Introduction of the Presenter Regulator Compliance Process Flow - - PowerPoint PPT Presentation
Introduction of the Presenter Regulator Compliance Process Flow - - PowerPoint PPT Presentation
CONTENTS Introduction of the Presenter Regulator Compliance Process Flow PSP Departments Load Forecast Generation Planning Transmission Planning Maximum Generation Despatch Resource Planning Ongoing Projects
CONTENTS
- Introduction of the Presenter
- Regulator Compliance
- Process Flow
- PSP Departments
- Load Forecast
- Generation Planning
- Transmission Planning
- Maximum Generation Despatch
- Resource Planning
- Ongoing Projects
- Future Projects
Department of Power System Planning
- Engr. Salman Shakeel
M.Sc Electrical Engineering, UET, Lahore Working as Assistant Manager ( Transmission Planning ) O/o General Manager ( Power System Planning ) National Transmission & Despatch Company Limited
3 25-June-18 NTDC
According to the National Transmission & Despatch Company (NTDC) License and Grid Code;
START END
Load Forecast & Generation Planning Transmission Planning Resource Planning
Generation Plan Load Forecast Transmission Investment Plan PC-II Transmission Expansion Plan PC-I
- Load Forecast and Generation Planning
- Transmission Planning
- Resource Planning
LOAD FORECAST
- Medium Term (5-10 years)
- Used in Transmission System Planning
- PMS software developed by HARZA (USA)
- Long Term (20-25 years)
- Used in Generation Expansion Planning
- E-Views software developed by Quantitative Micro
Software (California USA)
FORECAST METHODOLOGIES & TOOLS
PMS MODEL OUTPUTS
1) DISCOs’ Forecast
- Substation-wise Forecast
- Category-wise Forecast
- Summary of each DISCO
- Civil Administrative Division –wise Forecast
- Civil Administrative District–wise Forecast
- Overloaded 132kV Substations
- Month-wise Demand Projections
2) Province-wise Forecast 3) Consolidated Forecast of whole Country
National Transmission & Despatch Company Limited
12 7/30/2018 NTDCL
Geographic Territory of DISCOs
TESCO: Federally Administered Tribal Areas (FATA)) and Frontier Regions-FRs. PESCO : All districts of Khyber Pakhtunkhwa MEPCO: The area from Sahiwal to Sadiqabad, Bahawalnager to Bahawalpur, Tounsa Shari to Rajanpur, FESCO: The districts of Faisalabad, Sargodha, Mianwali, Khushab, Jhang, Bhakker, T.T Singh HESCO: All Province of Sindh except Karachi, Sukkur, Ghotki, Khairpur, Kashmore/Kandhkot, Jacobabad, Shikarpur, Larkana, Kambar/Shahdadkot, Dadu and Some Portions of Jamshoro, Naushehro Feroze, Shaheed Benazirabad and Rahimyar Khan
GEPCO: Districts of Gujranwala, Hafizabad, Sialkot, Narowal, Gujrat and Mandi Bahauddin LESCO: The Districts of Lahore, Kasur, Okara and Sheikhupura. SEPCO:Districts Sukkur, Ghotki, Khairpur, Kashm
- re/Kandhkot,Jacobabad, Shikarpur, Larkana, Ka
mbar/ Shahdadkot,Dadu and Some Portions of Jamshoro, Naushehro Feroze, Shaheed Benazirabad and Rahimyar Khan.
IESCO: The districts
- f Rawalpindi,
Chakwal, Attock, Jhelum and Federal Capital Islamabad
Reports Being Published by Load Forecast Section
- PMS for each DISCO and PEPCO since 1964.
- Regression forecast since 1994.
- Indicative Generation Capacity Expansion Plan
(IGCEP 2018-2040)
- Power Balance/Demand Vs Supply Power Data (2018-
2025)
- Data Reference Book since 2008. (2017-2018)
- Power System Statistics. (43rd Edition 2017-2018)
DISCO-wise Peak Demand Forecast (MW)
GENERATION PLANNING OBJECTIVE
Generation plan caters the following Aspects:
capacities to install to meet the demand & ensure an appropriate level of reliability? to pick the best combination among the different technologies at hand? to locate the new generation facilities with respect to fuel handling , availability of water and requisite infrastructure facilities? to incorporate new generation into the system?
