Introduction of the Presenter Regulator Compliance Process Flow - - PowerPoint PPT Presentation

introduction of the presenter regulator compliance
SMART_READER_LITE
LIVE PREVIEW

Introduction of the Presenter Regulator Compliance Process Flow - - PowerPoint PPT Presentation

CONTENTS Introduction of the Presenter Regulator Compliance Process Flow PSP Departments Load Forecast Generation Planning Transmission Planning Maximum Generation Despatch Resource Planning Ongoing Projects


slide-1
SLIDE 1
slide-2
SLIDE 2
slide-3
SLIDE 3

CONTENTS

  • Introduction of the Presenter
  • Regulator Compliance
  • Process Flow
  • PSP Departments
  • Load Forecast
  • Generation Planning
  • Transmission Planning
  • Maximum Generation Despatch
  • Resource Planning
  • Ongoing Projects
  • Future Projects
slide-4
SLIDE 4

Department of Power System Planning

  • Engr. Salman Shakeel

M.Sc Electrical Engineering, UET, Lahore Working as Assistant Manager ( Transmission Planning ) O/o General Manager ( Power System Planning ) National Transmission & Despatch Company Limited

3 25-June-18 NTDC

slide-5
SLIDE 5

According to the National Transmission & Despatch Company (NTDC) License and Grid Code;

slide-6
SLIDE 6

START END

Load Forecast & Generation Planning Transmission Planning Resource Planning

Generation Plan Load Forecast Transmission Investment Plan PC-II Transmission Expansion Plan PC-I

slide-7
SLIDE 7
  • Load Forecast and Generation Planning
  • Transmission Planning
  • Resource Planning
slide-8
SLIDE 8
slide-9
SLIDE 9

LOAD FORECAST

slide-10
SLIDE 10
  • Medium Term (5-10 years)
  • Used in Transmission System Planning
  • PMS software developed by HARZA (USA)
  • Long Term (20-25 years)
  • Used in Generation Expansion Planning
  • E-Views software developed by Quantitative Micro

Software (California USA)

FORECAST METHODOLOGIES & TOOLS

slide-11
SLIDE 11

PMS MODEL OUTPUTS

1) DISCOs’ Forecast

  • Substation-wise Forecast
  • Category-wise Forecast
  • Summary of each DISCO
  • Civil Administrative Division –wise Forecast
  • Civil Administrative District–wise Forecast
  • Overloaded 132kV Substations
  • Month-wise Demand Projections

2) Province-wise Forecast 3) Consolidated Forecast of whole Country

slide-12
SLIDE 12

National Transmission & Despatch Company Limited

12 7/30/2018 NTDCL

Geographic Territory of DISCOs

TESCO: Federally Administered Tribal Areas (FATA)) and Frontier Regions-FRs. PESCO : All districts of Khyber Pakhtunkhwa MEPCO: The area from Sahiwal to Sadiqabad, Bahawalnager to Bahawalpur, Tounsa Shari to Rajanpur, FESCO: The districts of Faisalabad, Sargodha, Mianwali, Khushab, Jhang, Bhakker, T.T Singh HESCO: All Province of Sindh except Karachi, Sukkur, Ghotki, Khairpur, Kashmore/Kandhkot, Jacobabad, Shikarpur, Larkana, Kambar/Shahdadkot, Dadu and Some Portions of Jamshoro, Naushehro Feroze, Shaheed Benazirabad and Rahimyar Khan

GEPCO: Districts of Gujranwala, Hafizabad, Sialkot, Narowal, Gujrat and Mandi Bahauddin LESCO: The Districts of Lahore, Kasur, Okara and Sheikhupura. SEPCO:Districts Sukkur, Ghotki, Khairpur, Kashm

  • re/Kandhkot,Jacobabad, Shikarpur, Larkana, Ka

mbar/ Shahdadkot,Dadu and Some Portions of Jamshoro, Naushehro Feroze, Shaheed Benazirabad and Rahimyar Khan.

IESCO: The districts

  • f Rawalpindi,

Chakwal, Attock, Jhelum and Federal Capital Islamabad

slide-13
SLIDE 13

Reports Being Published by Load Forecast Section

  • PMS for each DISCO and PEPCO since 1964.
  • Regression forecast since 1994.
  • Indicative Generation Capacity Expansion Plan

(IGCEP 2018-2040)

  • Power Balance/Demand Vs Supply Power Data (2018-

2025)

  • Data Reference Book since 2008. (2017-2018)
  • Power System Statistics. (43rd Edition 2017-2018)
slide-14
SLIDE 14

