ESCRI-SA Project Update
Project Report
A presentation for the ESCRI-SA Knowledge Sharing Reference Group, Meeting 1 – February 6, 2018
ESCRI-SA Project Update Project Report A presentation for the - - PowerPoint PPT Presentation
ESCRI-SA Project Update Project Report A presentation for the ESCRI-SA Knowledge Sharing Reference Group, Meeting 1 February 6, 2018 PRESENTATION OUTLINE > Delivery strategy and contracts > Design > Development approvals > Site
Project Report
A presentation for the ESCRI-SA Knowledge Sharing Reference Group, Meeting 1 – February 6, 2018
2
3
4
to BESS’ addition to the network (e.g. operation under islanded condition);
network and customers
and building available
6
7
8
33 kV Bus Dalrymple Substation Wattle Point Wind Farm 25 MVA TF 2 25 MVA TF 1 Ardrossan West Substation SAPN Exits BESS U/G Cable Transmission Network Connection Point BESS Connection Point 132 kV assets BESS Assets 33 kV assets Transmission Connection Assets Wattle Point WF Assets VT
9
10
Sponsorship)
11
by inclement weather in Europe and associated delays – especially for rescheduling
12
13
14
respective area;
15
Priority based Services Inherent Services
Priority Description of Service ID Description of Service 1 Islanded Operation A Voltage Control Frequency Control Fault Current Support Grid Connected modes below B (Voltage Control
Power Factor Control) Fast Frequency Response Fault Current Support 2 Network Support - SIPS 3 Contingency FCAS services 4 External set point mode (P & Q) (Energy Trading Modes) Cap Trading and/or Arbitrage
16
SAPN and WPWF (132kV, 33kV, 11kV).
17
result of BESS connection
under islanded condition);
contacts) planned outages;
via protection relays (even before the CBs would open) and transmitting trip signals via telecommunication systems unplanned outages
18
19
measurements)
stepping)
20
21
protection upgrades fro SAPN
Hugo Klingenberg Senior Manager Network Development ElectraNet Pty Limited