Green Project Elements Using Innovative, Energy Efficient, - - PowerPoint PPT Presentation

green project elements
SMART_READER_LITE
LIVE PREVIEW

Green Project Elements Using Innovative, Energy Efficient, - - PowerPoint PPT Presentation

Green Project Elements Using Innovative, Energy Efficient, Sustainable Design GMWEA Spring Conference May 30, 2013 Overview 1. Process for Assessment and Decision Making 2. Opportunities and Solutions 2A. Site 2B. Buildings 2C. Process and


slide-1
SLIDE 1

GMWEA Spring Conference May 30, 2013

Green Project Elements

Using Innovative, Energy Efficient, Sustainable Design

slide-2
SLIDE 2

Overview

  • 1. Process for Assessment and Decision Making
  • 2. Opportunities and Solutions
  • 2A. Site
  • 2B. Buildings
  • 2C. Process and Controls
  • 2D. Mechanical
  • 2E. Electrical
  • 2F. Biogas Cogeneration
  • 3. Take Aways
slide-3
SLIDE 3

Process for Assessment and Decision Making

slide-4
SLIDE 4

What do Green Project Elements Include?

Green Infrastructure

  • Stormwater solutions: Rain gardens, detention basins, buffers
  • Site design: Porous pavement

Energy Efficiency

  • Gas use
  • Electricity use
  • I/I reductions
  • Wet weather storage

Water Efficiency

  • Beneficial reuse of treated effluent
  • Leak repair program
  • Plumbing fixtures

Repurposing

  • Buildings
  • Reducing impervious areas
  • Tanks
  • Treated effluent reuse

Sustainability

  • Choosing durable materials with longer useful life
  • Waste reduction
  • Stormwater BMPs
slide-5
SLIDE 5

Matrix of Potential

Objective:

  • Identify items

included and not included

  • Identify all

potential improvements

  • Identify and

document potential benefit

slide-6
SLIDE 6

Industry Resources

  • Industry

resources

  • Review age
  • f

equipment

  • Review

equipment

  • perations

and controls

Identify Potential Improvements

slide-7
SLIDE 7

Energy Efficiency - Where to Start?

Establish an energy baseline

  • Identify equipment with highest

energy use – Wastewater Example

  • Blowers/Aeration
  • Pumps
  • Dewatering
  • HVAC
slide-8
SLIDE 8

Decision Making Process

  • Evaluation Criteria
  • Capital cost
  • Annual O&M Cost
  • Available funding sources
  • ROI: Return on investment
  • Feasibility
  • Complexity
  • Reliability/track record of emerging technologies

Determine Objectives

Economic Sustainable Social

slide-9
SLIDE 9

Examples

  • Worked with various participants

and stakeholders

Town of Hartford White River Junction and Quechee WWTFs

  • Green Project Elements Workshop
  • 7 year return on investment (ROI)

Village of Essex Junction WWTF

  • Energy Savings Scoping Study

Champlain Water District

slide-10
SLIDE 10

Town of Hartford Quechee & White River Junction WWTFs

Participants/Stakeholders

  • Town Staff
  • Town Energy Committee Members
  • State
  • Facilities Engineering
  • Wastewater Management Division
  • EPA
  • Efficiency Vermont
slide-11
SLIDE 11

Green Project Elements Workshop

  • Owner
  • Staff
  • Board

Members

  • Energy

Committee

  • Design Team
  • State of

Vermont

  • EPA
  • Efficiency

Vermont

  • VRWA
  • Local Industry
slide-12
SLIDE 12

Champlain Water District

Funded by Efficiency Vermont Energy Saving Scoping Study

  • Raw Water Intake
  • Water Treatment Facility
  • Four Pump Stations
  • Transmission System

Established baseline: Pumping accounted for 84% of overall electrical usage at CWD facilities

slide-13
SLIDE 13

Champlain Water District - Recommendations

Pump Control Efficiency

  • Operational modifications
  • Optimize VFD redundancy versus fixed speed operated pumps
  • Using 1 VFD pump to trim flow to the desired amount rather than

running multiple pumps at similar speeds

  • Soft starts on fixed speed pumps to limit power spikes
  • Pump replacement – right sizing the pump to improve efficiency
  • Pumps operating at significantly lower head than original design

head

  • Funding
  • CWD allowed to reinvest energy fees into energy improvements
slide-14
SLIDE 14

