SLIDE 1
ORANGE PUBLIC SCHOOLS FACILITIES PRESENTATION August 14, 2018
Facilities Project & Maintenance Issues
SLIDE 2 STEM Building Renovation (Phase II)
Summer Project: The Phase II:- Lower Level Renovation
- Demolition certain non-load bearing walls, to create larger
classroom spaces
- Remove and relocate certain number of lockers
- Determine a suitable location for Green House (either on flat roof or
grass area behind the convent building).
- Installation of new LED lights
- Sparkling, Painting & Finishing of classroom walls
- Install Carpet Tiles and or VCT Tiles where applicable
Long Term Project:
- Upgrade of Electrical power, new A/C units (Sanyo)
- Handicap upgrade (chair lift installation)
UPDATE: (a) Asbestos Abated (b) Demolition of walls 90% completed
SLIDE 3
STEM BUILDING RENOVATION Phase II – Wall demolition
SLIDE 4
STEM BUILDING RENOVATION Wall Demolition
SLIDE 5
STEM BUILDING RENOVATION Wall Demolition
SLIDE 6
STEM BUILDING RENOVATION Wall Demolition
SLIDE 7 OHS: Demolition of Buildings for Parking Lots – Clarendon Pl., etc.
- Bid has been awarded, demolition of 396 Clarendon Pl
is awaiting approval of permit.
- Grading and Repaving of School Lots (Pending)
- Renovation of OHS interior Court yard remove and
replace rotted wood, cut trees & weeds, clean and power wash (In Progress)
- Installation of new air conditioners (8 units already
installed)
SLIDE 8
OHS Interior Courtyard
SLIDE 9
OHS Interior Courtyard
SLIDE 10 Playgrounds Renovation
The renovation of the following schools was scheduled to be done this summer:
- Central Elementary School (In Progress)
- Forest Street School (Completed)
- Heywood Avenue School (In Progress)
- Oakwood Avenue School (In Progress)
- Our Lady of Mt. Carmel (Preschool playground) In Progress
SLIDE 11
Forest Elem Playground
SLIDE 12
Heywood Elem Playground
SLIDE 13 Gym Floors Renovation
.
- Central Elm School Gym Floor:- floor was ripped by PCI
maintenance services to locate the source of water damage prior to fixing the floor.( Renovation is Completed) .
- Heywood Gym Floor is partially renovated because the source
- f water damage has not been fixed.
SLIDE 14
Central Elem Gym Floor (Before)
SLIDE 15
Central Elem Gym Floor (Installation In Progress)
SLIDE 16
Central Elem Gym Floor (Installation In Progress)
SLIDE 17
Central Elem Gym (After)
SLIDE 18
Central Elem Gym (After)
SLIDE 19 Cleveland Elementary School (Move to Our Lady of The Valley)
SDA Renovation of OLV is in progress (Expected completion date – August 15, 2018). PCI has commenced renovation of 3rd floor District has started prepping the kitchen (Kitchen hood filters cleaned, tagged, Grease trap cleaned, Old oven disconnected to be replaced by
- ven at Cleveland, other work in progress)
SLIDE 20
OLV – 3rd Floor (Before)
SLIDE 21
OLV – 3rd Floor (Before)
SLIDE 22
OLV – 3rd Floor (Before)
SLIDE 23
OLV – 3rd Floor (Before)
SLIDE 24
OLV – 3rd Floor (Renovation In Progress)
SLIDE 25
OLV – 3rd Floor (Renovation In Progress)
SLIDE 26
OLV – 3rd Floor (Hallway painted)
SLIDE 27
Rosa Parks Main Hot Water Line (Before)
SLIDE 28
Rosa Parks Main Hot Water Line – (After)Fixed
SLIDE 29
Boiler Repairs (Pending) Forest Boiler-Section is Leaking
SLIDE 30
Boiler Repairs (Pending) Forest Boiler-Mud leg leaking
SLIDE 31
Boiler Repairs (Pending) Oakwood Boiler – Union leaking
SLIDE 32
Boiler Repairs (Pending) Oakwood -Release Valve - Inoperable
SLIDE 33
Boiler Repairs (Pending) Park – Boiler leaking at nipple
SLIDE 34
Boiler Repairs (Pending) OPA- Boiler refractory deteriorated
SLIDE 35
Boiler Repairs (Pending) OPA Boiler– Tubes to be installed
SLIDE 36
Boiler Repairs (Pending) OPA Boiler- Drain line corroded
SLIDE 37
Boiler Repairs (Pending) OPA Boiler-rear corroded & leaking
SLIDE 38
Boiler Repairs (Pending) OHS Tank – outlet union leaking
SLIDE 39
Boiler Repairs (Pending) OPA-water tank-pipe leaking
SLIDE 40 Oakwood Trailers Demolition
- Contents of both Trailers have been emptied
- Power and Sewer lines disconnection are in progress.
SLIDE 41
RPCS Sink Hole