Outline Background & Motivation Reserve Modeling Framework - - PowerPoint PPT Presentation
Outline Background & Motivation Reserve Modeling Framework - - PowerPoint PPT Presentation
Outline Background & Motivation Reserve Modeling Framework Types of improvements COMPETES simulations Results Challenges Arising from Wind Quack! Source: Flexibility in 21st Century Power Systems, NREL Report Source:
Outline
- Background & Motivation
- Reserve Modeling Framework
- Types of improvements
- COMPETES simulations
- Results
Challenges Arising from Wind
Source: Flexibility in 21st Century Power Systems, NREL Report
Quack!
Source: CAISO
Reserve
- Opera
rating Re Reserve ve is extra capacity (MW) needed in case of contingency
- Loss of a generator
- Loss of a transmission line
- Sudden change in load
- Now: change in renewable energy
40 60 80 100 120 1 6 11 16 21
MW Hour
Expected Demand Reserve+Expected Demand
Frequency restoration (mFRR), not automatic frequency response
Operational Reserve
1. Size / Procure
- How much do we need?
- E.g., extra 30 MW on-line in every hour
2. Allocate
- Who will be scheduled?
- Generator B & C will each provide 15
MW
3. Activate
- Who will provide the energy if actually
needed?
- Deliverability in real time market
Procurement
- How much do we need?
- Often called ’reserve requirement’
- Examples
- Capacity of largest generator or
transmission line
- X% of demand and Y% of renewables for …
- One day
- One season
20 40 60 80 100 120 1 6 11 16 21
MW Hour
Expected Demand Reserve Ex % Reserve Ex Fixed
Allocation Who will be scheduled?
- Most US markets
- Market based
- Primary
- Secondary
- Tertiary
- Determined in zones
- Most European markets
- Long-term contracts
- Portfolio based
- Unit based
- Some dispatch
- Determined by country
Source: ENTSO-E
Activation
- Who will actually provide reserves if needed?
- Generators change energy output level in
balancing
- Contract-based
- TSO can call on contracted generators to
provide reserve in real time
- Market-based (US)
- System operator calls on generators
selected in the day-ahead for reserve
- Energy must be deliverable
- Transmission constraints might limit
deliverability within and between countries
ECN-JHU Current Research Question What changes to market design will most enhance efficiency in procuring/allocating/activating reserve?
Types of Improvements
- Reserve r
requirement p procurement p period
- Seasonal
§ Current practice, four seasonal periods assessed
- Enhancement: Daily
§ Requirement determined daily
- Allocation t
type
- Contract-based
§ Current practice § Bi-lateral contracts between TSO and generators
- Enhancement: Market-based
§ Procured through co-optimization with energy market
- Amount o
- f c
coordination
- Independently determined, current practice
- Enhancement: Northwest Europe coordinates
Example requirement: 3% of demand and 5% of renewable generation
Efficiency of Reserve
- Each axis shows
a different improvement to reserve
- Increasing
complexity and efficiency moving away from origin
- Star =
hypothetical ideal
- Dot =
worst case
Reserve R Requirement Co Coordinati tion
DA & Balancing No Coordination Seasonal Daily
Increasing complexity, efficiency à Thanks to Qingyu Xu
COMPETES Network
- 33 node pan-European network
- Transmission mimics integrated EU
network with capacity limited by NTC
- Future generation +
potential energy storage
- Renewable scenario
based on ENSTO-E 2030 Vision 4 of “European Green Revolution”
Model Formulation: Unit Commitment
- Min Operating Cost
- Subject to
- Generator min & max capacity
- Ramp limits
- Min up & down times
- Transmission line capacity & flow (Net
Transfer Capacity)
- Startup & no-load binary constraints /
relaxed formulation
Operational Markets
- Day Ahead
- Schedules generation for the following day
- Inputs: bids & offers, forecast for load and wind
- Outputs: prices, schedule (on/off), dispatch
- à Reserve allocation phase
- Balancing
- Updates schedule to reflect new information
- Inputs: new bids & offers, updated forecast
- Outputs: prices, fast start schedule, dispatch
- à Reserve activation phase
- Was the right amount procured?
- Was it allocated to those who could deliver it?
