News
Steve, Vaia, Jan 9 2020
1
News Steve, Vaia, Jan 9 2020 Jan 9 2020 HL LHC IPT 1 On going - - PowerPoint PPT Presentation
News Steve, Vaia, Jan 9 2020 Jan 9 2020 HL LHC IPT 1 On going issues LS3 Schedule shift from CMS Upgrade Coordination Preliminary revised schedule by Feb 12, with internal review in Feb/March Finalized for P2UG April 1
1
▪ Preliminary revised schedule by Feb 12, with internal review in Feb/March ▪ Finalized for P2UG April 1 we update as early as possible after preliminary release
▪ From CMS week – CE Silicon will NOT do a PRR before CD3a
– But OT Silicon does
▪ Our proposal – move CE scope to November IPR/CD2
▪ Nov 17 meeting scope still to be determined – if CD2/3 is doable in early/mid 2021, preferable
▪ Almost done untangling the ball of yarn that was previous charging practice
▪ Will apply first statusing results when done, status Nov+Dec in 2nd round to catch up ▪ Fiscal Office/Directorate determined that we do not get special “construction” discount with MIE spending
▪ Total will be a BAC increase on the order of 0.5 - 1 M