gravity pipeline outreach meeting
play

Gravity Pipeline Outreach Meeting March 22, 2017 Regional - PowerPoint PPT Presentation

Gravity Pipeline Outreach Meeting March 22, 2017 Regional Environmental Sewer Conveyance Upgrade Agenda Introduction (Teresa) Gravity Pipeline Project Overview (Bruce) Procurement Process and Stages (Teresa) Key Parts of the


  1. Gravity Pipeline Outreach Meeting March 22, 2017 Regional Environmental Sewer Conveyance Upgrade

  2. Agenda • Introduction (Teresa) • Gravity Pipeline Project – Overview (Bruce) • Procurement Process and Stages (Teresa) • Key Parts of the RFQ (Bruce) • Estimates, Budgets and Pricing (Teresa) • Early Focus Areas (Stage 1) (Bruce) • Available Information (Teresa) • Questions (Please ask anytime)

  3. Gravity Pipeline Project – Overview • Background • Virtual tour of alignment and shafts – Horizontal – Vertical • Hydraulics – Diurnal and Seasonal Equalization • Status of EIR, Permits and Easements • Availability of SVCW Funding

  4. REDWOOD BELMONT CITY SAN CARLOS MENLO PARK EMERALD HILLS WEST BAY SANITARY DISTRICT WOODSIDE

  5. Problem we need to Solve  Joints every 12’ in RCP Force Main thru YBM  Design useful life = 25 to 50 years (ASCE; EPA)  Pipe is 45 years old  Originally designed for gravity flow (low pressure)  Currently operating at 2.5 times design pressure  64 leaks so far; rate of failure is increasing  Leaks are time-consuming, disruptive and expensive to repair . . . potentially catastrophic.

  6. Pipe cracked (not a joint separation) Raw sewage flowing from separated and offset joint

  7. Adjacent to airport . . . valve bonnet blew off . . . . . . raw sewage into the air

  8. Major Failures Corrosion + Surge

  9. Numerous Alternatives Considered 2014/2015 2013/2014 Microtunnel (deep) Open Cut in Street Tunnel Boring Machine (deep) Open Cut in Levee From SVCW Plant Lay in Slough From near Airport Lay in Lagoon Sliplining (w/ bypass) Microtunnel (shallow) Parallel Smaller Pipes Pipe Bursting (w/ bypass) Pipe Splitting (w/bypass) Swege (w/bypass) Replace in place (w/bypass)

  10. Current Project • SVCW will share all of the studies and alternatives developed to-date • We expect to work collaboratively with the PDB during Stage 1 to refine, revise or change these concepts to best meet SVCW objectives

  11. Virtual Tour

  12. “60% Permit Plans” – RLS Shaft

  13. RLS Shaft

  14. RLS Shaft

  15. RLS Shaft

  16. Airport Access Shaft

  17. Airport Access Shaft

  18. San Carlos Drop Structure

  19. San Carlos Drop Structure

  20. “60% Permit Plans” – Bair Island Inlet

  21. Bair Island Inlet Structure

  22. Bair Island Inlet Structure

  23. Alignment

  24. Governors Bay Alignment

  25. Easement Acquisition

  26. Pulgas Creek

  27. Geologic Profile

  28. Hydraulics Design Storm Equalization Diurnal Equalization San Carlos Drop Structure

  29. EIR Status • Draft EIR November 2016 • Comments Due January 2017 (very few comments) • Adoption expected April 2017

  30. Environmental Permits • Environmental Permit Applications submitted December 2016 – COE under Pulgas Creek – BCDC – California F&WS • Expected October 2017

  31. Easements • Affected along 3.3 miles: – Four private owners – Three public agencies • Legal Descriptions being prepared • Private acquisitions to start upon approval of EIR • Two of public agencies are members of SVCW • Currently leasing Airport Access Shaft staging area

  32. Funding • Currently have bond capacity to obtain bonds for entire program • Pursuing less expensive funding – SRF – WIFIA

  33. Procurement Process and Stages of Design-Build • Why Progressive Design Build • RFQ/RFP • Stage 1/Stage 2 with Phases • Schedule

  34. Why Progressive Design Build • Accelerate completion of overall Project relative to DBB delivery • Promote a cooperative and collaborative relationship between SVCW and the PDB team • Incorporate ongoing cost modeling and take a “design -to- budget” approach • Flexibility for phased design and construction • Early and ongoing staff involvement and training