, reserve sizing
Simulations & Sensitivity Analysis
- Simulations
- Simulated one day-ahead forecast
- Followed by 5 real-time ”actual” wind
realizations
- Results show mean of 5 simulations
- Error bars show minimum and
maximum deviations
- Added an extra coordination
component
- Due to results found by K. van den
Bergh in [4], we consider coordination in balancing alone with no coordination in day-ahead
- K. van den Bergh, [4]
Day-Ahead
- Bal. 1
- Bal. 2
- Bal. 5
- Bal. 3
- Bal. 4
Efficiency of Reserve
- Each axis shows
a different improvement to reserve
- Increasing
complexity and efficiency moving away from origin
- Star =
hypothetical ideal
- Dot =
worst case
Seasonal Daily
Co Coordinati tion Reserve R Requirement
Operating Costs
- Example results comparing
- Star, ‘ideal case’ (DMC)
- Reserve size based on daily average
- Market-based allocation
- Co
Coordinati tion in d day-ahead a and b balancing
- Rectangle (DMN)
- Reserve size based on daily average
- Market-based allocation
- No c
coordination +54.9%
54.0 55.6 0.32
- 0.29
0%
+59.3%
EU
NL
0%
54.9% = DMN op costs − DMC op cost DMC op cost
Deviation of minimum scenario Deviation of maximum scenario 54.9%: 20% load shedding 80% generation deviations
Seasonal Daily Co Coordinati tion Reserve R Requirement
Results – operating cost
% deviations from ‘ideal’ case without load shedding
Seasonal Daily
Co Coordinati tion Reserve R Requirement
30.9 33.0
- 0.21
0.51
- 0.23
0.49
+0.12% +0.11% +32.1% +40.9%
39.9 41.7
- 0.30
0.44
+0.05%
0.37
- 0.33
EU
NL
27.7 31.4
+29.1%
- 0.48
2.50
- 0.72
1.62 34.3 37.9
- 0.20
0.91
- 0.66
0.95
+0.67%
- 0.04%
+0.28% +35.7%
0%
0%
Daily
Co Coordinati tion Reserve R Requirement
Seasonal
CZE, DEW, FRA, GER, ITA, POR, SKO, SPA, SWE, SWI, NOR, BLK DEN, POL, UKI NED, BLT BEL, FIN, IRE
- Lowest Cost Solution by Country
Where is each country is better off?
Results – wind curtailed
% deviations from ‘ideal’ case, NL data in MWh
Seasonal Daily
Co Coordinati tion Reserve R Requirement
1.1 19
- 8.2
9.1
- 5.3
11.4
- 3.5%
- 0.6%
+6.2% +6.6%
1.7 20
- 7.7
10
- 2.7%
13
- 4.8
EU
NL
448 8350
3885 MWh
448 8350
0 MWh 0 MWh 0 MWh 3875 MWh
0%
0 MWh
Reserves: Source Fuel
All market based simulations showed similar percentages Storage prod. 59% Coal 2% Lignite 1% Res-e 1% Nuclear 0% Oil 0% Wind 0% Sun 0% Gas 37%
Contracted Reserve Cases
Reserve R Requirement Co Coordinati tion
Balancing No Coordination Seasonal Daily
+40.9% +0.17% +32.1% 0% +110% +30.0%
- All contracted cases
showed higher c costs
- Some cases were
double the cost of the market-based cases
§ Some countries faced significant load shedding § Wide difference in
- perating costs
country by country
- Fewer MWh of wi
wind d cu curtailment than ‘ideal’ case when reserves were coordinated in balancing
- Additional plants online
meant lower curtailment
Conclusions
Three Suggested Improvements: 1. Difference between daily vs. seasonal requirement is minimal 2. Coordination in balancing achieves almost all benefit,
- r can produce better
solution 3. Naïve contracts for reserves produce least efficient solution compared to market
- Coordination in reserve
allocation & balancing might make up for higher costs
Other Observations ØMore coordination may lead to more wind curtailment
- Possibly due to location of
reserve within country
- Consideration of forecast
uncertainty and wind farm location can reduce curtailment
ØStorage can provide a significant amount of reserve
References
[1]
- S. Kasina, S. Wogrin, and B.F. Hobbs, “A comparison of
unit commitment approximations for generation production costing,” Working Paper, Johns Hopkins University, 2014. [2] Ö. Özdemir, F. Munoz, J. Ho, and B.F. Hobbs, “Economic Analysis of Transmission with Demand Response and Quadratic Losses by Successive LP,” IEEE Trans. Power Syst., DOI: 10.1109/TPWRS.2015.2427799, in press. [3]
- J. Cochran, M. Miller, O. Zinaman, M. Milligan, D. Arent,
- B. Palmintier, M. O’Malley, S. Mueller, E. Lannoye, A. Tuohy, B.