Generation Planning Softwares
- WASP (Wien Automatic System Planning) 1994 NPP by Acres Canada
- SYPCO (System Production Costing Program) 2011 NPSEP by SNC
Lavalin Canada
- PDPAT-II Least Cost Generation Plan 2015 by JAICA
- PLEXOs Australia (Purchase Under Process)
- Power Balance/ Demand Vs Supply
Wien Automatic System Planning (WASP)
- Developed by IAEA, Austria
- Gives the economically optimal generation expansion
plan within user-specified constraints
- Used to develop the first National Power Plan (NPP) of
WAPDA in 1994
- NTDC is currently using WASP-IV (the latest version)
- Options for selection of Hydel plants are limited
System Production Costing Program (SYPCO)
- Developed by SNC Lavalin International, Canada
- Compares the cost of alternative generation
scenarios to serve a given load over a selected period
- f time
- Was used to develop long term National Power
System Expansion Plan (NPSEP) in 2011
Transmission Planning Objective
Transmission Planning Criteria
Transmission Planning Section is Responsible for:
- Preparing/updating transmission expansion plan.
- Proposing new substations and transmission lines (PC-1).
- Proposing site & Interconnection schemes for power dispersal
- f all types of new power plants, both in public and private
sectors.
- Review
- f
feasibility studies/reports submitted by consultants.
- Providing technical support/consultancy services to the
upcoming IPPs, PAEC, WAPDA, GENCO’s, DISCO’s and K- Electric.
- Interaction with NEPRA, MoW&P and International donor
agencies for transmission projects/issues.
Transmission planning is based on studies with
following two key inputs:
- Load Forecast
- Generation Plan
Following studies are carried out with the help of
state-of-the-art Power System Simulators for Engineers (PSS/E) software:
- Load Flow
- Short Circuit
- Transient Stability
- Power Quality Studies
TRANSMISSION PLANNING
Softwares Being Used by Transmission Planning Section
Following software tools, being used by leading consultants and
electric utilities worldwide, are available in Planning (Power) Section: 1. Power System Simulator for Engineering (PSS/E)
- Used for performing load flow, short circuit , transient stability studies
& power quality studies.
- Used in most of the transmission planning studies.
2. Power System Computer Aided Design (PSCAD)
- Used for performing electromagnetic switching overvoltage & other
equipment design related studies.
- Other advanced level equipment design studies, such as, HVDC, FACTS
devices etc.
3. Real Time Power System Simulator (RTPSS)
- Used for real-time transient analysis
- Used for relay testing
Transmission System Information
Description 500 kV 220 kV Generation Addition (MW)
- No. of Grid
Stations Capacity (MVA) Transmission Lines (km)
- No. of
Grid Stations Capacity (MVA) Transmission Lines (km) Installed Capacity as on 31-5-2018 16 20850 5326 42 28610 10386 30968 FY 2018-19
- 3150
396 03 2000 203 3322 FY 2019-20
- 391
05 3570 478 2271 FY 2020-21 03 3900 351 01 1890 260 5239 FY 2021-22 04 6000 1089 06 8000 1407 5204 Total 23 62
Existing Transmission Network of NTDC
Planned Transmission Network of NTDC (2021-22)
National Transmission & Despatch Company Limited
30 7/30/2018 NTDC
Max Generation Despatch
- Generation is dispatched from power plants to end consumers through
500/220/132 kV Transmission Network.
- Installed capacity:
27,596 MW
- De-rated capacity:
25,899 MW.
- Maximum Despatch: 19,070 MW (20-August-2017 9pm)
- Installed capacity:
30,968 MW
- De-rated capacity:
29,257 MW.
