PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL DI STRI CT MEASURE AA MEASURE AA
February 2008 February 2008 Update Update
McCarthy Building Companies McCarthy Building Companies LPA LPA -
- Architects
Architects
PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL - - PowerPoint PPT Presentation
PARAMOUNT UNI FI ED PARAMOUNT UNI FI ED SCHOOL DI STRI CT SCHOOL DI STRI CT MEASURE AA MEASURE AA February 2008 February 2008 Update Update McCarthy Building Companies McCarthy Building Companies LPA - - Architects Architects LPA
McCarthy Building Companies McCarthy Building Companies LPA LPA -
Architects
Three independent sets of drawings. Three independent sets of drawings.
1) 1)
Phase I Phase I Stadium and Athletic Complex Stadium and Athletic Complex
2) 2)
Phase II Phase II Stadium Field House Stadium Field House
3) 3)
Phase III Phase III Gymnasium, Science Building, Library, Classroom Gymnasium, Science Building, Library, Classroom renovation and West Campus Mini renovation and West Campus Mini-
gym and Auditorium renovation renovation
380’ ROSECRANS AVE.
4000 SEATS MAINTENANCE BLDG DISCUS SHOT PUT BASEBALL FIELD TRIPLE JUMP / LONG JUMP ACCESS ROAD PARKING TICKET/ CONCESSIONS TICKET/ CONCESSIONS HARD COURTS FIELD HOUSE VISITOR ENTRY HOME ENTRY GYM CLASSROOM BLDG PRESS BOX / RESTROOM
HIGH JUMP 2000 SEATS FOOTBALL POLE VAULT SOCCER 195’ X 360’ 9 LANE TRACK AND FIELD D - ZONE RESTROOM MAINTENANCE BLDG
Timeline Timeline – – May 2007 May 2007 – – October 2007 October 2007
Master planning and design drawings are complete. The are complete. The documents have been submitted to the Department of State documents have been submitted to the Department of State Architecture (DSA) for approval. Currently the estimated date Architecture (DSA) for approval. Currently the estimated date
The pre-
fabricated bleacher and press box system bleacher and press box system have been have been bid through a competitive process and a contractor selected. bid through a competitive process and a contractor selected. All fabrication and layout drawings are complete and have All fabrication and layout drawings are complete and have been submitted to DSA for review. been submitted to DSA for review.
Demolition and Earthwork bid through completion of process, which includes existing stadium, support buildings and which includes existing stadium, support buildings and
continue for approximately 8 weeks. continue for approximately 8 weeks.
The bid process for remaining scope will start upon approval
– – Track Track – – Football / soccer field Football / soccer field – – Baseball field Baseball field – – Restroom buildings Restroom buildings
Construction to start upon selection of the lowest qualified bidder and subsequent board of approval to award. bidder and subsequent board of approval to award.
Timeline Timeline – – September 2008 September 2008 – – January 2010 January 2010
Drawings are currently in design development and due to project team for review on 2/29/08. project team for review on 2/29/08.
Upon review and approval of documents LPA Architects will move forward with construction documents. move forward with construction documents.
Project is scheduled for DSA submittal early summer 2008.
Upon DSA approval construction is scheduled to begin Fall/Winter 2008. Fall/Winter 2008.
Timeline Timeline – – December 2007 December 2007 – – August 2010 August 2010
Drawings are currently in design development and scheduled to complete for project team review early April 2008. to complete for project team review early April 2008.
Upon approval of drawings LPA Architects will move into construction documents. construction documents.
Estimated time frame of submittal to DSA, Summer 2008.
Estimated Construction start Spring 2009.
The project team is currently looking at the phasing options with the most expeditious schedule and minimum amount of with the most expeditious schedule and minimum amount of disruption to each campus. disruption to each campus.
Perspective View of North-East Elevation
Interior Perspective View - Hall of Champions
Perspective View of West Elevation
Perspective
Perspective
Perspective View of North Elevation
PARAMOUNT BOULEVARD
SOCCER OVERLAY 225’ x 360’
THIRD STREET
SOFTBALL FIELD PARKING CLEARWATER AUDITORIUM EXISTING JOINT USE BACKSTOP 280’ HARD COURTS
Mini-Gym Locker Room Reno.
Clearwater Auditorium
Interior Improvements Concept
Interior
Add mini-
gymnasiums for future middle grade campuses
Add flexible science laboratory classrooms for future middle grade programs grade programs
Improve ingress/egress for some campuses
Renovate some old libraries
Replace old portable classrooms with newer classrooms that will extend the life of the school. will extend the life of the school.
Add inclement weather coverings, as needed.
Renovate communication systems at campuses to provide consistent safety in all areas. consistent safety in all areas.
Currently planning with staff at future middle grade campuses to establish facility needs for reconfiguration changes. to establish facility needs for reconfiguration changes.
Meet with architects to begin design drawings for mini-
gyms. February, 2008 February, 2008