DISCO-wise Peak Demand Forecast (MW)

slide-15
SLIDE 15
slide-16
SLIDE 16

GENERATION PLANNING OBJECTIVE

slide-17
SLIDE 17

Generation plan caters the following Aspects:

capacities to install to meet the demand & ensure an appropriate level of reliability? to pick the best combination among the different technologies at hand? to locate the new generation facilities with respect to fuel handling , availability of water and requisite infrastructure facilities? to incorporate new generation into the system?

slide-18
SLIDE 18

Generation Planning Softwares

  • WASP (Wien Automatic System Planning) 1994 NPP by Acres Canada
  • SYPCO (System Production Costing Program) 2011 NPSEP by SNC

Lavalin Canada

  • PDPAT-II Least Cost Generation Plan 2015 by JAICA
  • PLEXOs Australia (Purchase Under Process)
  • Power Balance/ Demand Vs Supply
slide-19
SLIDE 19

Wien Automatic System Planning (WASP)

  • Developed by IAEA, Austria
  • Gives the economically optimal generation expansion

plan within user-specified constraints

  • Used to develop the first National Power Plan (NPP) of

WAPDA in 1994

  • NTDC is currently using WASP-IV (the latest version)
  • Options for selection of Hydel plants are limited
slide-20
SLIDE 20

System Production Costing Program (SYPCO)

  • Developed by SNC Lavalin International, Canada
  • Compares the cost of alternative generation

scenarios to serve a given load over a selected period

  • f time
  • Was used to develop long term National Power

System Expansion Plan (NPSEP) in 2011

slide-21
SLIDE 21
slide-22
SLIDE 22

Transmission Planning Objective

slide-23
SLIDE 23

Transmission Planning Criteria

slide-24
SLIDE 24

Transmission Planning Section is Responsible for:

  • Preparing/updating transmission expansion plan.
  • Proposing new substations and transmission lines (PC-1).
  • Proposing site & Interconnection schemes for power dispersal
  • f all types of new power plants, both in public and private

sectors.

  • Review
  • f

feasibility studies/reports submitted by consultants.

  • Providing technical support/consultancy services to the

upcoming IPPs, PAEC, WAPDA, GENCO’s, DISCO’s and K- Electric.

  • Interaction with NEPRA, MoW&P and International donor

agencies for transmission projects/issues.

slide-25
SLIDE 25

 Transmission planning is based on studies with

following two key inputs:

  • Load Forecast
  • Generation Plan

 Following studies are carried out with the help of

state-of-the-art Power System Simulators for Engineers (PSS/E) software:

  • Load Flow
  • Short Circuit
  • Transient Stability
  • Power Quality Studies

TRANSMISSION PLANNING

slide-26
SLIDE 26

Softwares Being Used by Transmission Planning Section

 Following software tools, being used by leading consultants and

electric utilities worldwide, are available in Planning (Power) Section: 1. Power System Simulator for Engineering (PSS/E)

  • Used for performing load flow, short circuit , transient stability studies

& power quality studies.

  • Used in most of the transmission planning studies.

2. Power System Computer Aided Design (PSCAD)

  • Used for performing electromagnetic switching overvoltage & other

equipment design related studies.

  • Other advanced level equipment design studies, such as, HVDC, FACTS

devices etc.

3. Real Time Power System Simulator (RTPSS)

  • Used for real-time transient analysis
  • Used for relay testing
slide-27
SLIDE 27

Transmission System Information

Description 500 kV 220 kV Generation Addition (MW)

  • No. of Grid

Stations Capacity (MVA) Transmission Lines (km)

  • No. of

Grid Stations Capacity (MVA) Transmission Lines (km) Installed Capacity as on 31-5-2018 16 20850 5326 42 28610 10386 30968 FY 2018-19

  • 3150

396 03 2000 203 3322 FY 2019-20

  • 391

05 3570 478 2271 FY 2020-21 03 3900 351 01 1890 260 5239 FY 2021-22 04 6000 1089 06 8000 1407 5204 Total 23 62

slide-28
SLIDE 28

Existing Transmission Network of NTDC

slide-29
SLIDE 29

Planned Transmission Network of NTDC (2021-22)

slide-30
SLIDE 30

National Transmission & Despatch Company Limited

30 7/30/2018 NTDC

Max Generation Despatch

  • Generation is dispatched from power plants to end consumers through

500/220/132 kV Transmission Network.

  • Installed capacity:

27,596 MW

  • De-rated capacity:

25,899 MW.

  • Maximum Despatch: 19,070 MW (20-August-2017 9pm)
  • Installed capacity:

30,968 MW

  • De-rated capacity:

29,257 MW.

