MM Roma 10 03 2015 Riunione 27 marzo, situazione ordini - - PowerPoint PPT Presentation

mm roma 10 03 2015
SMART_READER_LITE
LIVE PREVIEW

MM Roma 10 03 2015 Riunione 27 marzo, situazione ordini - - PowerPoint PPT Presentation

MM Roma 10 03 2015 Riunione 27 marzo, situazione ordini incollatrice, Situazione camera pulita, delivery dei componenti, tempi costruzione, workflow (P.Bagnaia) stato QAQC: leak test, limbo, controlli vari


slide-1
SLIDE 1

MM Roma 10 – 03 – 2015

 Riunione 27 marzo,  situazione ordini incollatrice,  Situazione camera pulita,  delivery dei componenti,  tempi costruzione,  workflow (P.Bagnaia)  stato QAQC: leak test, limbo, controlli vari clean room, ….

slide-2
SLIDE 2

Fabien Janneau, NSW week 10 March 2015

slide-3
SLIDE 3

Part Quantity Company Responsible Cost Delay (w) Status #1 (external+gas) 27 x 1.3m (35.1m) 36 x 2.2m (79.2m) Extal (IL)

  • G. Ciapetti

Die: 3k€ Parts: 3.7 k€ 15/03/15 Shipped (1) #2 (external drift + R/O) 174 x 1.25m (217.5m) 72 x 1.5m (108m) Extal (IL)

  • G. Ciapetti

Die: 3 k€ Parts: 10.125 k€ 15/03/15 Shipped (1) #3 (mesh frame) 105 x 1m (105m) 148 x 1.25m (185m) 60 x 1.55m (93m) MIFA (NL)

  • R. Hertenberger

Die: 1.225 k€ Parts: 2 k€ ? In progress(2) #4 (R/O internal bars – 60x10x1.5) 69 x 1m (69m) 85 x 1.6m (136m) 50 x 2.1m (105m) MIFA (NL)

  • R. Hertenberger

Die: 2.525 k€ Parts: 3.9 k€ ? In progress(3) #5 (Drift internal bars – 30x10x1.5)

  • Include in #4

#6 (gas gap frame) 315 x (1000x13mm) 175 x (700x13mm) MIFA (NL)

  • R. Hertenberger

Die: 1 k€ Parts: 1.5 k€

25/02/15 Delivered(4) BB5 Mesh frame corners (SM1, SM2 and LM1) 160 (2 mod. +25%

spare)

Freiburg University

  • R. Hertenberger

Raw material

  • In progress

Gas gap frame corners 192 (3 modules) Construction sites Construction sites

  • Cooling tubes

100m (2 modules) Buntmetall

  • U. Landgraf

8 k€ + 8k€ (water-jet cut) Delivered Thermal insulator 108m ?

  • U. Landgraf

? ? Offer ? Copper plates 256 ?

  • U. Landgraf ?

? ? ?

(1) Material: Aluminum 6063-T66 ; Finish: mill finish / Alodine (2) Material: Aluminum 6060-T5 ; Finish: Surtec 650 ; Geometry: straightness 0.6/1000mm, torsion 0.4/1000mm, tolerance measurement 5.06 +/-0.025 (3) Material: Aluminum 6060-T5 ; Finish: Surtec 650 ; Tolerance measurement 10 +/-0.05 (middle) +/-0.03 (edges) Geometry:

  • straightness and torsion 0.4/1000mm for 1 and 1.6m lengths
  • straightness and torsion 0.6/2000mm for length 2100mm

(4) Material: Aluminum 6060-T5 ; Tolerance 13+/-0.1mm and 5.17 +/- 0.03 mm Geometry:

  • straightness 0.4/1000mm; torsion 0.2/1000mm

Frames – M0

  • #1 and #2 (Extal)

https://edh.cern.ch/Document/SupplyChain/DAI/5842339

  • #3 and #4 (Mifa)

https://edh.cern.ch/Document/SupplyChain/DAI/5861568

  • #6 (Mifa)

https://edh.cern.ch/Document/SupplyChain/DAI/5878986 3 modules

slide-4
SLIDE 4
slide-5
SLIDE 5

Procurement schedule – production

Cost Delay (w) March April May June July Aug. Sept. Oct. R/O PCB >200 k€ 8 Technical meeting Open tender, close tender, place the contract

Delivery

Drift PCB >200 k€ 4 Resistive foils 4-5 Frames 10<>200 k€ 4-5 Cooling 10<>200 k€ 8-9 HC 10<>200 k€ 3

