Decision on Generator Project Downsizing Keith Johnson Manager, - - PowerPoint PPT Presentation

decision on generator project downsizing
SMART_READER_LITE
LIVE PREVIEW

Decision on Generator Project Downsizing Keith Johnson Manager, - - PowerPoint PPT Presentation

Decision on Generator Project Downsizing Keith Johnson Manager, Infrastructure Policy Board of Governors Meeting General Session September 13-14, 2012 Interconnection customers have requested additional opportunities to reduce the size of


slide-1
SLIDE 1

Decision on Generator Project Downsizing

Keith Johnson Manager, Infrastructure Policy Board of Governors Meeting General Session September 13-14, 2012

slide-2
SLIDE 2

Interconnection customers have requested additional

  • pportunities to reduce the size of their projects.

Page 2

  • Under current process, generator projects may be unable

to downsize due to material impacts on later queued projects

  • In such cases, the interconnection customer may be

forced to withdrawal from interconnection process

  • To address this situation, the ISO has developed an

additional downsizing opportunity

slide-3
SLIDE 3

The downsizing proposal includes the following key features.

Page 3

  • Open to any generator project in Cluster 4 or earlier
  • No limit on amount of downsizing
  • Can downsize for any reason
  • One-time window to submit requests
  • $200,000 deposit to cover study and administrative costs
  • Requires mitigation of impacts on later queued projects
  • Projects electing to downsize give up suspension rights
slide-4
SLIDE 4

There is broad support for the proposal, but some stakeholder concerns remain.

  • That proposal should include a second downsizing

request window

  • That interconnection customer should not have to

give up ability to temporarily suspend work if it exercises downsizing option

Page 4

slide-5
SLIDE 5

Management recommends Board approval.

  • Allows interconnection customers to reduce size of

projects and proceed with development

  • Allows ISO to evaluate collective impacts of downsizing

requests all at once in orderly and efficient manner

  • Works in conjunction with other ISO initiatives and

contributes to ISO’s queue management effort

  • Stakeholders largely support proposal

Page 5