HALFWAY COMMUNITY PARK: A NEW PARK FOR CARDONALD
Pauline Fletcher, Community Initiatives Manager
HALFWAY COMMUNITY PARK: A NEW PARK FOR CARDONALD Pauline Fletcher, - - PowerPoint PPT Presentation
HALFWAY COMMUNITY PARK: A NEW PARK FOR CARDONALD Pauline Fletcher, Community Initiatives Manager Why a new Park for Cardonald? A sea of green Very few outdoor opportunities for residents Topography the slope a
HALFWAY COMMUNITY PARK: A NEW PARK FOR CARDONALD
Pauline Fletcher, Community Initiatives Manager
Halfway Community Park Timeline / Progress to date
Community Consultation 2014/15 Planning Permission granted 2015 6 x Trainees Appointed to work
maintenance 2015/16 Community Garden installed Sept 2015 39 Trees Planted (Feb 2016)
Viewing Platform, Seating, pram path upgrade completed 2015
New Path installed 2016
Funding package secured March 2017 onwards
Friends of group constituted Aug 17 Detailed Design / community conversations
Lots of work going on behind the scenes!
Site start April 2018 ….completion December 2018
Green Infrastructure Fund Glasgow City Council (City Deal Funds) Southside Housing Association Landfill Funds (WREN / EB Scotland) ENV2 Funds Glasgow Tree Lover’s Society
£907K
Up to
£800K £500K £70K £34K £2.5K
Removal of roads / creation of ‘homezones’ Toddlers play area Natural play area Tree and shrub planting Seating / community spaces Growing space Outdoor gym and Parkour
https://youtu.be/DT8LuCNkEwY
Video clip created by Lorne Gill, Scottish Natural Heritage, Summer 2017
management/prevention colleagues)
Community Park group
Community Park group.
Trip 1: Millennium Space, Kingsway Court, Movement Park, Cuningar Loop
Play Space to meet Trees Balance Navigate / welcome Shelter Open space
Trip 2: Linn Park Adventure Playground, The Croft, Barrowfield Community Park
Tender for construction Liaise with
Continue to support the Friends group Continue to involve and update local community Youth engagement Explore activities with ParkLives / Glasgow Life and other providers