- Maximum Despatch: 20, 795 MW (11-June-2018 9.15pm)
Responsibilities of Resource Planning Section
- Preparation of PC-I(s) for NTDC Development Projects
- Preparation of PC-II(s) for Feasibility Studies of Mega
Projects
- Preparation of Investment Plan
- Financing arrangements through International Financing
Agencies
- Preparation of PC-I(s) and PC-II(s) for Public Sector Power
Projects
NTDC Development Projects include:
- New 500 & 220 kV transmission lines and Grid stations for
strengthening of NTDC network for reliable and efficient transmission of Power to DISCO networks
- Augmentation of existing 500 & 220 kV Transmission
System
- Interconnection of Power Plants with National Grid for
Evacuation of Power generated from Power Plants
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion Grid Station Projects 1- 220 kV GIS Ghazi Road Lahore G/S 2x250 30 31.07.2018 2- 220kV Chakdara G/S 2x250 85 31.07.2018 3- 220kV D.I. Khan G/S 2x250 100 30.09.2018 4- 220kV Rawat G/S Extension/Augmentation of TF (2x160 to 2x250 + 1x250) 430
- 30.09.2018
5- 220 kV Nowshera G/S 3x250 10 30.09.2018
Ongoing ing Project cts
Sr. No. Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 6- 500kV Rawat Augmentation of one ATB 1x450 to 1x750
- 28.2.2019
7- 220kV Quetta Industrial G/S Augmentation of TFs 2x160 to 2x250
- 30.10.2018
8- Extension/Augmentation at Existing Grid Stations 1050 (500kV) 6096 (220kV)
- 30.06.2019
9- Conversion of Four 220kV Grids from AIS to GIS
- 30.06.2019
10- 220kV Lalian New G/S 3x250 8 30.09.2019 Transmission Line 11- 3rd 500 kV Circuit from Jamshoro to Rahim Yar Khan
- 600
31.12.2018 12- Improvement & Upgradation of Protection System to Avoid the Frequent Trippings in South Areas
- 31.12.2018
Ongoin ing g Proje ject cts
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 969 MW Neelum Jhelum HPP
- Ph-1: 150km
Ph-2: 130km Ph-2: Feb 2019 2- 1200 MW Thar CFPP (500 kV Thar – Matiari T/L)
- 250
30.06.2018 3- 1320 MW Imported Coal Power Plant at HUBCO
- Ph-1: 01 km
Ph-2: 220 km Ph-1: June, 2018 Ph-2: Dec, 2019 4- 1320 MW Imported CFPP at Sahiwal (Addition of ATB) 1x600
- Dec, 2018
5- 1200 MW LNG Based Power Plant at Balloki (Addition of ATB) 1x750 40 TL: 30.04.2018 ATB: July, 2018 6- 500kV D/C T/L from Guddu- Muzzafargarh (747 MW Guddu)
- 276
Dec, 2018
Ongoing ing Powe wer Evacuat ation n Project cts
Sr. No. Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 7- Reinforcement in Islamabad and Burhan area for Tarbela 4th Extension:
- i) Replacement of existing
220 kV Tarbela-Burhan D/C T/L (35km)
- 35
30.06.2018 ii) Replacement of existing 220 kV Tarbela-Burhan- ISPR D/C T/L (62.5km)
- 62.5
June, 2019 8- 147 MW Patrind HPP (Phase-II)
- 70 (132kV)
June, 2018 9- Evacuation Of Power from 1230MW RLNG Power Plant At Trimmu 250 220kV: 100 132kV: 15
- Aug. 2018
10- Extension work at 500kV Jamshoro G/S 1x450
- 31.12.2018
11- 1320 MW Bin Qasim Plant (Phase-II)
- 130
31.12.2018
Ongoing ing Powe wer Evacuat ation n Project cts
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 220 kV Zhob G/S 2x160 220 2019-20 2- 220kV Mirpur Khas G/S 2x250 70 2019-20 3- 220kV Zero Point G/S 3x250 24 2019-20 4- 220kV Punjab University 3x250 4 2019-20 5- 220kV Gharo G/S 2x250 85 (220kV) 20 (132kV) 2019-20 6- New 220kV Guddu-Uch-Sibbi S/C TL
- 360
2019-20 7- Evacuation of Power from K2/K3 Nuclear Power Plants
- 116
2019-20
Pl Planned d Pr Projects jects (2019-20) 20)
Sr. No. Name of the Project MVA Capacity Addition in T/L (km) Expected Completion
8- Evacuation of Power from 2x660 MW Coal Based SSRL/ SECL Power Plant at Thar
- 275
2019-20 9- Installation of Series Compensation for Enhancement in Transmission Capacity
- 2019-20
10- Procurement of 5 No 220kV Mobile Grid Stations
- 2019-20
11-
Evacuation of Power from 1224MW Wind Power Plants at Jhimpir Clusters 1250 220kV: 35 132kV: 220 2019-20
Planned d Projects ects (2019-20 20)
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 500 kV Faisalabad West GS 2x750 + 3x250 125 (220 kV) 32 (500 kV) 2020-21 2- 500kV Chakwal G/S 2x450 + 4x160 33 2020-21 3- 500 kV Lahore North 2x750 110 (500 kV) 15 (220 kV) 2020-21 4- 220kV Mastung G/S 2x250 120 2020-21 5- Evacuation of Power from Karot and Azad Pattan HPPs
- 10
2020-21
Planned d Projects ects (2020-21 21)
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 6- Evacuation of Power from Tarbela 5th Extension
- 53
2020-21 7- Evacuation of Power from 350 MW Siddiqsons Ltd.
