CUI Seminar Stavanger, 07-06-18 UK HSE, Energy Division Chris - - PowerPoint PPT Presentation

cui seminar
SMART_READER_LITE
LIVE PREVIEW

CUI Seminar Stavanger, 07-06-18 UK HSE, Energy Division Chris - - PowerPoint PPT Presentation

CUI Seminar Stavanger, 07-06-18 UK HSE, Energy Division Chris Scales ales CEng MIMMM SenM nMWeldI eldI HSE Energy gy Division ision - Offshor ore e Spec ecial ialist ist Inspec pector tor - Material ials and Corrosion on Energy


slide-1
SLIDE 1

CUI Seminar Stavanger,

07-06-18

UK HSE, Energy Division

Chris Scales ales CEng MIMMM SenM nMWeldI eldI HSE Energy gy Division ision - Offshor

  • re

e Spec ecial ialist ist Inspec pector tor - Material ials and Corrosion

  • n
slide-2
SLIDE 2

Energy Division – Topic Specialists

slide-3
SLIDE 3

How we Regulate Tools we use What we find What we are doing/What is happening

slide-4
SLIDE 4

UK Legislation – Goal Setting Regime

Health and Safety at Work (etc.) Act, 1974 – General duty towards employees and non-employees (contractors). Management of Health and Safety at Work Regulations, 1999 Offshore Installations (Prevention of Fire and Explosion, and Emergency Response) Regulations, 1995 Offshore Installations and Wells (Design and Construction etc.) Regulations, 1996 The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015

How We Regulate

slide-5
SLIDE 5

Piper Alpha – Safety Case Regulations

A central recommendation of the Cullen enquiry; Every operator/owner of an offshore installation must prepare and submit a Safety Case to the Regulator (HSE) for acceptance. The Safety Case must identify all risks with the potential to cause a major accident, and describe the processes in place to reduce them to a level which is as low as reasonably practicable (ALARP). The Safety Case is assessed and may be accepted by the Regulator. Every operator/owner must have an accepted Safety Case for each installation they operate.

slide-6
SLIDE 6

Safety Cases, Inspection and Goal Setting

Operators must comply with their accepted Safety Case, which means… do what they said they were going to do! HSE Inspectors ensure by inspection that operators are doing what they said they were going to do in their accepted Safety Case, to control risks. The goal set is to identify, reduce and manage risks. The means by which operators achieve this is up to them. How does this relate to CUI…?

slide-7
SLIDE 7

Regulating - CUI

  • Inspect and assess

CUI management strategy,

  • nshore
  • Inspect and assess function
  • f strategy offshore.

Inspect plant.

  • Enforce where we identify a

risk gap or non-compliance.

  • Achieve sustained

compliance.

slide-8
SLIDE 8

Tools we use;

Provision and Use of Work Equipment Regulations, 1998

Regulation 5 (1) – Maintenance Every employer shall ensure that work equipment is maintained in an efficient state, in efficient working

  • rder and in good repair

Regulation 6 (2) (a) – Inspection Every employer shall ensure that work equipment exposed to conditions causing deterioration which is liable to result in dangerous situations is inspected— (a) at suitable intervals

Legislation

slide-9
SLIDE 9

Guidance

Energy Institute; “Guidance for Corrosion Management in Oil and Gas production and Processing” – specific section on CUI HSE; “HSG 65, Managing for Health and Safety” – Plan, Do, Check, Act. EFC 55 (Revised); “Corrosion Under Insulation (CUI) Guidelines” HSE, SPC/Tech/Gen/18 – “Corrosion under insulation of plant and pipework v3” (available on HSE website). HOIS Document (16)R2 Issue 01– “HOIS Guidance for in-situ inspection of corrosion under insulation (CUI)” – guidance on effectiveness of NDT techniques.

Tools we use;

slide-10
SLIDE 10

What we find

New module Original vessel, insulation found waterlogged. Replaced with new – 18 months old. Example 1

slide-11
SLIDE 11

Example 2 8” flowline, 30 bar, 80°C, 18.3mm nominal WT, insulation looked OK. Measured down to 6.8mm

What we find

slide-12
SLIDE 12

What we find

Example 3 Quality/Workmanship…or not!

slide-13
SLIDE 13

Example 3 continued…

What we find

Poor quality Lack of awareness/understanding

slide-14
SLIDE 14

What we find

These examples raise the question, “Why does the operator not know what they are getting?” In many cases Fabric Maintenance, including insulation removal, reinstatement and application is contracted to a 3rd Party. The “Intelligent Customer” should know what they require, why they require it and if they are getting it. …management of sub-contract work. Training and recognised standards in applying insulation is lacking in the UK sector, and will be a focus going forward.

slide-15
SLIDE 15

Incident occurred late 2015. Corroded, insulated 8” pipe. High pressure gas. Ongoing.