  35. RFQ/RFP Process • Step 1: – RFQ issuance, – Pre-submittal meeting – Interviews with selected Respondents, – Shortlisting of three (or up to four) Respondents. • Step 2: – RFP issuance to short-listed Respondents, – Pre-Proposal Meeting – Confidential Meetings with each short-listed Respondent – Reference checking – Interviews – Selection of winning Respondent – Negotiation of Stage 1 Preconstruction contract

  36. Stage 1/Stage 2 with Phases • Stage 1 – Collaboratively bring the design from a 5% to 10% level to a 60% to 70% level – Negotiate Stage 2 Contract Pricing and Schedule • Stage 2 – Final design (100%) – Construction – Testing and Start-up • Phases – As needed to move project forward

  37. Schedule • Issue RFQ Shortly after April 13 • SOQ Submission End of May • Shortlist and RFP Early June • Proposals Due Late August • Stage 1 Approval September or October • Stage 2 Approval 2018 Construction: Two to three years

  38. Key Parts of the RFQ • RESCU Success Factors • Gravity Pipeline Project Objectives • Risk Responsibility Matrix • Required elements of SOQ

  39. RESCU Success Factors “Success” - collaboratively implementing an appropriate balance of the following: • Cost: Provide a complete functional conveyance system that meets the goals of the Program at the lowest practical capital and lifecycle cost . • Operations: Produce projects that are easy, efficient, and effective to operate . • Maintenance: Produce projects that minimize required maintenance . • Safety: Implement projects that are safe to construct, operate, and maintain. • Schedule: Place new wastewater conveyance system projects into operation with best practical safe speed , while maintaining the present level of service with existing facilities. • Stakeholder Impacts: Solicit, evaluate, and respond to stakeholder’s concerns, and implement a Program that best meets the combined needs of stakeholders while reaching the Program’s goals .

  40. Gravity Pipeline Project Objectives • Quality : Provide a gravity pipeline that will be sustainable over 100 years and will reliably receive, convey and equalize wastewater flows ranging from 2 mgd to 103 mgd in full compliance with environmental requirements. • Cost: Provide a complete functional gravity pipeline and inlet facilities that meet the goals of the Project at the lowest practical capital and lifecycle cost . Provide early and ongoing total Gravity Pipeline cost predictability . • Schedule : Achieve the best practical safe speed to complete the tunnel and inlet structures so that the existing failing pipeline and pump stations can be taken out of operation as early as reasonably possible. • Risk: Generally assign to the Design-Builder the risks that the Design-Builder can reasonably anticipate and control . Assign to SVCW the risks that the Design-Builder cannot reasonably anticipate and control. • Safety: Implement an effective safety program incorporating better than industry practices . • Accountability : Design-Builder to provide for a single point of accountability for performance of all services under Stage 1 and Stage 2. SVCW to provide a single point of accountability for all direction to the Design-Builder. • Collaboration : Implement an integrated design process that collaboratively includes SVCW management, engineering, operations and maintenance as well as the Design-Build contractor and engineer to develop a design that optimally achieves SVCW success factors and Gravity Pipeline requirements . • Innovation : Apply proven technology from other locations to uniquely achieve Gravity Pipeline goals .

  41. Risk Responsibility Matrix • Approach: Collaboratively reduce risk and then assign to PDB what the PDB can best control • Built from a thorough Risk Register prepared during project planning (biggest risk was cost over budget)

  42. Required Elements of SOQ • Team structure (including parties responsible for shafts, tunnel, concrete segments) • Key personnel • Experience collaborating with owners • Similar projects • Safety Pass fail items, financial, insurance, bonding, etc.

  43. Estimates, Budgets and Pricing • Budget vs Current Cost Estimate – design to budget • Indicative Pricing

  44. Focus Areas during early PDB Preconstruction Services (Stage 1) • RLS shaft – coordination with FoP • Pipe in tunnel • Shaft construction • Benefit of Bair Island start vs environmental/permitting delay risks • Project cost and schedule

  45. RLS shaft – coordination with FoP

  46. Pipe in Tunnel – Alternatives • Two Pass – FRP in tunnel – HDPE lining • One Pass – HDPE lined segments • Field weld • Combisegments – Multiple layers of defense • Upstream dosing • Water and air flow • Special concrete • Monitoring

  47. Shaft Construction - Constraints • Geotech – YBM, Sand, Groundwater • Airport Height limits – ~55’, ~45’, ~25’ • Protected species – Rail and Mouse • Traffic – Redwood Shores Parkway

  48. Benefit of Bair Island start vs environmental/permitting delay risks Risks • Ridgeway Rail – no night work • Mouse – no work during high tides • New Biological opinion – 9 to 12 months • EIR amendment Benefits • Eliminate airport access shaft • No TBM relocation – one launch • Muck spoil on site

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend