PROTECT Stratford District Council O&S Briefing
23rd March 2014 Tonino Ciuffini & John Parmiter
PROTECT
www.cswbroadband.org.uk
PROTECT
Stratford District Council
- We are pleased to be able to provide this very positive news for Stratford
District Council.
- The District benefits from a significant share of BDUK funding.
- The district features in major elements of the first two phases of the roll-
- ut of Superfast Broadband.
- It is anticipated that approximately 47% of the targeted premises in
Stratford district will be upgraded to Next Generation Access during the first two phases.
- The CSW Project Team have met all expected target dates from BDUK for
the management of this project.
- BT is presently slightly ahead of expected target dates for survey and
deployment.
PROTECT
www.cswbroadband.org.uk
PROTECT
Investment
- The total number of premises passed by the CSW Broadband project is 51,685 or
77% of the Intervention Area.
- The number of premise in Stratford District that will be upgraded as a result of the
project is 21,614 which equates to 42% of the total number of premises in the CSW region being upgraded.
- The Total Public Subsidy for the project throughout the region is £8,890,000. For
Stratford District the public investment is £3,317,638 (42% of total) of which BDUK is contributing £1,858,842.
- The Local Authority investment in Stratford District is £1,858,842 of which
Warwickshire County Council are contributing £1,385,142 (75%) and Stratford District Council are contributing £463,700 (25%).
- Warwickshire County Council is investing 46% of its overall contribution to the roll-
- ut of Broadband in Stratford.
PROTECT
www.cswbroadband.org.uk
PROTECT
www.cswbroadband.org.uk
PROTECT
Phase 1 Roll-out
- BT is planning to implement 52 cabinets as part of the Phase 1
roll-out throughout CSW. Of these 52 cabinets 31 are located in Stratford District and equate to approx. 7190 Total Homes Passed (THP), or 33% of the premises in the Stratford District to be upgraded as part of the project.
- Surveys of these 31 cabinets have been completed and build
work has commenced. According to the Implementation Plan installation for the Phase 1 cabs is scheduled to be completed by June 2014 and ready for service by September 2014.
PROTECT
www.cswbroadband.org.uk
PROTECT
7th April 2014
DETAILED FORECAST REPORT
Exchange Cab Number Technology THP SNITTERFIELD 2 FTTC 292 STRATFORD ON AVON 6 FTTC 94 STRATFORD ON AVON 15 FTTC 183 STRATFORD ON AVON 34 FTTC 175 STRATFORD ON AVON 35 FTTC 83 STRATFORD ON AVON 36 FTTC 111 STRATFORD ON AVON 39 FTTC 243 STRATFORD ON AVON 45 FTTC 84 STRATFORD ON AVON 46 FTTC 80 STRATFORD ON AVON 47 FTTC 140 STRATFORD ON AVON 51 FTTC 101 STRATFORD ON AVON 54 FTTC 132 STRATFORD ON AVON 62 FTTC 104 HENLEY- IN-ARDEN 2 FTTC 203 2025