Opportunities & Solutions

slide-15
SLIDE 15

Opportunities & Solutions

Site Buildings Process and Controls Mechanical Electrical Biogas Cogeneration

slide-16
SLIDE 16

Site

slide-17
SLIDE 17

Site – Porous Pavement

Porous Pavement: Improves stormwater management by allowing passage of surface runoff to infiltrate into ground

slide-18
SLIDE 18

Site – Porous Pavement

Examples:

  • Hartford White River Junction WWTF
  • Hartford Quechee WWTF
  • Essex Junction WWTF
slide-19
SLIDE 19

Site – Porous Pavement

Benefits:

  • Reduces impervious area
  • Eliminates need for additional stormwater

treatment

Lessons Learned:

  • Requires sweeping and routine maintenance
  • Need suitable permeable soil conditions
  • Limited durability – use in low traffic areas
slide-20
SLIDE 20

Buildings

slide-21
SLIDE 21

Buildings - Repurposing

Examples:

  • Hartford White River Junction WWTF
  • Renovated existing Control Building
  • Aeration tanks converted to SBR tanks
  • Secondary clarifier converted to sludge storage
  • Essex Junction WWTF
  • Original filter building converted to chemical feed/storage building

Benefits:

  • Minimizes new construction
  • Doesn’t increase impervious area

Lessons Learned:

  • Not necessarily less expensive
  • Creates more sequencing issues during construction
slide-22
SLIDE 22

Buildings – Solar Collector Walls

Mounted a few inches from building’s

  • uter wall.

Perforations in wall allow outside air to travel through wall and through the panel, then to the building’s ventilation system. Summer bypass system

slide-23
SLIDE 23

Buildings – Solar Collector Walls

Examples: Essex Junction WWTF Benefits: Reduced heating and cooling costs

slide-24
SLIDE 24

Buildings – Daylighting

Maximize opportunities for daylighting building space

  • Window, skylight placement considered in building design to maximize

use of light and solar gain

Benefits:

  • Reduced electric lighting and heating usage
slide-25
SLIDE 25

Buildings – 2011 Vermont Commercial Building Energy Standards

Building Envelope

  • Higher R-values for building insulation required

for roofs and walls

  • Increased building material cost
slide-26
SLIDE 26

Process & Controls

slide-27
SLIDE 27

Grit Removal Systems - Vortex

Non-mechanical grit removal

  • Gravitational forces used to

separate grit from water

  • No external power source
  • No internal moving parts
  • Installed as free standing

structure or in concrete structure

slide-28
SLIDE 28

Examples

  • Hartford Quechee
  • Hartford White River Junction
  • Middlebury

Benefits

  • Lower energy usage
  • Smaller footprint
  • Less concerns about odors

Lessons Learned

  • Provide screening upstream to reduce plugging
  • f grit removal line

Grit Removal Systems - Vortex

slide-29
SLIDE 29

Biological Nutrient Removal

Removal of BOD5, phosphorus, and nitrogen through biological process

slide-30
SLIDE 30

Anaerobic Selectors - Benefits

Green Project Benefits

  • Enhances biological phosphorus removal
  • For lagoon systems – increases BOD removal
  • Reduces chemical usage and sludge generation
  • Less sludge to dewater and dispose
  • Decrease volume of RAS that needs to be

pumped

slide-31
SLIDE 31

Examples - Facilities with Biological Phosphorus Removal

Phosphorus: Create conditions for phosphorus accumulating organisms (PAO) to thrive

  • Anaerobic Selectors
  • SBRs

Conventional Activated Sludge

  • Essex Jct WWTF
  • Springfield WWTF

Oxidation Ditch: Fair Haven Extended Aeration: Enosburg Falls Aerated Lagoon: Hardwick SBRs

  • Hartford Quechee and White River Junction
  • Shelburne
  • Middlebury
slide-32
SLIDE 32