  • Maximum Despatch: 20, 795 MW (11-June-2018 9.15pm)
slide-31
SLIDE 31
slide-32
SLIDE 32

Responsibilities of Resource Planning Section

  • Preparation of PC-I(s) for NTDC Development Projects
  • Preparation of PC-II(s) for Feasibility Studies of Mega

Projects

  • Preparation of Investment Plan
  • Financing arrangements through International Financing

Agencies

  • Preparation of PC-I(s) and PC-II(s) for Public Sector Power

Projects

slide-33
SLIDE 33

NTDC Development Projects include:

  • New 500 & 220 kV transmission lines and Grid stations for

strengthening of NTDC network for reliable and efficient transmission of Power to DISCO networks

  • Augmentation of existing 500 & 220 kV Transmission

System

  • Interconnection of Power Plants with National Grid for

Evacuation of Power generated from Power Plants

slide-34
SLIDE 34
slide-35
SLIDE 35
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion Grid Station Projects 1- 220 kV GIS Ghazi Road Lahore G/S 2x250 30 31.07.2018 2- 220kV Chakdara G/S 2x250 85 31.07.2018 3- 220kV D.I. Khan G/S 2x250 100 30.09.2018 4- 220kV Rawat G/S Extension/Augmentation of TF (2x160 to 2x250 + 1x250) 430

  • 30.09.2018

5- 220 kV Nowshera G/S 3x250 10 30.09.2018

Ongoing ing Project cts

slide-36
SLIDE 36

Sr. No. Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 6- 500kV Rawat Augmentation of one ATB 1x450 to 1x750

  • 28.2.2019

7- 220kV Quetta Industrial G/S Augmentation of TFs 2x160 to 2x250

  • 30.10.2018

8- Extension/Augmentation at Existing Grid Stations 1050 (500kV) 6096 (220kV)

  • 30.06.2019

9- Conversion of Four 220kV Grids from AIS to GIS

  • 30.06.2019

10- 220kV Lalian New G/S 3x250 8 30.09.2019 Transmission Line 11- 3rd 500 kV Circuit from Jamshoro to Rahim Yar Khan

  • 600

31.12.2018 12- Improvement & Upgradation of Protection System to Avoid the Frequent Trippings in South Areas

  • 31.12.2018

Ongoin ing g Proje ject cts

slide-37
SLIDE 37
slide-38
SLIDE 38
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 969 MW Neelum Jhelum HPP

  • Ph-1: 150km

Ph-2: 130km Ph-2: Feb 2019 2- 1200 MW Thar CFPP (500 kV Thar – Matiari T/L)

  • 250

30.06.2018 3- 1320 MW Imported Coal Power Plant at HUBCO

  • Ph-1: 01 km

Ph-2: 220 km Ph-1: June, 2018 Ph-2: Dec, 2019 4- 1320 MW Imported CFPP at Sahiwal (Addition of ATB) 1x600

  • Dec, 2018

5- 1200 MW LNG Based Power Plant at Balloki (Addition of ATB) 1x750 40 TL: 30.04.2018 ATB: July, 2018 6- 500kV D/C T/L from Guddu- Muzzafargarh (747 MW Guddu)

  • 276

Dec, 2018

Ongoing ing Powe wer Evacuat ation n Project cts

slide-39
SLIDE 39

Sr. No. Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 7- Reinforcement in Islamabad and Burhan area for Tarbela 4th Extension:

  • i) Replacement of existing

220 kV Tarbela-Burhan D/C T/L (35km)

  • 35

30.06.2018 ii) Replacement of existing 220 kV Tarbela-Burhan- ISPR D/C T/L (62.5km)

  • 62.5

June, 2019 8- 147 MW Patrind HPP (Phase-II)

  • 70 (132kV)

June, 2018 9- Evacuation Of Power from 1230MW RLNG Power Plant At Trimmu 250 220kV: 100 132kV: 15

  • Aug. 2018

10- Extension work at 500kV Jamshoro G/S 1x450

  • 31.12.2018

11- 1320 MW Bin Qasim Plant (Phase-II)

  • 130

31.12.2018

Ongoing ing Powe wer Evacuat ation n Project cts

slide-40
SLIDE 40
slide-41
SLIDE 41
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 220 kV Zhob G/S 2x160 220 2019-20 2- 220kV Mirpur Khas G/S 2x250 70 2019-20 3- 220kV Zero Point G/S 3x250 24 2019-20 4- 220kV Punjab University 3x250 4 2019-20 5- 220kV Gharo G/S 2x250 85 (220kV) 20 (132kV) 2019-20 6- New 220kV Guddu-Uch-Sibbi S/C TL