Kujala, M. Sommer, H. Holttinen, J. Kiviluoma, and S. K. Soonee, “Flexibility in 21st Century Power Systems,” Golden, CO, 2014. [4]
- K. van den Bergh, R. B. Hytowitz, K. Bruninx, E. Delarue, W.
D'haeseleer, and B.F. Hobbs, "Benefits of coordinating sizing, allocation and activation of reserves among market zones," Electric Power Systems Research, 143: 140–148, Feb. 2017.
Thank you! Questions?
Email: hytowitz@jhu.edu
Backup slides
Results – operating cost
% deviations from ‘ideal’ case
Seasonal Daily
Co Coordinati tion Reserve R Requirement
54.3 56.1
- 0.06
0.37
- 0.08
0.36
+0.14% +0.17% +55.4% +54.9%
54.0 55.6
- 0.26
0.39
+0.04%
0.32
- 0.29
EU
NL
57.4 61.1
+58.8%
- 0.28
2.69
- 0.74
1.60 58.0 61.5
- 0.34
0.77
- 0.66
0.95
+0.87%
- 0.05%
+0.14% +59.3%
0%
0%
Generation Mix
TWhdifference between (Seasonal/Market/No Coordination) -(Daily/Market/Coordination)
←More in ‘ideal case’ More in S/M/NC case→
Seasonal Daily Co Coordinati tion Reserve R Requirement
Net Trade (Imports)
for market based simulations, (+) = fewer imports, (-) = more imports
Daily Requirement Seasonal Requirement Day-ahead & Balancing Coordination No or Only Balancing Coordination Day-ahead & Balancing Coordination No or Only Balancing Coordination BEL
0% 0.07% 0.06%
- 0.01%
CZE
0% 0.15% 0.23% 0.14%
DEN
0% 0.15% 0.07% 0.12%
DEW
0% 0.47% 0.01% 0.64%
FIN
0% 0.34%
- 0.05%
0.04%
FRA
0% 0.16% 0.07% 0.19%
GER
0% 0.03% 0.26% 0.04%
IRE
0% 0.20% 0.26% 0.19%
ITA
0%
- 0.05%
- 0.09%
- 0.02%
NED
0% 1.27%
- 0.08%
1.90%
POL
0%
- 0.06%
- 0.04%
- 0.08%
POR
0% 0.45% 0.60% 0.65%
SKO
0% 0.06%
- 0.58%
- 0.50%
SPA
0%
- 0.21%
- 0.19%
- 0.62%
SWE
0%
- 0.02%
0.13% 0.07%
UKI
0% 0.55%
- 0.04%
0.55%
SWI
0% 0.31% 0.29% 0.34%
NOR
0%
- 0.40%
0.41%
- 0.31%
BLK
0%
- 0.04%
- 0.08%
- 0.19%
BLT
0%
- 0.13%
- 0.09%
- 0.14%
AUS
0% 0.32% 0.09%
- 0.03%
Total Energy Traded 0.15% less trade 0.07% less trade 0.15% less trade
Reserve Requirement
5 10 15 20 25
Frequency Bin
Winter
10 20 30 40
Frequency Bin
Spring
5 10 15 20 25 6302 6708 7115 7522 7928 8335 8741 9148 9554 9961
Frequency Bin
Summer
10 20 30
Frequency Bin
Fall
Seasonal: 8675 MW Seasonal: 8032 MW Seasonal: 7625 MW Seasonal: 7870 MW
Four different scenarios (A↔D) considered
31
A B C D Si Sizing
- +
Allo Allocation
- +
+ Ac Activation
- +
+ + “+” = coordinated “-” = uncoordinated
(3) Activation of reserves (real-time)
32 Allocation, activation and net cost savings relative to scenario A.
Conclusions
1) Coordinating real-time reserve activation is always beneficial 2) Coordinating reserve sizing & allocation can lead to suboptimal results (possibly even deteriorated) if network constraints are neglected 3) Further research deals with including network constraints in (deterministic) reserve sizing and allocation rules
33
Model Formulation
binary variables
ui
... ...
Commitm tment w t with thin th the N Neth therlands
Day-Ahead
xi
... ...
continuous variables
Model Formulation
relaxed binary variables
Commitm tment o t outs tside th the N Neth therlands
Day-Ahead
xi
... ...
continuous variables
ui
... ...
binary variables fast start units
ui
... ...
Model Formulation
... ...
continuous variables
Commitm tment o t only with thin th the N Neth therlands
Balancing
xi
... ...
Fixed variables: line flows, slow units