NEI Uranium Enrichment Task Force February 5, 2009 Felix M. - - PowerPoint PPT Presentation

nei uranium enrichment task force
SMART_READER_LITE
LIVE PREVIEW

NEI Uranium Enrichment Task Force February 5, 2009 Felix M. - - PowerPoint PPT Presentation

NEI Uranium Enrichment Task Force February 5, 2009 Felix M. Killar, Jr. Senior Director Nuclear Energy Institute 1 Overview Task Force Makeup and Objective Issues per licensing phase Pre-application Application review


slide-1
SLIDE 1

NEI Uranium Enrichment Task Force

February 5, 2009 Felix M. Killar, Jr. Senior Director Nuclear Energy Institute

1

slide-2
SLIDE 2

Overview

  • Task Force Makeup and Objective
  • Issues per licensing phase

– Pre-application – Application review – Construction – Operation – License Termination

2

slide-3
SLIDE 3

Task Force Makeup

  • Membership

– USEC Incorporated – Louisiana Energy Services – AREVA Enrichment Services – Global Laser Enrichment, LLC

3

slide-4
SLIDE 4

Task Force Objectives

  • Objectives

– To identify policy actions and a regulatory framew ork to help ensure a stable and effective regulatory process for facilities that enrich uranium – Identification of requirements necessary (existing or proposed) to further support the licensing and regulatory oversight of enrichment facilities by consolidating them into a cohesive set of regulations to reduce the regulatory burden on applicants and licensees, as w ell as the U.S. Nuclear Regulatory Commission.

4

slide-5
SLIDE 5

Pre-application

  • Regulatory Requirements

– 10CFR Parts 2, 7, 8, 9, 11, 12, 19, 20, 21, 25, 26, 40, 61, 62, 70, 71, 73, 74, 75, 95, 110, 170, and 171 – Regulatory Guides – Branch Technical Positions – Interim Staff Guidance – SECY/SRMs – Commission Orders – Commission Policy Statements – Pre-submittal meetings w ith NRC staff

5

slide-6
SLIDE 6

Application Review

  • Application

– Environmental Report and License Application

  • Level of detail
  • Completeness
  • Timing of submittal

– NRC Review time

  • Acceptance review
  • Contention submittals
  • Requests for additional information (RAIs)

schedule

  • Environmental Report
  • Safety Evaluation Report
  • Public hearing process

6

slide-7
SLIDE 7

Construction

  • Pre-construction activities
  • Construction schedule
  • NRC construction inspections
  • Pre-operation completeness

review

  • Operation readiness

7

slide-8
SLIDE 8

Operations

  • NRC Inspections

– Resident Inspector – Routine Inspections – Special Inspections – Enforcement Actions – Regulatory Oversight Program

  • License Amendments
  • License Renew al

8

slide-9
SLIDE 9

License Termination

  • Demonstrating criteria for free

release of the site

  • Task Force w ill monitor

decommissioning proposed rule and related guidance

9

slide-10
SLIDE 10

Industry Observations

  • Clear need for increased domestic

enrichment capacity

– Serve existing and future nuclear fleet – Increased energy security – Support domestic industry; create jobs

  • Leveraging proven technology and

industry experience

  • Continued Need for Predictable

and Efficient Licensing Process

10

slide-11
SLIDE 11

Industry Observations (cont.)

  • Commission oversight and

efficient hearing process is critical

  • Challenges:

– Comprehensive set of requirements unique to enrichment facilities needed – More relevant guidance, e.g., quality assurance, pre-construction activities, environmental issues – Protection of classified information and technology

11