Gravity Fed System
Team Members: James Brinkerhoff, Christopher Kulbago, Patrick O’Connell, Lauren Pahls, Ted Rakiewicz, Sarah Salmon Group Number: P13631
1
Gravity Fed System Team Members: James Brinkerhoff, Christopher - - PowerPoint PPT Presentation
Gravity Fed System Team Members: James Brinkerhoff, Christopher Kulbago, Patrick OConnell, Lauren Pahls, Ted Rakiewicz, Sarah Salmon Group Number: P13631 1 Table of Contents 1. Team Roles 2. Project Background 3. Schedule MSD II 4.
Team Members: James Brinkerhoff, Christopher Kulbago, Patrick O’Connell, Lauren Pahls, Ted Rakiewicz, Sarah Salmon Group Number: P13631
1
1. Team Roles 2. Project Background 3. Schedule MSD II 4. High Level Customer Needs 5. Budget and Costs 6. Bill of Materials 7. Engineering Specifications 8. Concept Generation 9. Feasibility Analysis 10. Original System Architecture 11. Original P&ID 12. Original Cart Layout 13. MSD I vs. MSD II Comparison 14. Final P&ID 15. Final Cart Layout 16. Test Results Data 17. Labview Layout 18. Risk Assessment 19. Successes and Failures 20. Issues and Actions MSD I 21. Issues and Actions MSD II 22. Questions
2
3
Demonstrate process control in a lab environment using a gravity fed loop with a control valve with an existing flow cart as reference.
RIT’s Chemical Engineering Department
Kodak’s Steve Possanza was our guide through this process. Kodak also donated old parts to make our cart fully functional.
Students who will use the machine, the Department, Dr. Sanchez, Dr. Richter, and staff who will maintain the machine.
Two other groups are designing similar process control machines whose aesthetic appearances must match ours.
4
5
Customer need: Does project fulfill need? Safety Yes Ergonomics Yes Mobility Yes Teaching Manually Yes Teaching Auto-Controls Yes Ease of Assembly Yes Low Cost Yes Use of LabVIEW Yes Drained Tank Dynamics Yes 6
engenders learning.
modeling, disturbances, and/or hysteresis.
7
1086.74 1206.28 1500 200 400 600 800 1000 1200 1400 1600 Money ($)
Budget Tracking
Actual Spent Anticipated Spending Original Request
8
9 Grouping of items:
to better inform team of item status.
purchased and confirming the cost when the items arrived.
customer needs into technical specifications.
summarized below:
18 1
Specifications
Specifications met Specification assumed met Specification not met 10
11
12
13
14
cart and lab manual.
15
16
17
18
19
20
Item MSD I MSD II Overall goal Concept Generation Building and Integration Deliverables Theoretical; Organization and charts As-built final documents Time 10 weeks 16 weeks Individual Contributions About equal More work from EE and ME Grading Throughout; Several milestones Only a Functional Review and a Final Review 21
22
23
24
25
26
for student interaction for real-time process control of a dynamic system.
project hindrance.
intent (as of right now).
27
line feed,” where we had a permanent height for a gravity feed stream.
code in order to be able to be more versatile and mimic different heights with different water pressures from a water line.
three groups.
28
therefore the water flow rate out in preliminary testing was too low.
drain at the required flow rate.
mounting, it gave erroneous readings.
did not know how to properly control the 2 I/P circuits, preventing control valve operation.
fully functional as anticipated.
29
and measure time it takes for students to complete the lab.
Instruments Data Acquisition for increased accuracy, ease of assembly and use.
differential pressure cell would minimize this risk.
the robustness of the cart can improve.
30
31