Anaerobic Selectors Process Schematic

Anoxic Stage 1 Anaerobic Stage 2 Aerobic Secondary Clarifier Return Activated Sludge (RAS) Primary Effluent Metal Salt Addition (Alum) Addition of anoxic zone for denitrification (nitrate removal)

slide-33
SLIDE 33

Anaerobic Selectors – Lessons Learned

Lessons Learned

  • Requires anoxic for

denitrification to optimize biological phosphorus removal

  • Mixing is required and consider

type of mixer for reliability

  • ORP automatic monitoring for

process control

  • Reduced RAS return rates
slide-34
SLIDE 34

Hyperbolic Mixers

More energy efficient option for mixing compared to submersible mixers

  • Require ~40% less energy to achieve equal mixing
slide-35
SLIDE 35

Hyperbolic Mixers

Examples

  • Essex Junction WWTF
  • South Burlington Airport Parkway

Benefits

  • Lower Energy Required for Mixing
  • Fewer units required
  • Improved reliability over submersible

mixers

  • Motor accessible for maintenance
slide-36
SLIDE 36

Converting fixed speed motor operation to variable frequency drive (VFD) operation

  • Equipment is designed for peak flows
  • VFDs allow equipment motor to run at

partial load to save energy at average flows at design year

  • Automatic or manual
  • Eliminate throttling valves
  • Improved process flow control

VFD Operation – Pumps & Blowers

slide-37
SLIDE 37

Benefits:

  • Improves energy efficiency through range
  • Provides better process control

Lessons Learned:

  • Locate VFD close to equipment
  • Addition of VFD slightly reduces energy efficiency
  • Use wall mounted units vs. cabinets
  • Replace soft starts and can be used for phase converters
  • Maintain minimum velocities in force main at low set speed

VFD Operation – Pumps & Blowers

slide-38
SLIDE 38

Inefficiency in oversized pumps & blowers for design Examples

  • Champlain Water District
  • Essex Junction WWTF

Lessons Learned

  • Multiple units – sometimes 3 vs. 2 units

Right Equipment Sizing

slide-39
SLIDE 39

Turbo Blowers

  • New blower technology available in US for ~5years
  • Operate at a very high speed
  • Manufacturers:
  • Aerzen (formerly K-Turbo)
  • Neuros APG
  • Atlas Copco (HSI)

Turbo Blowers

slide-40
SLIDE 40

Turbo Blowers - Examples

Essex Junction WWTF: HSI Hartford White River Junction: HSI Burlington WWTF: KTurbo South Burlington Airport Parkway: KTurbo

slide-41
SLIDE 41

Benefits

  • Smaller footprint
  • Includes internal variable frequency drive
  • Greater capacity per BHP compared to
  • ther types of blowers
  • Doesn’t run hot
  • Quieter

Turbo Blowers - Benefits

slide-42
SLIDE 42

Lessons Learned

  • Good incentives provided by Efficiency Vermont
  • Doesn’t have the wide turndown (operating

range) claimed

  • Better application in sizes > 100 HP
  • Automatic control can be problematic in parallel
  • peration with other types of blowers
  • Long-term reliability still a concern

Turbo Blowers - Lessons Learned

slide-43
SLIDE 43

Solar Aerators

Solar aerators supplement or replace the mixing/aeration in lagoons & ponds Lagoon Aeration – Swanton WWTF

Item Description Original Proposed Average Daily Flow 0.9 mgd 0.9 mgd Peak Hour Flow 2.2 mgd 2.2 mgd Aerators Type Grid Powered Solar Number 16 5 Power Requirements each unit 5 HP 3 x 80 watt photovoltaic panels

slide-44
SLIDE 44

Solar Aerators – Lessons Learned

Good incentive through Efficiency Vermont Lease arrangements available Shouldn’t be used to replace original aeration system, but

  • perated to supplement

Haven’t been in operation long enough to determine long- term reliability

slide-45
SLIDE 45

Instrumentation

Monitoring

  • DO – Pacing blowers to meeting DO concentration set point
  • ORP – Process control for biological nutrient removal

Flow pacing chemicals Benefits

  • Optimizes energy usage
  • Improves process control
slide-46
SLIDE 46

Non-potable Reuse

Optimizing use of plant water in lieu of potable water Benefits

  • Reduces municipal potable water use

Lessons Learned

  • Filtering may be required
  • Covering of tank may be needed to

minimize algae growth

slide-47
SLIDE 47

Mechanical

slide-48
SLIDE 48

Mechanical – Heat Recovery System

Example

  • Hartford White River Junction
  • Transfer excess heat generated in

blower room to other spaces

  • Essex Junction WWTF
  • Solar collector walls pre-heat air for

ventilation

Benefit

  • Reduced heating energy and energy

costs

slide-49
SLIDE 49

Buildings – Heat Recovery

New Code requirements

  • NFPA 820 – Fire Protection

Class I, Div 1, Group D Spaces - NFPA 820 requires 12 air changes per hour for continuous ventilation and 30 air changes per hour if intermittently ventilated