  • Al. pin

10<>200 k€ 8 Mesh high cost >200 k€ 4 Mesh low cost 10<>200 k€ 4

Market survey Price inquiry or tendering process Delivery ? FDR Place orders

slide-6
SLIDE 6

Maccarrone, NSW week 10 March 2015

slide-7
SLIDE 7

Timeline

10 Mar 2015

  • S. Zimmermann

2

July 2014 June 2015 Jan 2015 Sept 2015 Jan 2016 Design Review: Green light for module-0 Module-0 Material orders

sTGC Mod.0 construct IL, CA, CL, CN

Mod-0 Materials reception

MM Mod.0 construct IT,DE, CERN MM Mod.0 construct Saclay MM Mod.1 construct GR + JINR Module-0 Test (Cosmics, GIF++, Testbeam), Integration sTGC + MM series production FDR (*)

milestones

sTGC Mod.0 construct

  • St. Petersburg

(*) so far assumed without panning for review scope

S.Zimmermann, NSW week 10 March 2015

slide-8
SLIDE 8

Required Reviews and Review Types

10 Mar 2015

  • S. Zimmermann

3

Preliminary Design (PDR), Final Design (FDR) and Production Readiness Review (PRR) are part

  • f the regular progress reporting to ATLAS, under control of TC and the Review office

During intial ATLAS construction: additionally had production site visits/reviews which proved extremely useful

slide-9
SLIDE 9

Case of NSW MM/sTGC chamber construction

Slightly different situation for MicroMegas and sTGC chamber construction – Design Review end of July 2014 somewhat between in a Preliminary Design and Final Design Review

  • FDR: Green light for module-0
  • FDR: Green light to start procurement/tender process for mass prod. Materials
  • PDR: No full-size prototype had been built before
  • PDR: MM p

r esented assembly procedure defined only “on paper”, not executed in a prototype – prove that it works pending

  • PDR: Several decision remained to be taken

– MM: Mesh specification (pitch) – MM: Arrange resistive strips with an angle w.r.t. readout strips or not – MM: Resistive Foil technique – sputtering versus screen printing – Detailed Grounding scheme including mechanical elements – Details of mounting chambers to spacer frame – Details of electronics + service integration

10 Mar 2015

  • S. Zimmermann

4

slide-10
SLIDE 10

Post module-0

Next Review after module-0 completion must

  • Demonstrate that requirements in terms of mechanical precision have been achieved

(measurement results)

  • Demonstrate that requirements in terms of operational behavior (HV current, noise,

dead channels, …) h a ve been met

  • Demonstrate all choices left open at the July 2014 Design Review have been settled (NB:

this does not rule out having different sites use different well defined methods, eg MM vacuum bad versus stiffback method)

  • Present and justify any changes to the construction procedure and manual since the July

2014 Design Review, and p r ove no further “will be developed during construction” points are left

  • Demonstrate material qualifications have been completed
  • Demonstrate QA/QC protocol including detailed (possible site specific) methods
  • Prove sufficient resources exist to complete production according to schedule, present

detailed work flow and resource loaded schedule (hours per step, FTEs incl. names, work hours per week)

  • Provide information/show source of all materisls, provide delivery schedule,

demonstrate logistics flow

10 Mar 2015

  • S. Zimmermann

5

Somewhat made more complicated by module-0s not all completed at the same time …

slide-11
SLIDE 11

MM Proposal (NSW management)

2. Review (1 day meeting, presentation + prior documentation based, ATLAS Review panel)

  • Report on module-0 construction experience
  • Present module-0 results, prove requirements are

met

  • Present/justify changes to (global) construction

procedure

  • Report final material choices, present material

qualification results

  • Present details on orders, chosen manufacturers,

material delivery schedule

  • Logisitics work flow from CERN to institutes
  • QA/QC database infrastructure

10 Mar 2015

  • S. Zimmermann

6

  • 3. Site visits
  • Review site specific construction

procedure

  • Review site specific QA/QC

implementation

  • Review resources (manpower),

resource loaded schedule

  • INFN/DE: September
  • Saclay: November/December
  • Dubna/Thessaloniki: December,

including review of module-1 results

  • Review committee consisting of MM

experts (other sites) + 1-2 external members

  • 1. MM Mechanical Workshop after module-0 completion --- discuss construction experience,

possible problems, agree (potential) changes to construction procedure w.r.t. PDR one, define definite and final procedures.

End July/Early September – before final material order MM construction groups. (end) June

  • 4. Schedule Review (overall MM construct.) – 0.5 day meeting, ATLAS Review panel

Dec/Jan)

slide-12
SLIDE 12

MM Proposal -- Alternative

2. Review (1 day meeting, presentation + prior documentation based, ATLAS Review panel)

  • Report on module-0 construction experience
  • Present module-0 results, prove requirements are

met

  • Present/justify changes to (global) construction

procedure

  • Report final material choices, present material

qualification results

  • Present details on orders, chosen manufacturers,

material delivery schedule

  • Logisitics work flow from CERN to institutes
  • QA/QC database infrastructure

10 Mar 2015

  • S. Zimmermann

7

  • 4. Site visits
  • Review site specific construction

procedure

  • Review site specific QA/QC

implementation

  • October 2015 to January 2016
  • For Dubna/Thess including review
  • f module-1 results
  • Review committee consisting of MM

experts (other sites) + 1-2 external members

  • 1. MM Mechanical Workshop after module-0 completion --- discuss construction experience,

possible problems, agree (potential) changes to construction procedure w.r.t. PDR one, define definite and final procedures.

End July/Early September – before final material order MM construction groups. (end) June

  • 5. PRR (review manpower, resources, resource loaded schedule)

Nov/Dec