MM Roma 10 – 03 – 2015
Riunione 27 marzo, situazione ordini incollatrice, Situazione camera pulita, delivery dei componenti, tempi costruzione, workflow (P.Bagnaia) stato QAQC: leak test, limbo, controlli vari clean room, ….
MM Roma 10 03 2015 Riunione 27 marzo, situazione ordini - - PowerPoint PPT Presentation
MM Roma 10 03 2015 Riunione 27 marzo, situazione ordini incollatrice, Situazione camera pulita, delivery dei componenti, tempi costruzione, workflow (P.Bagnaia) stato QAQC: leak test, limbo, controlli vari
Riunione 27 marzo, situazione ordini incollatrice, Situazione camera pulita, delivery dei componenti, tempi costruzione, workflow (P.Bagnaia) stato QAQC: leak test, limbo, controlli vari clean room, ….
Fabien Janneau, NSW week 10 March 2015
Part Quantity Company Responsible Cost Delay (w) Status #1 (external+gas) 27 x 1.3m (35.1m) 36 x 2.2m (79.2m) Extal (IL)
Die: 3k€ Parts: 3.7 k€ 15/03/15 Shipped (1) #2 (external drift + R/O) 174 x 1.25m (217.5m) 72 x 1.5m (108m) Extal (IL)
Die: 3 k€ Parts: 10.125 k€ 15/03/15 Shipped (1) #3 (mesh frame) 105 x 1m (105m) 148 x 1.25m (185m) 60 x 1.55m (93m) MIFA (NL)
Die: 1.225 k€ Parts: 2 k€ ? In progress(2) #4 (R/O internal bars – 60x10x1.5) 69 x 1m (69m) 85 x 1.6m (136m) 50 x 2.1m (105m) MIFA (NL)
Die: 2.525 k€ Parts: 3.9 k€ ? In progress(3) #5 (Drift internal bars – 30x10x1.5)
#6 (gas gap frame) 315 x (1000x13mm) 175 x (700x13mm) MIFA (NL)
Die: 1 k€ Parts: 1.5 k€
25/02/15 Delivered(4) BB5 Mesh frame corners (SM1, SM2 and LM1) 160 (2 mod. +25%
spare)
Freiburg University
Raw material
Gas gap frame corners 192 (3 modules) Construction sites Construction sites
100m (2 modules) Buntmetall
8 k€ + 8k€ (water-jet cut) Delivered Thermal insulator 108m ?
? ? Offer ? Copper plates 256 ?
? ? ?
(1) Material: Aluminum 6063-T66 ; Finish: mill finish / Alodine (2) Material: Aluminum 6060-T5 ; Finish: Surtec 650 ; Geometry: straightness 0.6/1000mm, torsion 0.4/1000mm, tolerance measurement 5.06 +/-0.025 (3) Material: Aluminum 6060-T5 ; Finish: Surtec 650 ; Tolerance measurement 10 +/-0.05 (middle) +/-0.03 (edges) Geometry:
(4) Material: Aluminum 6060-T5 ; Tolerance 13+/-0.1mm and 5.17 +/- 0.03 mm Geometry:
https://edh.cern.ch/Document/SupplyChain/DAI/5842339
https://edh.cern.ch/Document/SupplyChain/DAI/5861568
https://edh.cern.ch/Document/SupplyChain/DAI/5878986 3 modules
Cost Delay (w) March April May June July Aug. Sept. Oct. R/O PCB >200 k€ 8 Technical meeting Open tender, close tender, place the contract
Delivery
Drift PCB >200 k€ 4 Resistive foils 4-5 Frames 10<>200 k€ 4-5 Cooling 10<>200 k€ 8-9 HC 10<>200 k€ 3
10<>200 k€ 8 Mesh high cost >200 k€ 4 Mesh low cost 10<>200 k€ 4
Market survey Price inquiry or tendering process Delivery ? FDR Place orders
Maccarrone, NSW week 10 March 2015
10 Mar 2015
2
July 2014 June 2015 Jan 2015 Sept 2015 Jan 2016 Design Review: Green light for module-0 Module-0 Material orders
sTGC Mod.0 construct IL, CA, CL, CN
Mod-0 Materials reception
MM Mod.0 construct IT,DE, CERN MM Mod.0 construct Saclay MM Mod.1 construct GR + JINR Module-0 Test (Cosmics, GIF++, Testbeam), Integration sTGC + MM series production FDR (*)
milestones
sTGC Mod.0 construct
(*) so far assumed without panning for review scope
S.Zimmermann, NSW week 10 March 2015
10 Mar 2015
3
Preliminary Design (PDR), Final Design (FDR) and Production Readiness Review (PRR) are part
During intial ATLAS construction: additionally had production site visits/reviews which proved extremely useful
Slightly different situation for MicroMegas and sTGC chamber construction – Design Review end of July 2014 somewhat between in a Preliminary Design and Final Design Review
r esented assembly procedure defined only “on paper”, not executed in a prototype – prove that it works pending
– MM: Mesh specification (pitch) – MM: Arrange resistive strips with an angle w.r.t. readout strips or not – MM: Resistive Foil technique – sputtering versus screen printing – Detailed Grounding scheme including mechanical elements – Details of mounting chambers to spacer frame – Details of electronics + service integration
10 Mar 2015
4
Next Review after module-0 completion must
(measurement results)
dead channels, …) h a ve been met
this does not rule out having different sites use different well defined methods, eg MM vacuum bad versus stiffback method)
2014 Design Review, and p r ove no further “will be developed during construction” points are left
detailed work flow and resource loaded schedule (hours per step, FTEs incl. names, work hours per week)
demonstrate logistics flow
10 Mar 2015
5
Somewhat made more complicated by module-0s not all completed at the same time …
2. Review (1 day meeting, presentation + prior documentation based, ATLAS Review panel)
met
procedure
qualification results
material delivery schedule
10 Mar 2015
6
procedure
implementation
resource loaded schedule
including review of module-1 results
experts (other sites) + 1-2 external members
possible problems, agree (potential) changes to construction procedure w.r.t. PDR one, define definite and final procedures.
End July/Early September – before final material order MM construction groups. (end) June
Dec/Jan)
2. Review (1 day meeting, presentation + prior documentation based, ATLAS Review panel)
met
procedure
qualification results
material delivery schedule
10 Mar 2015
7
procedure
implementation
experts (other sites) + 1-2 external members
possible problems, agree (potential) changes to construction procedure w.r.t. PDR one, define definite and final procedures.
End July/Early September – before final material order MM construction groups. (end) June
Nov/Dec