  • Headworks
  • Primary Sludge Pumping
  • Influent Pumping

Challenge in winter to heat buildings when drawing in cold air to meet ventilation requirements Opportunity for heat recovery to reduce heating energy use

slide-50
SLIDE 50

Mechanical – Heat Pump Systems

Use of treated effluent for heating/cooling

slide-51
SLIDE 51

Mechanical – Heat Pump Systems

Hartford White River Junction WWTF Essex Junction WWTF

slide-52
SLIDE 52

Mechanical – Heat Pump Systems

Benefits

  • Beneficial reuse of effluent
  • Reduces energy usage for heating and cooling

Lessons Learned

  • Maintain storage in chlorine contact tank
  • May want to cover chlorine contact tank to minimize

algae growth

  • Filter or straining is needed
slide-53
SLIDE 53

Mechanical – Geothermal Wells

Used to supply building heating and cooling Two Types:

  • Open Loop: Water from well(s) as conductor
  • Closed Loop: Earth/ground as conductor
slide-54
SLIDE 54

Mechanical – Geothermal Wells

Example: Essex Junction WWTF

  • Open loop system

Benefits:

  • Delivers 3-5 times more heat

than the electrical energy

Lessons Learned:

  • Open loop systems are more efficient
  • System needs to be compatible with building heating system
  • Well pump needs to be sized appropriately
slide-55
SLIDE 55

Electrical

slide-56
SLIDE 56

Solar Electric

Solar panels are used to generate electricity for on-site use or net metering Example

  • Hinesburg WWTF
  • Montpelier WWTF

Benefits

  • Reduces energy usage
  • Reduces greenhouse gases

Lessons Learned

  • Funding challenges – Public/Private Partnership
  • Payback
slide-57
SLIDE 57

Lighting

Lighting Occupancy Sensors Daylighting Lessons Learned

  • Incentives available from Efficiency Vermont
slide-58
SLIDE 58

Biogas Cogeneration

slide-59
SLIDE 59

Biogas Cogeneration

Methane gas from the anaerobic digestion process is used to generate electricity. Requires pre-treatment with gas conditioning for siloxanes and/or hydrogen sulfide and moisture removal Power is generated by either microturbines or internal combustion engines

slide-60
SLIDE 60

Biogas Cogeneration – Essex Junction WWTF

Gas production ~37,000 cfd System Components

  • Biogas Treatment
  • Moisture Removal
  • Siloxane Removal
  • Combined Heat and Power

(CHP) Module

  • 120 kW Engine
  • Generator
slide-61
SLIDE 61

Biogas Cogeneration - Benefits

Benefits

  • Use of methane gas for electrical generation reduces electrical

costs

  • “Plug & Play” - Engines are available in container module
  • Engine vs. microturbines
  • Higher electric and thermal efficiencies
  • Better turndown
  • Gas compression system is not required
slide-62
SLIDE 62

Biogas Cogeneration – Lessons Learned

Lessons Learned

  • Good incentives from Efficiency Vermont
  • Need to determine if sufficient gas production is available
  • Gas treatment is necessary for siloxanes and hydrogen

sulfide plus moisture removal

  • Microturbines are not available or supported in smaller

sizes

  • Be aware of space classifications - some equipment may

need to be exterior

slide-63
SLIDE 63

Take Aways

slide-64
SLIDE 64

Take Aways

Many of these opportunities should be standard for most large upgrade projects Communicate and share experiences with other facilities and stakeholders Public education and outreach for customers on green project elements Solutions need to provide reasonable Return on Investment (ROI) of 7 to 10 years Explore and leverage all public/private funding opportunities Understand the complexity, reliability, and O&M costs of newer technologies

slide-65
SLIDE 65

Questions?

slide-66
SLIDE 66

Presentation is Available at:

www.AEengineers.com