SLIDE 1
Equipment Replacement Project Presented by Pippin Cavagnaro NUTE - - PowerPoint PPT Presentation
Equipment Replacement Project Presented by Pippin Cavagnaro NUTE - - PowerPoint PPT Presentation
Biotower and Biofilter Equipment Replacement Project Presented by Pippin Cavagnaro NUTE ENGINEERING Look Back: Mt View Sanitary: 1939 Mt View Sanitary: 1987 Pre Biotower Mt View Sanitary: June 1993, Pre-UV Mt View Sanitary: April 2008,
SLIDE 2
SLIDE 3
Mt View Sanitary: 1987 – Pre Biotower
SLIDE 4
Mt View Sanitary: June 1993, Pre-UV
SLIDE 5
Mt View Sanitary: April 2008, UV Visible
SLIDE 6
Mt View Sanitary: June 2014
SLIDE 7
Mt View Sanitary: March 2017
SLIDE 8
Dual Feed Biofilter & Biotower
SLIDE 9
Hydraulic Flow Schematic
SLIDE 10
Project Objective
- 1. Replace the Biotower Rotating Mechanism
- 2. Replace the Biofilter Mechanism
- 3. Install a rotational speed controller on the
Biotower, and have the speed control option for the Biofilter in the future
- 4. Replace the Corroded and Out-of-Code MCC
- 5. Replace Biotower Pump Valves and related
parts.
SLIDE 11
Project Benefits
Replacing the Biotower and Biofilter rotary distributor mechanisms will offer:
– Repair aging equipment, failing bearings, corrosion – Improve nutrient removal – Improve flushing of biomass – Reduce system clogging snails – Reduce bio-weight on filter media, extending life – Reduce electrical energy use of Biotower – Reduce maintenance, – Reduce MCC overheating
SLIDE 12
Existing Biotower Mechanism
SLIDE 13
Existing Equipment To Be Replaced
Biotower Mechanism The Biotower was constructed completed in 1988 and is now almost 30 years old: i. Eimco Impulse Drive Rotary Distributor Mechanism, painted carbon steel, bottom bearing leaking ~1/4 recirculation water ii. Recirculation Pump Motor Control Center, rusted,
- perational heating and Code issues
- iii. Pump isolation and check valves, leaking and warn
SLIDE 14
Existing MCC and VFD Cabinet
SLIDE 15
Existing Check and Plug Valves
SLIDE 16
Existing Biofilter Mechanism
SLIDE 17
Existing Equipment To Be Replaced (continued)
Biofilter Mechanism The Biofilter rotating distribution mechanism was first installed in 1968. i. Existing Dual Feed Eimco rotating distributor center well with custom Dorr Oliver style truss arms, made from painted carbon steel
- ii. Rehabilitated in the early 1990’s, now is over 25
years old: bearing and seals are aging, arms are rusty
SLIDE 18
New Equipment: Westech Mechanism
SLIDE 19
New Equipment: Biotower Mechanism
SLIDE 20
New Equipment: Motor Control Center
SLIDE 21
New MCC Location Plan w/ Aluminum Shade Canopy
SLIDE 22
New MCC and Canopy Elevation
SLIDE 23
Water Application Differences
Dosing Rate Increase:
- Typical passive system: 0.25 to 1 gal/ft/pass
- Motor/Speed Controlled: 2.5-5 gal/ft/pass
- Flushing Rate: 7.5-25 gal/ft/pass
Rotation Speed from 1 min per revolution ( 1 RPM) Adjustable from 2 min to 45 min per RPM, Up to 2 hours per rev for flushing.
SLIDE 24
Reduced Recirculation Possible
a) Current Recirculation Rate = 9 – 11 times in dry weather. b) Using 95 - 105 HP with 3 pumps. c) Possible reduced recirculation= 3 - 5 times. d) Proposed 25 to 45 HP with 1 or 2 pumps. e) Save 50-60 HP or 325,000 KW per year. f) At 15 cents/KW-hr, Save $49,000- $59,000 per year, est.
SLIDE 25
Resulting Improvements
i. Stainless steel
- ii. Increased control of the rotational speed,
- iii. Longer bearing life
- iv. Covered MCC relocated away from the Biotower
tank walls, Shaded, AC for hot days
- v. Space in the MCC for future installation of
controls for a blower or other process
- vi. Provisions in the MCC for connection to SCADA.
SLIDE 26
Proposed Timeline and Milestones
- November 2017: Notice to Proceed
- December 2017: Major Equipment Submittals (in
process now)
- January 2018, MCC Submittal and Minor submittals,
Mobilization, Tree Removal, Grading, Prep for Concrete
- Late February 2018: Biotower Mechanism
- March 2018: Biofilter Mechanism
- April 2018: Valves and Pipework
- May 2018: MCC installation
- June 2018: Testing, Tuning and Project Close-out.