- 40
2020-21 8- Evacuation of Power from 660 MW Lucky Electric Power Company
- 13
2020-21 9- 500 kV HVAC T/Lines for Interconnection of HVDC Converter Station at Lahore & Matiari with existing HVAC System
- 60
2020-21
Planned d Projects ects (2020-21 21)
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 1- 500 kV Islamabad West G/S 2x750 + 3x250 35 (220 kV) 27(500 kV) 2021-22 2- 500 kV Peshawar New (Nowshera) GS, CASA-1000 2x750 15 (500 kV) 24 (220 kV) 2021-22 3- 220kV Jamrud G/S 2 x 250 20 2021-22 4- 220kV Jauharabad 2x250 12 2021-22 5- Enterprise Resource Planning System. (ERP)
- 2021-22
6- Evacuation of Power from Suki Kinari, Kohala and Mahal Hydro Power Projects
- 500kV
697 2021-22
Planned d Projects ects (2021-22 22)
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 7- 220kV Larkana Grid Station 3x250 65 2021-22 8- Interconnection Scheme for CASA-1000 (HVDC Part)
- HVDC
100 km 2021-21 9- Evacuation of Power from 2160 MW Dasu Hydro Power Project (Phase-I)
- 765kV
250 2021-22 10- Upgradation/Extension of NTDC's Telecom & SCADA System
- 2021-22
11- 220kV Head Faqirian 2x160 88 2021-22 12- 500kV Moro Grid Station 2x750 + 3x250
- 2021-22
13- 220kV Dharki-Rahimyar khan- Bahawalpur D/C T/L
- 335
2021-22
Planned d Projects ects (2021-22 22)
- Sr. No.
Name of the Project MVA Capacity Addition in T/L (km) Expected Completion 14- 220 kV Gujranwala-II 2x250 20 2021-22 15- 220 kV Arifwala 2x250 10 2021-22 16- 220 kV Sialkot 2x250 20 2021-22 17- 220kV Kohat G/S 2x250 50 2021-22 18- 220kV Kamra G/S 2x250 5 2021-22 19- 220 kV Nawabshah 3x250 65 2021-22
Planned d Projects ects (2021-22 22)
Sr. No. Name of the Project Capacity (MVA) Addition in T/L (km) Status Estimated Cost (MUS$) Required year
- f Completion
1- Rehabilitation of existing Grid Stations and Transmission Lines of NTDC system
- Under Study
300 2022-23 2- 500kV Sialkot Grid Station 2x750 50 km (500 kV) Under Study 100 2024-25 3- 500kV Quetta Grid Station along with 500 kV Quetta- D.G Khan T/L 2x750 350 km (500 kV) Concept Paper submitted on 12.12.2017 240 2024-25 4- 220kV Khuzdar - Gawadar T/L along with associated 220 kV G/S 2x250 670 km (220 kV) Concept Paper submitted 15.11.2017 285 2024-25
Future ure Project cts
National Transmission & Despatch Company Limited
52 7/30/2018 NTDCL