athletic Complex

380’ ROSECRANS AVE.

4000 SEATS MAINTENANCE BLDG DISCUS SHOT PUT BASEBALL FIELD TRIPLE JUMP / LONG JUMP ACCESS ROAD PARKING TICKET/ CONCESSIONS TICKET/ CONCESSIONS HARD COURTS FIELD HOUSE VISITOR ENTRY HOME ENTRY GYM CLASSROOM BLDG PRESS BOX / RESTROOM

Paramount High School

LPA

HIGH JUMP 2000 SEATS FOOTBALL POLE VAULT SOCCER 195’ X 360’ 9 LANE TRACK AND FIELD D - ZONE RESTROOM MAINTENANCE BLDG

slide-4
SLIDE 4

Status Status – – Phase I Phase I Stadium & Athletic Complex Stadium & Athletic Complex

Timeline Timeline – – May 2007 May 2007 – – October 2007 October 2007

  • Master planning and design drawings

Master planning and design drawings are complete. The are complete. The documents have been submitted to the Department of State documents have been submitted to the Department of State Architecture (DSA) for approval. Currently the estimated date Architecture (DSA) for approval. Currently the estimated date

  • f approval is March 31, 2008.
  • f approval is March 31, 2008.
  • The pre

The pre-

  • fabricated

fabricated bleacher and press box system bleacher and press box system have been have been bid through a competitive process and a contractor selected. bid through a competitive process and a contractor selected. All fabrication and layout drawings are complete and have All fabrication and layout drawings are complete and have been submitted to DSA for review. been submitted to DSA for review.

  • Demolition and Earthwork bid through completion of process,

Demolition and Earthwork bid through completion of process, which includes existing stadium, support buildings and which includes existing stadium, support buildings and

  • infrastructure. Earthwork will follow immediately and
  • infrastructure. Earthwork will follow immediately and

continue for approximately 8 weeks. continue for approximately 8 weeks.

slide-5
SLIDE 5

continued continued

  • The bid process for remaining scope will start upon approval

The bid process for remaining scope will start upon approval

  • f drawings. Remaining scope includes:
  • f drawings. Remaining scope includes:

– – Track Track – – Football / soccer field Football / soccer field – – Baseball field Baseball field – – Restroom buildings Restroom buildings

  • Construction to start upon selection of the lowest qualified

Construction to start upon selection of the lowest qualified bidder and subsequent board of approval to award. bidder and subsequent board of approval to award.

slide-6
SLIDE 6

Demolition Demolition – – in progress in progress

slide-7
SLIDE 7

Status Status – – Phase I I Field House Phase I I Field House

Timeline Timeline – – September 2008 September 2008 – – January 2010 January 2010

  • Drawings are currently in design development and due to

Drawings are currently in design development and due to project team for review on 2/29/08. project team for review on 2/29/08.

  • Upon review and approval of documents LPA Architects will

Upon review and approval of documents LPA Architects will move forward with construction documents. move forward with construction documents.

  • Project is scheduled for DSA submittal early summer 2008.

Project is scheduled for DSA submittal early summer 2008.

  • Upon DSA approval construction is scheduled to begin

Upon DSA approval construction is scheduled to begin Fall/Winter 2008. Fall/Winter 2008.

slide-8
SLIDE 8

Cockrill Cockrill Field becomes Field House Field becomes Field House (East view) (East view)

slide-9
SLIDE 9

Field House (West view) Field House (West view)

slide-10
SLIDE 10

Status Status – – Phase I I I Gymnasium, Science Phase I I I Gymnasium, Science Building, Library, Classroom Renovation and Building, Library, Classroom Renovation and West Campus Mini West Campus Mini-

  • gym and Auditorium

gym and Auditorium Renovation Renovation

Timeline Timeline – – December 2007 December 2007 – – August 2010 August 2010

  • Drawings are currently in design development and scheduled

Drawings are currently in design development and scheduled to complete for project team review early April 2008. to complete for project team review early April 2008.

  • Upon approval of drawings LPA Architects will move into

Upon approval of drawings LPA Architects will move into construction documents. construction documents.

  • Estimated time frame of submittal to DSA, Summer 2008.

Estimated time frame of submittal to DSA, Summer 2008.

  • Estimated Construction start Spring 2009.

Estimated Construction start Spring 2009.

  • The project team is currently looking at the phasing options

The project team is currently looking at the phasing options with the most expeditious schedule and minimum amount of with the most expeditious schedule and minimum amount of disruption to each campus. disruption to each campus.

slide-11
SLIDE 11

PHS Gym expansion PHS Gym expansion

Perspective View of North-East Elevation

slide-12
SLIDE 12

Interior Perspective View - Hall of Champions

slide-13
SLIDE 13

Perspective View of West Elevation

Science / Medical Health Building

Perspective

slide-14
SLIDE 14

Library Expansion

Perspective

Perspective View of North Elevation

slide-15
SLIDE 15

West Campus- Development

PARAMOUNT BOULEVARD

SOCCER OVERLAY 225’ x 360’

THIRD STREET

SOFTBALL FIELD PARKING CLEARWATER AUDITORIUM EXISTING JOINT USE BACKSTOP 280’ HARD COURTS

Paramount High School

LPA

Mini-Gym Locker Room Reno.

slide-16
SLIDE 16

West Campus

Clearwater Auditorium

Interior Improvements Concept

slide-17
SLIDE 17

West Campus Mini Gym

Interior

slide-18
SLIDE 18

K K-

  • 8 Campuses

8 Campuses

  • Add mini

Add mini-

  • gymnasiums for future middle grade campuses

gymnasiums for future middle grade campuses

  • Add flexible science laboratory classrooms for future middle

Add flexible science laboratory classrooms for future middle grade programs grade programs

  • Improve ingress/egress for some campuses

Improve ingress/egress for some campuses

  • Renovate some old libraries

Renovate some old libraries

  • Replace old portable classrooms with newer classrooms that

Replace old portable classrooms with newer classrooms that will extend the life of the school. will extend the life of the school.

  • Add inclement weather coverings, as needed.

Add inclement weather coverings, as needed.

  • Renovate communication systems at campuses to provide

Renovate communication systems at campuses to provide consistent safety in all areas. consistent safety in all areas.

slide-19
SLIDE 19

Status Status

  • Currently planning with staff at future middle grade campuses

Currently planning with staff at future middle grade campuses to establish facility needs for reconfiguration changes. to establish facility needs for reconfiguration changes.

  • Meet with architects to begin design drawings for mini

Meet with architects to begin design drawings for mini-

  • gyms.

gyms. February, 2008 February, 2008