Facilities Update (as required by Policy 4:150 Facility Management and Building Programs) December 9, 2019 Presentation Overview Deferred Maintenance Plan (9/4/18) Recap of Major FY 19-20 Projects 2020-21 Capital Improvement
Presentation Overview
2
- Deferred Maintenance Plan (9/4/18)
- Recap of Major FY 19-20 Projects
- 2020-21 Capital Improvement Projects
- Crouse Education Center
- Still Masonry
- MVHS Solar
- Roof Expenses
- Elementary Air Conditioning
- Energy Management Initiatives
- Next Steps
Goal for Deferred Maintenance Plan
3
- Reduce deferred maintenance projects as fast as possible
- Focus on building envelope, heating/cooling, and safety
- Ensure quality work through manageable pace
- Proactively maintaining existing projects
- Use available resources from
- Capital Outlay Account
- Developer Contributions
- Sale of Property
- Prior Year Fund Balance
Projects Actual Cost Phase V – Elementary A. C. Special $4,800,000 Classroom Lock Modifications @ 34 Schools Special $ 568,683 BAS Replacement @ Birkett Deferred $ 333,900 Graham Slope Roof Replacement Deferred $ 841,896 Phase II Masonry Work - Fischer Deferred $ 315,149 WVHS Tile Floor Replacement Deferred $ 206,897 Varsity Softball Fence Replacement @ WVHS Scheduled $ 51,449 FY 19 Roof Leak Repairs Scheduled $ 237,282 Wheatland Hardscape Special $ 258,639 Wheatland Gym Floor Special $ 89,418 Wheatland (other costs) Special $ 137,976
FY 19-20 Completed Projects
4
Projects Projected Cost Fischer Slope Roof Replacement Deferred $1,180,000 Asphalt Replacement (NV, Birkett, Hill, WVHS) Deferred $1,089,500 WVHS Gym Floor/Bleacher Replacement Deferred $1,732,800 2019 Masonry Restoration Deferred $ 635,200
FY 19-20 On Going Projects
5
WVHS Gym Floor & Bleacher Replacement
6
WVHS Main Gym Bleacher Replacement Preparing for lines on new fieldhouse floor
FY20-21 Capital Improvement Projects
7
8
CEC Projects
CEC Exterior Renovation
9
10
Still Masonry
11
MVHS Solar Project
Roof Expenses
12
$705,200 $592,500 $399,869 $641,200 $786,459 $1,478,800 $424,686 $547,500 $1,170,374 $1,947,568 $1,811,868 $137,894 $223,620 $127,911 $102,214 $205,455 $126,867 $208,415 $237,282 $0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 EMG yearly Ave.
Roof Repairs Roofing Replacement
Elementary Air Conditioning
13
- Funding from delayed state payments
- Installed over five years in 19 schools (Total of 590 classrooms)
- Phase VI – LMC area
- Summer 2020 – Install all roof top units
- Beginning September 2020 – 2nd shift work
- Project Completed August 2021
Energy Management Initiatives
- 2nd year participation in the EnerNOC Demand Response
Incentive Program (ComEd territory only) results in the district receiving $71,657 for a two year total of $124,257. This year we anticipate receiving an additional $65,000. (Fischer, Granger, Still, MVHS & WVHS)
- Transitioning outside lighting to LED.
- Board accepted a proposal for installation of solar panels
at MVHS. (Power Purchase Agreement)
14
Next Steps
- Prioritize capital improvement and other district needs based
- n the following hierarchy:
1. Safety Related Items 2. Approved Curriculum Related needs 3. Necessary Repairs 4. State-required Life Safety Projects (building code changes) 5. Aesthetic
- Explore grant and other cost savings opportunities
15