  • 360

2019-20 7- Evacuation of Power from K2/K3 Nuclear Power Plants

  • 116

2019-20

Pl Planned d Pr Projects jects (2019-20) 20)

slide-42
SLIDE 42

Sr. No. Name of the Project MVA Capacity Addition in T/L (km) Expected Completion

8- Evacuation of Power from 2x660 MW Coal Based SSRL/ SECL Power Plant at Thar

  • 275

2019-20 9- Installation of Series Compensation for Enhancement in Transmission Capacity

  • 2019-20

10- Procurement of 5 No 220kV Mobile Grid Stations

  • 2019-20

11-

Evacuation of Power from 1224MW Wind Power Plants at Jhimpir Clusters 1250 220kV: 35 132kV: 220 2019-20

Planned d Projects ects (2019-20 20)

slide-43
SLIDE 43
slide-44
SLIDE 44
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 500 kV Faisalabad West GS 2x750 + 3x250 125 (220 kV) 32 (500 kV) 2020-21 2- 500kV Chakwal G/S 2x450 + 4x160 33 2020-21 3- 500 kV Lahore North 2x750 110 (500 kV) 15 (220 kV) 2020-21 4- 220kV Mastung G/S 2x250 120 2020-21 5- Evacuation of Power from Karot and Azad Pattan HPPs

  • 10

2020-21

Planned d Projects ects (2020-21 21)

slide-45
SLIDE 45
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 6- Evacuation of Power from Tarbela 5th Extension

  • 53

2020-21 7- Evacuation of Power from 350 MW Siddiqsons Ltd.

  • 40

2020-21 8- Evacuation of Power from 660 MW Lucky Electric Power Company

  • 13

2020-21 9- 500 kV HVAC T/Lines for Interconnection of HVDC Converter Station at Lahore & Matiari with existing HVAC System

  • 60

2020-21

Planned d Projects ects (2020-21 21)

slide-46
SLIDE 46
slide-47
SLIDE 47
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 500 kV Islamabad West G/S 2x750 + 3x250 35 (220 kV) 27(500 kV) 2021-22 2- 500 kV Peshawar New (Nowshera) GS, CASA-1000 2x750 15 (500 kV) 24 (220 kV) 2021-22 3- 220kV Jamrud G/S 2 x 250 20 2021-22 4- 220kV Jauharabad 2x250 12 2021-22 5- Enterprise Resource Planning System. (ERP)

  • 2021-22

6- Evacuation of Power from Suki Kinari, Kohala and Mahal Hydro Power Projects

  • 500kV

697 2021-22

Planned d Projects ects (2021-22 22)

slide-48
SLIDE 48
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 7- 220kV Larkana Grid Station 3x250 65 2021-22 8- Interconnection Scheme for CASA-1000 (HVDC Part)

  • HVDC

100 km 2021-21 9- Evacuation of Power from 2160 MW Dasu Hydro Power Project (Phase-I)

  • 765kV

250 2021-22 10- Upgradation/Extension of NTDC's Telecom & SCADA System

  • 2021-22

11- 220kV Head Faqirian 2x160 88 2021-22 12- 500kV Moro Grid Station 2x750 + 3x250

  • 2021-22

13- 220kV Dharki-Rahimyar khan- Bahawalpur D/C T/L

  • 335

2021-22

Planned d Projects ects (2021-22 22)

slide-49
SLIDE 49
  • Sr. No.

Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 14- 220 kV Gujranwala-II 2x250 20 2021-22 15- 220 kV Arifwala 2x250 10 2021-22 16- 220 kV Sialkot 2x250 20 2021-22 17- 220kV Kohat G/S 2x250 50 2021-22 18- 220kV Kamra G/S 2x250 5 2021-22 19- 220 kV Nawabshah 3x250 65 2021-22

Planned d Projects ects (2021-22 22)

slide-50
SLIDE 50
slide-51
SLIDE 51

Sr. No. Name of the Project Capacity (MVA) Addition in T/L (km) Status Estimated Cost (MUS$) Required year

  • f Completion

1- Rehabilitation of existing Grid Stations and Transmission Lines of NTDC system

  • Under Study

300 2022-23 2- 500kV Sialkot Grid Station 2x750 50 km (500 kV) Under Study 100 2024-25 3- 500kV Quetta Grid Station along with 500 kV Quetta- D.G Khan T/L 2x750 350 km (500 kV) Concept Paper submitted on 12.12.2017 240 2024-25 4- 220kV Khuzdar - Gawadar T/L along with associated 220 kV G/S 2x250 670 km (220 kV) Concept Paper submitted 15.11.2017 285 2024-25

Future ure Project cts

slide-52
SLIDE 52

National Transmission & Despatch Company Limited

52 7/30/2018 NTDCL

THANK YOU.