What we find

Example 3 This incident, together with increased HSE focus on CUI, appeared to have prompted renewing of strategies, increased resource and Leadership Commitment across the UKCS.

slide-16
SLIDE 16

What we find

A significant proportion of assets on the UKCS are operating close to, or beyond their original design lives. Often, installations have been owned and run by a number of Operators and as a result, in many cases historical information is missing or no longer accurate. The location or extent of insulation, inspection history, history of physical change or changes to the process do not reflect the current status, meaning that effective management is not possible without a substantial re-baselining exercise. In many cases, operators are coming from a position of ‘catch up’, following periods of mismanagement or neglect, sometimes by previous

  • wners. Extensive re-baselining is necessary to establish status.
slide-17
SLIDE 17

What we find

4”, 20 Bar fuel gas line pinhole leak – outboard, difficult access, never stripped for inspection. Not reported, rather than reported as “not inspected”. Inadequate reporting process, poor supervision and lack of audit of inspection activities…RBI scheme. Example 4

slide-18
SLIDE 18

What we find

From Example 4

  • The Operator acknowledged historic failings in the CUI

management programme that led to the failure.

  • Stripped and inspected 60% of Hydrocarbon containing pipework
  • ver approximately 2 month period. Further findings….
  • Took the opportunity to

review historical data, reset their understanding of the status of insulated systems and update CUI management strategy.

slide-19
SLIDE 19

What we find

Example 5 The Operator was told, and reminded, but just did not inspect.

slide-20
SLIDE 20

What we find

Common Enforcement

  • Damaged or poorly applied/reinstated insulation.
  • Insulation removed for inspection and not restored or partially

restored, leaving open ends.

  • Lack of historic information, inaccurate data, uncertainty over

status.

  • Failure to inspect.
  • Inadequate management strategies; stripping only at

anomalies, visual inspection.

  • No consideration of risks associated with removing insulation.
slide-21
SLIDE 21

What we are doing/ What is happening

  • HSE works with industry groups to provide the

Regulator’s viewpoint and assist in developing guidance and techniques, e.g. HOIS, Energy Institute.

  • HSE is looking to initiate the reformation of the UK CUI

Forum, which includes offshore, onshore industries including those outside oil and gas, e.g. nuclear.

  • HSE is planning a project to gather and analyse data
  • n CUI incidents/failures/enforcement that we hold,

but possibly with additional outreach to industry.

  • Establishing and maintaining links on technical issues

with other regulatory bodies such as PSA, as well as at the International Regulator’s Forum (IRF).

slide-22
SLIDE 22

SD (formerly HSL)

Health and Safety Laboratory – expertise and facilities to perform a wide range of Testing, analysis and research work.

slide-23
SLIDE 23

What we are doing/ What is happening

Inspection Focus – Risk Based Inspection (RBI) HSG 65; Plan, Do, Check, Act

slide-24
SLIDE 24

What we are doing/ What is happening

  • Understanding what you have (where the insulation is and

condition, actual process parameters etc.)

  • Developing an effective CUI management strategy/identify risks

Getting the basics right;

  • Implement the Strategy
  • Inspection with effective repair – quality, assurance, awareness
  • Measure/analyse data (failures, near misses, anomalies)
  • Review strategy
  • Implement changes as required

Plan Do Check Act How many incidents/anomalies, how much remedial work and resource could be saved if the basics were carried out fully and effectively?

slide-25
SLIDE 25

What we are doing/ What is happening

Energy Institute - Guidance – Revised edition soon to be

issued…..updates since 2008 focus on the following areas;

– key differences between carbon steel and Corrosion Resistant Alloys (CRA) – timing for thorough inspections typically range from 5 – 20 years – insulation removal is still the most effective form of thorough inspection – predictability and definition of prone areas – suitability of Non-Intrusive Inspection (NII) techniques – limitations of probability assessment – the pitfalls to avoid – consideration for live equipment insulation removal – permanent and partial permanent removal of insulation – increased rupture threat for under-inspected carbon steel

slide-26
SLIDE 26

What we are doing/ What is happening

Oil and Gas Technology Centre (OGTC) – UK Government Funded

  • An open call for ideas to provide solutions for solving

CUI issues, under the headings;  Predicting  Detecting  Inspecting  Mitigating

  • Funding is available to develop the most promising
  • ideas. Submission window recently closed.
slide-27
SLIDE 27

What we are doing/ What is happening

HOIS – Industry JIP concerned with NDT “Guidance for in-situ inspection of Corrosion Under Insulation (CUI) “ – this is a confidential document to HOIS JIP participants. Further NDT trials are about to begin in June, part funded by OGTC, including;

  • New variants of PEC
  • Realtime radiography
  • Guided wave

This should lead to a substantially revised document which will be publicly available.

slide-28
SLIDE 28

Conclusions

  • The regulatory challenge is to ensure CUI management strategies

are effective and fully implemented, enforcing legislation where risk gaps are identified and holding operators to account where negligence can be demonstrated.

  • During the Lifecycle, insulation has to be installed, removed and

reinstated – emphasis must be placed on quality of materials/design, competency of personnel, heightened awareness and culture.

  • Current NDT techniques may best be used in combination as

a screening tool but need to be demonstrated to be effective for this purpose.

  • Accuracy and completeness of information gathered and used

in building a CUI management strategy is vital to its success. All parameters need to be considered.

slide-29
SLIDE 29

Conclusions (2)

  • No single or combination of NDT techniques currently available can

provide sufficiently detailed information of a high enough confidence to negate the need for visual inspection.

  • Stripping and visual inspection of insulated process equipment remains

the most reliable way to find and assess the extent of CUI.

  • By engaging with, educating and raising the awareness of the workforce,

this large resource could be more effectively used to;

  • Report instances of evidence of CUI.
  • Report evidence of damaged/compromised insulation.
  • Avoid damage to insulation.
slide-30
SLIDE 30

Tusen Takk. Questions?